Report to: General Committee Report
Date:
SUBJECT: Award of Tender 159-T-09 Centennial Community Centre Pool Renovation
PREPARED BY: Dennis Riggs, Tel. (905) 294-6111 Ext. 224
Tony Casale, Ext. 3190
RECOMMENDATION:
1) That the report entitled “Award of Tender 159-T-09 Centennial Community Centre Pool Renovation” be received;
2) And That the contract for 159-T-09 Centennial Community Centre Pool Renovation be awarded to BWK Construction Company Ltd, the lowest priced bidder in the amount of $405,300.00 inclusive of PST and exclusive of GST;
3) And That a separate purchase order in the amount of $40,530.00 exclusive of GST be issued for contingency to cover any additional fees and that the Director of Recreation be authorized to approve expenditure of this contingency amount up to the specified limit in accordance with the Expenditure Control Policy;
4) And That the award be funded from the 2008 Recreation Department Capital Project 500-101-5399-8074 Centennial CC – Pool Acoustical Material Replacement in the amount of $387,933.96;
5) And That the shortfall be funded from account 500-101-5399-8077 Centennial CC - Rink seating replacement in the amount of $57,896.00;
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
The purpose of this report is to obtain Council approval to award the Centennial Community Centre Pool Renovation.
The acoustical material in the pool area at the Centennial Community Centre is over 30 years old on the ceilings and 20 years old on the walls. The normal life expectancy is in the area of 15 years. The material has blackened to the point that it has a dirty appearance creating an unacceptable environment to the patrons. The darkening effect has resulted in lower lighting levels. Pieces of the material have also been falling down periodically over the last several years onto the deck or in the pool. The existing material cannot be painted or cleaned.
This project involves removing the acoustical material on the walls and ceilings and replacing it with a green, approved acoustical boarding that can be painted and/or cleaned while maintaining the same acoustical values currently present in the facility. A PVC membrane will secure the membrane below the roof deck to give the ceilings a smooth look. The scope of work includes painting of all trusses and exposed roof decking.
OPTIONS
/ DISCUSSION:
Due to the scope of the project,
contractors were pre-qualified to ensure that all bidders had the necessary
qualifications, experience and resources to complete the work in accordance
with the Town of
Pre-qualification
Details
Advertised |
ETN |
Bids closed on |
|
Number of Contractors picking up the bid
document |
70 |
Number of Contractors responding to bid |
18 |
Number of contractors
pre-qualified |
11 |
Tender # 159-T-09 was issued in accordance
with
Advertised |
Pre qualified Bidders |
Bids closed on |
|
Number of pre qualified bidders |
11 |
Number responding to bid |
8 |
Company |
Prices
(excluding GST) |
BWK Construction Company
Ltd |
$405,300.00 |
P & C General Contracting Ltd. |
$426,015.00 |
|
$482,240.00 |
Brown Daniels Associates Inc. |
$503,492.85 |
Garritano Bros Ltd. |
$512,400.00 |
J.D. Strachan Construction Limited |
$514,680.00 |
Mady Contract Division Ltd. |
$543,000.00 |
M.J. Dixon Construction Limited |
$583,000.00 |
The work for this
project shall commence on
The Centennial CC – Rink Seating Replacement account has a remaining balance of $186,754.00 which is sufficient to complete that project and to cover the shortfall in the Centennial CC – Pool Acoustical Material account in the amount of $57,896.00.
Not Applicable
Not Applicable
The
RECOMMENDED
BY: ________________________ ________________________
Glen Taylor Brenda Librecz
Acting Director, Recreation Commissioner, Community
Services & Fire Services