Report to: General committee Report
Date:
SUBJECT: Award of Tender # 071-T-09 2009 Relining of Cast Iron and Ductile Watermains
PREPARED BY: Ernie Ting, Ext: 3650
David Huynh Ext: 2400
Patti Malone Ext: 2239
RECOMMENDATION:
1) THAT the report entitled “Award
of Tender # 071-T-09 2009 Relining of Cast Iron and Ductile Watermains” be received;
2)
3)
4)
5)
EXECUTIVE SUMMARY:
Not Applicable.
The purpose of this report is to award the contract for 2009 Relining of Cast Iron & Ductile Iron Watermains.
A 20-year program to
cement line cast iron and ductile watermains was approved and adopted by
Council in 1997 to improve the water quality due to internal corrosion. The Town of
The 2009 cement
relining plan will occur on the following streets: Main Street Unionville,
Approximately 3.6 of
watermains will receive cement relining in 2009. It is estimated that the
remaining 11.4 km of unlined watermains will be completed by 2012.
Cement relining program extends the life expectancy of the watermains and results in:
· Restoring water quality to meet the Ontario Ministry of Environment Drinking Water Quality Standards.
· Reducing in cost of watermains rehabilitation and replacement.
· Enhancing watermain life expectancy to +50 years.
· Improving supply capacity (better water flow) for domestic usage and fire demand.
· Minimizing unnecessary disturbance and inconvenience to water customers.
Not applicable
Advertised, place and
date |
ETN |
Bids closed on |
|
Number of contractors
picking up bid documents |
5 |
Number of contractors
responding to bid |
4 |
DETAILED PRICING INFORMATION:
Company |
Total Price, Excl GST |
Fer-Pal Construction Ltd. |
$ 948,891.49 |
Spinello
Companies |
$1,067,622.00 |
Main
Rehabilitation Co Ltd |
$1,067,787.00 |
The low bidder ($43,648.49 or 4.5% less than
the recommended proponent) on bid opening was disqualified after review of bid. The bidder was disqualified on the basis that
they did not meet the mandatory requirements and therefore, was non-compliant with the requirements of the Tender
(including the Town’s General Terms
and Conditions and
Based on similar unit items in the 2008 contract, the pricing has decreased by an estimated amount of 7% due to favourable pricing received from the vendor.
The bid documents have been verified for accuracy and compliance with the tender specifications and staff are satisfied that all terms, conditions and bid prices comply with the Town’s requirements.
The following
table is a summary of the financial considerations for this report: |
||||
Original Budget and Account # |
|
$1,200,000 |
|
053-6150 -9285-
005 Cement Relining Iron Watermain |
Current Budget Available (unspent) |
|
$1,200,000 |
|
|
Less Cost |
|
($948,891) |
|
Awarded
to Fer-Pal Construction Ltd. |
Less Contingency |
|
($94,889) |
|
|
Budget Remaining |
|
$156,220 |
|
|
Upon completion of the project the remaining funds shall be returned to the original funding source. Note: The contract will be managed by internal staff. Therefore, no external contract administrative fees are required.
Not applicable
Not applicable
This report is consistent with the
following:
Infrastructure Management
To build, renew and strategically
manage the Town’s infrastructure to meet the demands and expectations of the
growing community.
Fiscal Stewardship
To ensure that resources are managed responsibly and taxpayers receive the best value for their money.
· Purchasing - Be part of the tendering and award process. Upon receipt of the signed report, Purchasing will initiate the execution of Purchase Orders for the Contract.
· Communication and Community Relations – Residents to be informed of the project schedule and work to be done on each street.
· Fire & Emergency Services– To be informed of limited fire flow during construction.
RECOMMENDED
BY: ________________________ ________________________
Jerry Klaus Peter Loukes
General
Manager,
________________________
Brenda Librecz
Commissioner, Community
& Fire Services
· 2009 Cement Relining of Cast Iron and Ductile Watermains – Project Locations