Report to: General Committee Date of
Meeting:
SUBJECT: Status of Capital
Projects as of
PREPARED BY: David Milenkovski, Senior Financial Analyst
RECOMMENDATION:
That the report
dated
That $1.21M from closed capital projects be transferred to the sources of funding as listed on Exhibit A; and,
That Staff be authorized and directed to do all things necessary to give effect to this resolution.
PURPOSE:
To inform Council about the status of capital projects as of
BACKGROUND:
CAPITAL PROJECTS TO BE CLOSED
There are 55 capital projects ($12.17M budget) recommended for closure. Of these, 41 projects were not fully spent, resulting in a total of $1.21M to be returned to the original sources of funding as listed in Exhibit A. The details by project are listed in Exhibit B. The remaining 14 projects, as listed on page 2 of Exhibit B, were fully spent.
STATUS OF OPEN CAPITAL
PROJECTS
The total capital budget for open projects at
Staff has conducted a compliance review on all open capital
projects. In accordance with the Capital
Budget Control Policy Section 4.1, projects that remain inactive for a period
of twenty-four months or longer are subject to closure. The non-compliant
projects were discussed and reviewed by the business units, of which a majority
of these inactive projects are being closed and are included in Exhibit A.
FINANCIAL
CONSIDERATIONS:
A detailed listing of capital projects with unexpended funds totaling $1.21M, to be closed upon approval of this report, is outlined in the following Exhibits:
EXHIBIT A - CAPITAL PROJECTS TO BE CLOSED
Exhibit A “Summary of Closed Capital Project Funding
to be Transferred” summarizes where the closed capital project balances will be
transferred;
Exhibit B (Page 1) “Closed Capital Projects – With
Funds to be Returned to Original Sources of Funding” provides a detailed
summary by project where the closed capital project balances will be
transferred;
Exhibit B (Page 2) “Closed Capital Projects – Projects
to be Closed and Fully Expended” outlines projects that have been 100% spent
and therefore have no balance to return to their original funding source(s).
Exhibit A summarizes the return of funds from the closed capital projects to the original sources of funding. In accordance with the Capital Budget Control Policy, the remaining funds from the closure of operating budget and life cycle replacement and capital reserve funded capital projects will be transferred to top up the capital contingency project to a maximum of $250,000. Exhibit A shows a transfer of $105,188 to top up the capital contingency project. Further closures of operating budget and life cycle reserve funded capital projects in the amount of $217,467 will be returned to the life cycle replacement and capital reserve. Therefore, the total amount being closed from projects that were originally funded by the operating budget and life cycle replacement & capital reserve fund is $322,655 ($105,188 + $217,467), as summarized on the bottom of Page 1 of Appendix B.
Similarly, there are
The remaining development charge funded projects in the amount of $807,074 will be returned to the DC reserve. Therefore, the total amount being closed from projects that were originally funded by the DC reserve is $826,275 ($807,074 + $19,201), as summarized on the bottom of Page 1 of Appendix B.
In summary, the net amount $1.21M as outlined in Exhibit A to be transferred back to the original sources of funding is as follows:
DCA $0.81M
Design DC Capital Contingency $0.02M
Total $1.21M
The majority of the projects listed on Page 1 of Exhibit B are projects that were completed within budget. Projects that were under spent will have the balance transferred back to the original source(s) of funding. There are various reasons for the projects listed not utilizing their entire budgets and the following are the reasons for some of the projects with larger variances;
Operations - Fleet
Project # 7516 – Corporate Fleet Replacement – Annual Program – Remaining
Budget of $158,331 : The amount spent was less than budgeted because of lower
prices obtained through the tender process on some vehicles, as well as a
condition assessment done on non-Fleet vehicles, which resulted in a reduction in
the number of replacements required.
Corporate Communications
Project # 8146 – Exterior Branding at Town Facilities – Remaining Budget
of $100,000 : This project has been deferred. This request was for a study to
re-brand all Town facilities but it was determined that the time and expense
required to re-brand the facilities would be excessive.
There are also two projects listed on Exhibit B, which had zero spending
and the following are the reasons for closing these projects;
Engineering
Project # 9298 – Birchmount Road Extension – Phase 1 (EA) – Remaining
Budget of $494,000 : This project will be completed by Developers.
Planning
Project # 7828 – Growth Summit – Remaining Budget of $25,000 : This
budget was set up to hold a Growth Summit in
Projects with over expenditures (or negative balances remaining) will be offset against other identified closed projects with the same funding source(s), as per guidelines established in the Expenditure Control Policy.
Page 2 of Exhibit B lists the projects that have been completed on budget and have no remaining funds to be transferred back to the original sources of funding.
STATUS
OF OPEN CAPITAL PROJECTS
As of
The following summarizes the status of open capital:
Open Capital $401.58M
Total Encumbered $175.46M 44%
Unencumbered/Uncommitted $226.12M 56%
This indicates that 44% of the total approved open capital project budget is encumbered.
These totals do not include the 55 capital projects recommended for closure in this report.
The
total encumbered of $175.46M includes commitments of $64.22M and expenditures
of $111.24M.
Commitments refer to purchase orders (
RECOMMENDED
BY: ________________________ ________________________
Barb Cribbett, Treasurer Andy Taylor, Commissioner
Corporate Services
ATTACHMENTS:
Exhibit A - Summary of
Closed Capital Project Funding to be Transferred
Exhibit B - Closed Capital Projects – With Funds
to be Returned to Original Sources of Funding & Projects to be Closed and
Fully Expended