Report to: General Committee Report
Date:
SUBJECT:
PREPARED BY: Yanli Xu, Senior Stormwater Management Engineer, ext.2894
Phoebe Fu, Manager, Capital of Right-of -Way, ext.3010
RECOMMENDATION:
1) THAT the report entitled “West Thornhill Stormwater Remediation Class EA Study – Update” be received;
2)
AND THAT staff report back to General Committee with study
recommendations.
3)
EXECUTIVE SUMMARY:
Not applicable
The purpose of this report is to outline the next steps for West Thornhill Stormwater Flood Remediation Class B Environmental Assessment (Class EA) Study.
On
In response,
On
1) That the report entitled
“West Thornhill Stormwater Remediation Class EA Study – Project Update” be received; and,
2) That the presentation provided by Ms.
3) That the presentation provided by Ms.
4) That the deputations from Ms. Marilyn Ginsburg, on behalf of the
Grandview Area Residents Association, and Ms. Eileen Liasi, on behalf of the
German Mills Ratepayers Association at the June 2, 2009 Special Development
Services Committee meeting be received, and
5) That staff be directed to hold Public Information Centre (
6) That
Council confirm its position regarding the "#4 - 100 year level of
protection" subsequent to the announcement on the infrastructure grant
funding and the submission of a final recommendation of staff; and,
7) That
staff report back to General Committee with final recommendations on
8) That Staff be authorized and directed
to do all things necessary to give effect to this resolution.
As per Council resolution Item 6,
Council is to confirm its position
regarding the "#4 - 100 year level of protection" subsequent to the
announcement on the infrastructure grant funding. Following the
Staff will report back in the Fall
of 2009 with the Class EA recommendations.
Once the Council makes the decision on the level of protection, staff
will move forward to host the Public Information Centre #2 in the Fall of 2009. Subsequently, staff will report to the
Council with final recommendations and file the Class EA report in winter of
2009/2010.
Not applicable
Not applicable
This report is consistent with the Building Markham’s Future Together strategic priority on the “Environment” as it considers sustainability on the built environment.
Not applicable
RECOMMENDED
BY:
________________________ ________________________
Steve
Andrews Brenda
Librecz
Director,
Not Applicable