Report to: General Committee Report
Date:
SUBJECT:
PREPARED BY: Max Stanford, Project Manager, Asset Management
RECOMMENDATION:
1)
THAT
the report entitled “Varley Art Gallery of Markham Expansion” be received.
2)
AND
that
3)
And
that Site Plan Approval be delegated to the Director of Planning or her
designate.
4)
AND that Staff be authorized and directed to do all things necessary to
give effect to this resolution.
The purpose of this report is to advise Council of the
progress achieved on the preliminary design, the result of a public meeting
held to seek feedback on the preliminary design and to request authorization to
direct the Architect to complete the design and proceed to tender.
On
The Architect was further instructed to research the possibility of having
the design for the expansion meet LEED standards.
The cost for the project was estimated at $2.58M, which is funded in
large part by donation of $1.56M from Mr. Wallace Joyce to the Varley McKay Art
Foundation of
Further to Council’s
Design features incorporated into the preliminary design are:
-
An
addition that is integrated with the design of the existing building
-
An
addition of 1205 square feet of display area in the gallery.
-
An
addition of approximately 1100 square feet of second floor office space with an
“Open Design” concept to maximize functionality and flexibility.
-
A
design for the expansion that incorporates a LEED SILVER standard. A Silver Certification cannot be attained due
to the design of the existing structure, but all efforts to achieve a Silver
Standard are being made in the expansion.
Some of the targets being investigated are: Storm Water Management,
Green Roof, landscape design, upgrade of glazing, Building Envelopes, and review
of CFC use.
-
A landscape design that will satisfy the requirements
of the
The Landscape Architect Kenneth Hoyle and Staff met with
Staff is expecting to report back to Council in mid-September with
tender results and recommendations for award of contract.
The total project
cost and 2009 budget is $2.58M as detailed in table below. An updated cost estimate indicates that
projected costs are within budget.
Expenditures |
|
Construction |
$1,850,000 |
LEED (10% of the construction cost): |
$ 185,000 |
Fees and Internal Costs
including Architect and Project Management costs (15% of
Construction/LEED) |
$ 305,000 |
Contingency (10% of
Construction/LEED) |
$ 205,000 |
Cost balance of Study (2008) |
$ 40,000 |
Total Expenditure |
$2,585,000 |
|
|
Funding |
|
Wallace Joyce-Varley McKay Art Foundation |
$1,491,083 |
Interest (2008 estimated) –Varley McKay Art
Foundation |
$
70,000 |
Town of |
$ 923,917 |
Varley Foundation fundraising |
$ 100,000 |
Total Funding |
$2,585,000 |
Operating costs of $13,000 for heat, light and hydro on a larger building will be offset by earned programme revenue.
Planning and Development Service (Heritage)
RECOMMENDED
BY: ________________________ ________________________
Steve Andrews, P.Eng. John Ryerson
Director, Asset Management. Director, Cultural Services.
________________________
Brenda Librecz,
Commissioner, Community
and Fire Services
Attachment ‘A’ –
by
Q:\Commission
Share\Operations and Asset Management\Reports\2009\Asset Management\Varley Art
Gallery Report\Committee Report.doc