Report to: General Committee Date
Report Authored: December 2, 2009
SUBJECT: Thornhill Community
Centre & Library Expansion & Renovation Project
PREPARED BY: Glen Taylor,
Acting Director of
RECOMMENDATION:
1)
THAT the report and presentation titled
“Thornhill Community Centre & Library Expansion & Renovation Project”
be received;
2)
3)
4)
5)
The purpose of
this report is to update Council on action items coming out of the October 19,
2009 General Committee meeting, seek council approval to proceed with tender
release, to delegate site plan approval to staff, and to inform Council about
developments that have the potential to impact overall project budget.
The Town of
Thornhill Community Centre is a multipurpose facility serving
The expansion and renovation of the
The Library and
-
Allocation for a space for
nursing mothers
-
An additional children sized
washroom stall in the basement women’s washroom
-
Signage installed at tender
award to advise of landscape plans to mitigate concerns raised by the required
removal of trees
-
Appropriate and adequate
lighting
-
Mitigation of any obtrusive
lighting in glass dome
-
Accessibility considerations,
including review by the Accessibility Advisory Committee
-
Review of exterior glazing
using FLAP
-
Review of the new south east
entrance addition roof design
-
Future renderings of the new
entrance will include trees in the area.
The following will be investigated:
-
Additional trees and
landscaping
-
Investigate the use of Cycling
Studio and associated equipment as an energy source including battery back-ups
The Additional Design
Review Processes will include:
-
FLAP review of proposed
construction activities with respect to mitigating bird injuries
-
Plans submitted to
Accessibility Advisory Committee for review
Given the feedback of Council and staff,
and the tight timelines required, it is recommended that the project proceed to
tender release with the fore mentioned feedback reflected within the tender
release documents.
Due to the tight
schedule associated with this project and that this project involves a very
small existing building footprint increase, site plan approval should be
delegated to staff. This will
significantly decrease the amount of time required to obtain site plan
approval, thus decreasing the risk that this project will not be completed by
the
Through
preliminary work, there have been developments that have the potential to
impact the overall budget including asbestos removal, and compliance with
Ontario Building Code. Given these
potential budget impacts, it is recommended that the library elevator extension
be included in the design but priced separately.
COMMUNICATION
PLAN:
Signage and project design boards will be
placed in the community centre. An
Infrastructure Fair will occur in January on all projects as well as a ground
breaking will be planned for February / March subject to input by all three
levels of government.
Timeline:
·
General Contractor Prequalification
- December 2009
·
Tender - January / February
2010
·
Construction Commences-
February / March 2010
·
Project Completion -
FINANCIAL
CONSIDERATIONS:
At this stage of the project, the cost
estimate is approximately 7% above the project budget of $6M. Items will be separately costed in the tender
document so that when the tender closes the report to Committee will identify
options to keep within the $6M budget.
The cost estimate includes a 10%
construction contingency to address any issues that may occur during
construction as a result of this being an existing older building.
Not Applicable
The Thornhill
Community Centre and Library Infrastructure Renovation Project objectives
include enhanced accessibility, improved energy efficiency, and will support
recommendations anticipated within the Integrated Leisure Master Plan.
Asset
Management, Finance,
RECOMMENDED
BY: ________________________ ________________________
Glen Taylor Brenda
Librecz
Acting
Director of Commissioner
of
A - “Thornhill
Community Centre & Library Infrastructure Renovation Project Presentation”
B – “Project
Budget Snapshot”
Q:\Recreation\SITES\SIT074\Thornhill CCL - Report to
General Committee - edited dec 3.doc