Report to: General Committee Report
Date:
SUBJECT: Angus Glen Indoor Tennis Structure (RInC Fund) Update
PREPARED BY: Linda A. Irvine, Manager, Parks and Open Space Development, ext. 2120
RECOMMENDATION:
1) THAT the report entitled “Angus Glen Indoor Tennis Structure (RInC Fund) Update” be received;
2) THAT the conceptual site plan as presented herein for the Angus Glen Tennis Structure and parking lot be approved in principle;
3) THAT staff proceed with further detailed design work, preparation of working drawings, tendering, and tender award as required to insure that construction of this facility commences as soon as possible;
4)
THAT the tendering process be waived in accordance with
Purchasing By-Law 2004-341, Part II, Section 7, 1(b), Non Competitive
Procurement, where there is only one source of supply for the goods to be
purchased, and that Council authorize staff to negotiate a contract for the
supply and installation of a tension frame structure from Cover-All
5)
THAT staff seek confirmation from the Recreational
Infrastructure
6)
The purpose of
this report is to update General Committee on the status of the Angus Glen
Indoor Tennis Structure project that received Recreation Infrastructure
In September 2009, Council approved funding for three applications to the 2009 RInC Program. The projects included: Saint Roberts Artificial Turf and Bubble project; Indoor Tennis Courts at Angus Glen Community Centre & Library project; and, the Outdoor Civic Centre Skating Rink project.
The indoor tennis courts project at the Angus Glen Community Centre and Library includes:
·
Construction
4 tennis courts and running track
·
Construction
of a permanent structure over the facility
In addition, this
tennis facility will include washrooms, change rooms, storage rooms, all
appropriate lighting, heating and cooling and furnishings. The small clubhouse
will be comprised of an office, mezzanine meeting room, elevator and storage. The
consultant team that has been hired to complete the design, working drawings
and contact administration of the
Permanent Tension Frame Structure vs. Inflatable Air Structure or “Bubble”:
Staff reviewed a number of similar indoor
tennis facilities in the GTA including making a visit to a similar tension frame
structure at
Preferred
Supplier Recommendation:
Clause 5.6 of the RInC Contribution
Agreement relating to Competitive Process provides that the requirement for a
competitive process may be waived with prior written approval by the RInC
Program in
Only five companies from across
Consequently, staff recommends that
Cover-All
Conceptual
Site Plan and Additional Parking:
Attached is a conceptual site plan (Figure 2) of the indoor tennis structure showing it located behind the Angus Glen Community Centre and Library on a portion of the existing parking lot to the edge of the completed soccer field. Orienting the structure north-south is space efficient, permits it to be as low as possible on the site, takes economical advantage of the existing sloping grade across the site, and allows for the construction of a parking lot immediately to the east of the new facility to serve the community park as well as the tennis courts. While some parking spaces will be removed at the existing westerly parking lot, no net loss of parking will result with the construction of the new parking lot to the east. The small clubhouse facility will be a two storey structure that can be entered from the existing parking lot at the mezzanine level, and at the lower level from the new parking lot.
Compatibility
with the Angus Glen Community Centre and Library:
The clubhouse facility and tennis structure will be designed to be as compatible as possible with the existing architecture of the Angus Glen Community Centre. This will be done by choosing similar building materials and building colors whenever possible. Landscaping, paving, site furnishings and exterior walls will also be designed to be compatible and complimentary to the community centre.
This award will be
funded from the
As part of staff’s analysis, two quotes were received, one from an air structure and another from a tension frame structure manufacturer even though these products and the services provided are not entirely the same nor are they directly comparable. Not surprisingly, there is, however, a cost premium of about 10%- 15% for frame structures over air structures. A frame structure of the size proposed (with footings but excluding heating and cooling) will cost approximately $500,000. An allowance has been requested of $250,000 to cover any additional costs for mechanical, electrical, HVAC, and other ancillary components that are integral to the structure.
Furthermore, there will be annual operational cost savings (of about $20,000) with a tension frame structures because it does not have to be taken down, stored and put back up each year. These annual cost savings will more than compensate for slightly higher initial product costs over the life time of the product.
The Purchasing, Finance and Recreation Departments have been consulted in the preparation of this report.
ATTACHMENTS:
Figure 1:
Photograph of “Cover-All” Structure at
Figure 2: Location
of Proposed Indoor Tennis Facility in
Figure 3: Conceptual Site Plan of the Proposed Indoor Tennis Facility
RECOMMENDED
BY:
________________________
Ronji Borooah
Town Architect
________________________
Glen Taylor
Acting Director, Recreation
________________________
Jim Baird
Commissioner, Development Services
Q:\Development\Design\linda\Parks\Angus Glen Tennis Structure update report Nov. 16.doc