Report to: General Committee                                                          Report Date: May 1, 2009

SUBJECT:                     Contract Award 039-T-09 Markham Fire Station No. 93 (Cathedral) Construction

PREPARED BY:          Henry Tse, P. Eng., Project Manager

 

RECOMMENDATION:

 

1)   THAT the report titled “Contract Award 039-T-09 Markham Fire Station No. 93 (Cathedral) Construction” be received; and,

 

2)   THAT staff be authorized to award contract 039-T-09  to the lowest priced qualified bidder Devlan Construction Ltd for the construction of Fire Station #93 located at Major Mackenzie Drive and Woodbine Avenue, in the amount of $2,998,000.00 exclusive of GST;  and,

 

3)   THAT the Architectural/Engineering Services fee for Thomas Brown Architects be increased by $132,750 primarily to account for the non-repeat design of the fire station as well as costs associated with targeting the project to achieve LEED Gold Certification; and

 

4)   THAT a contingency amount of $299,880.00, exclusive of GST, be established to cover any additional construction costs,  and that the Director of Asset Management, or his designate, be authorized to approve the expenditure of this contingency amount up to the specified limit in accordance with the Town’s Expenditure Control Policy; and,

 

5)   THAT staff be authorized to retain external project management resource for the construction phase of Fire Station No. 93 (Cathedral), at an upset limit of $120,000 and in accordance with the Purchasing Bylaw; and,

 

6)   THAT the awards be funded from the Fire Station No. 93 (Cathedral) project budget account 067-5350-7710-005  

 

7)   THAT the required additional $593,268.00 be funded from the Development Charges Reserve; and further,

 

8)   THAT staff be authorized and directed to do all things necessary to give effect to this resolution;

 

 

PURPOSE:

The primary purpose of this report is to seek Council’s approval to award the construction contract to Devlan Construction Ltd for the construction of Markham Fire Station #93 (Cathedral).  This report also seeks Council’s authorization to increase the Architectural and Engineering Services fee to Thomas Brown Architects.

 

 

 

 

 

BACKGROUND:

The Unionville Sub-committee of Council adopted, in part, the following resolution at their May 21, 2008 meeting:

            That the Unionville Subcommittee is in support of the three-dimensional schematic design of the proposed sloped roof elevation for the West Cathedral Fire Station as presented by Thomas Brown Architect’s at the May 21, 2008 Unionville Subcommittee meeting;”

Council adopted by resolution at their June 24, 2008 meeting:

“That staff be directed to develop the detailed design and technical specifications with the target of achieving the certification level of LEED Gold”

 

Detailed design drawings and technical specifications were produced accordingly.  Tender for the construction phase of the project closed on April 24, 2009.

 

OPTIONS/ DISCUSSION:

Prequalification

Due to the scope of the project, contractors were pre-qualified to ensure that all bidders would have the necessary qualifications, experience and resources to complete the works within the project timelines.  The prequalification package was issued in accordance with the Purchasing By-law 2004-341.

PREQUALIFICATION INFORMATION

Advertised, place and date

(ETC) Nov. 25, 2008

Prequalification closed on

Dec. 12, 2008

Number of contractors picking up bid documents

39

Number of contractors responding to bid

20

Number of contractors prequalified

6

 

Construction Tender

The construction tender # 039-T-09 was issued in accordance with the Purchasing By-law 2004-341.  Asset Management and Purchasing staff and the Architectural/Engineering Consultant have reviewed the bid documents and are satisfied that all terms, conditions, bid prices and specifications comply with the Town’s requirements.  The tender results are summarized below:

BID INFORMATION

Tender release

March 31, 2009

Bids closed on

April 24, 2009

Number of contractors picking up bid documents

6

Number of contractors responding with valid bid

 5

 

 

 

 

 

 

DETAILED PRICE INFORMATION:

 

Contractors

Bid Price

1

Devlan Construction Ltd

 $   2,998,000

2

Pre-Eng Contracting Ltd.

 $   3,090,000

3

J.J. McGuire General Contractors Inc.

 $   3,179,000

4

Gay Company Ltd.

 $   3,190,000

5

Gateman-Milloy Inc.

 $   3,230,000

 

 

Tender prices submitted fall within a tight range, see summary above.  The lowest bidder, at $2,998,000 exclusive of GST, is Devlan Construction Ltd.  The Town’s retained Project Architect advised that he had worked satisfactorily with this contractor on a similar project previously (within the past 5 years).  Staff recommends that Council authorizes the award of the construction contract to this contractor.

 

The original approved project was to utilize a repeat architectural design that was used for the recent Bur Oak Fire Station project.  The Town’s Architectural Consultant estimated a corresponding construction cost of $2.7 m. in 2007.  Since then Council has selected a design that is more consistent with the built-form of the surrounding neighbourhood.  In support of the progressive ideal of sustainable design, Council also authorized staff to target this project to achieve the LEED Gold certification level, with the inclusion of a ground-source heating and cooling (geothermal) system. 

 

Prior to tendering, a cost consultant was retained to provide an estimate of the construction cost of the project.  Based on typical mid-range costs, rather than a prediction of low bid, the consultant estimated a value of $3.678 m, exclusive of GST.  The Town’s retained Architectural Consultant advised that it is reasonable to expect a tender result in the range of $3.5 m to 3.7 m.  The tender result represents an excellent competitive process.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FINANCIAL CONSIDERATIONS AND TEMPLATE:

 

COST SUMMARY

 

Land

Building

Design Fees

Other Fees

FF&E

Total

Budget for Cathedral (A)

  741,000

     2,400,000

     150,500

       249,500

      363,500

      3,904,500

 

 

 

 

 

 

 

Actuals:

 

 

 

 

 

 

Land

  409,018

 

 

 

 

         409,018

Construction

 

     2,998,000

 

 

 

      2,998,000

Construction Contingency

 

        299,800

 

 

 

         299,800

Design Fees (Repeat Design)

 

 

     135,000

 

 

         135,000

Design Fees (Energy Modelling)

 

 

       15,500

 

 

           15,500

Additional Design Fees (non-repeat design)

 

 

       45,000

 

 

           45,000

Additional Design Fees (security system, cost report, green funding)

 

 

       15,250

 

 

           15,250

Additional Design Fees (LEED Gold design, Admin & Registration)

 

 

       62,500

 

 

           62,500

Additional Design Disbursements

 

 

       10,000

 

 

           10,000

Other Engineering Consultant Costs

 

 

 

         24,200

 

           24,200

Project Management consultant fee (construction phase)

 

 

 

       120,000

 

    120,000 

FF&E expected

 

 

 

 

      363,500

         363,500

Total Actuals & Forecast (B)

  409,018

     3,297,800

     283,250

       144,200

      363,500

      4,497,768

 

 

 

 

 

 

 

Budget Variance (A-B)

  331,982

      (897,800)

   (132,750)

       105,300

                -  

       (593,268)

 

There is a favourable variance in the actual land purchase cost as a result of an OMB settlement with the developer, at a rate far below market value.

 

The original approved construction cost component of the project, $2.4 m, was based on the previous Bur Oak Fire Station No. 98 that was approved in 2004.  Based on established industry cost adjustment factors, this amount would escalate to $3.36 m in 2009 value.  Note that the scope of work included for the Bur Oak project did not include features and cost to achieve the LEED Gold certification level.  In June 2008, the Town’s Architectural Consultant presented to Council the estimated additional construction cost for the present Fire Station 93 (Cathedral) project to achieve LEED Gold certification level to be $255,000.  The tender result of $2.998 m actually represents an excellent competitive price. The Town will be designing and certifying a LEED Gold building.

 

There is a provision for retaining a project management consultant for the construction phase of the project.  In-house workload necessitated this need.

 

 

 

PROPOSED FUNDING SOURCES:

Fire stations are 100% funded from Development Charges.  Staff recommends to provide the remaining funding for the project from the Development Charges account.

 

ENVIRONMENTAL CONSIDERATIONS:

The design of the Markham Fire Station No. 93 (Cathedral) incorporates sustainable and environmentally friendly features, including a ground source heating and cooling (geothermal) system.  The project will pursue the LEED Gold Certification level.

 

ACCESSIBILITY CONSIDERATIONS:

The facility has been designed in accordance with all requirements of the Ontario Building Code as well as the current (2007) Accessibilities Guidelines of the Town.

 

ENGAGE 21ST CONSIDERATIONS:

The project aligns with the following Town of Markham corporate goals:  Infrastructure Management, Economic Development, Quality Community and Environmental Focus.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Fire Services

Real Estate Services

Financial Services

 

 

 

 

__________________                                                _____________________

Bill Snowball                                                                Steve Andrews, P.Eng.

Fire Chief,                                                                    Director,

Fire & Emergency Services                                           Asset Management

 

 

 

 

________________________                                   

Brenda Librecz                                                              

Commissioner,                                                             

Community and Fire Services                                       

 

 

 

 

 

Q:\commission share\operation & asset management\reports\2009\asset management\Cathedral Fire Station FS 93 GC Report – Tender Award - 2009-05-15.doc