Report to: General Committee Report Date: December 7, 2009
SUBJECT: West Thornhill Stormwater Flood Remediation Class Environmental Assessment
PREPARED BY:
Yanli Xu, Senior Stormwater Management Engineer, ext.2894
RECOMMENDATION:
1) THAT the report entitled “West Thornhill Stormwater Remediation Class Environmental Assessment” be received;
2)
3)
4)
5)
EXECUTIVE SUMMARY:
Not applicable
The purpose of this report is to seek Council’s endorsement
for the preferred alternative solution, the 100 year level of protection, to
improve the stormwater system performance in West Thornhill and to obtain the Council’s authorization to
file the Class EA report for the 30 day public review.
West Thornhill (Attachment A – Study Area) like many other
older areas in Markham is vulnerable during severe storm events to significant
surface and building flooding. Rainfall
events that excess the level of protection available in the municipal
infrastructure such as that which occurred in August of 2005 have the potential
to cause flooding of many basements and damage to the Town's infrastructure
such as culverts, storm sewers and watercourses.
In response to the damages that occurred from the 2005 storm event, the Town of Markham initiated, in February 2008, a Municipal Class B Environmental Assessment study to assess the existing stormwater system capacity, explore alternative solutions and to arrive at a preferred alternative solution to improve the level of protection in West Thornhill.
On March 23, 2009, Staff presented to General Committee a
detailed presentation on the background of the area, the characteristics of the
rainfall event, causes of basement flooding, modeling results of various
simulations and the new infrastructure required to improve the level of
protection to the 5, 25 and 100 year level.
Included also was the estimated cost for these improvements. Council authorized staff to proceed to host
Public Information Centre (
On June 2, 2009 at a Special Development Services Meeting
(SDSC), staff presented the alternative solutions, evaluation criteria /
methodology, funding options, Town-wide financial implications, application for
the federal infrastructure stimulus funding and next steps pending results from
the stimulus announcement. Staff were directed to hold Public Information
Centre (
At the Council meeting on June 3, 2009, there were further discussions and clarification on the rational why staff were recommending a 5 year level of protection as the preferred solution and it was explained that:
·
· The storm event that occurred in August 2005 was a very intense storm with a return probability of over 150 years. Given the large storm that occurred, the storm system performed extremely well with only several hundred homes flooded in the area of over 8000 properties. The likelihood of another rainfall of this intensity hitting this particular area is low. Under frequent rain events, the area is relatively well protected.
· There was concern about the cost to implement a program to transform a community’s infrastructure to the extent of a 100 year design storm. It was communicated that a more modest increase to a 5 year level would be more affordable and management on a Town-wide basis initially with options available in the future to increase this level further using in-line storage or other environmental techniques. It was clarified that the 100 year level of protection does not provide 20 times more protection compared to the 5 year level of protection, but rather only twice as much. The rainfall volume of the 100 year is only 40% more than the 5 year design storm.
· It was explained also that flooded basements can be caused by a lot of factors including lot grading issues, drain problems and building foundation defects that are outside the scope of the improvements identified and beyond the control of the municipality.
· The sanitary sewer system responds in proportion to the rainfall intensity and there will be a larger cost to protect against sanitary sewer surcharging to this higher level of protection. This is not part of this Class EA study but staff had communicated some of the potential costs.
· The infrastructure upgrades identified in the study were established on the basis of alleviating flooding in areas where flooding occurred to a cluster of homes. Individual properties flooded in the upper reaches of the drainage area due to back falling driveways or particularly low basement elevations were not addressed in the study due to the high cost. Therefore not all vulnerable basements will be protected with extent of the infrastructure established in the study.
On June 5 2009, it was confirmed that the Town was not successful in the infrastructure stimulus funding application. On June 22 2009, Staff reported to General Committee with the project update report. In the report, staff indicated that “once Council makes the decision on the level of protection, staff will move forward to host the Public Information Centre #2 in the fall of 2009.” General Committee confirmed its position on the 100 year level of protection.
At the June 23, 2009 Council meeting, Council further
discussed the report, “West Thornhill Stormwater Flood Remediation Class Study
Update”. At this meeting Council
reconfirmed its position on the 100 year level of protection and directed staff
to proceed to host
A Public Liaison Committee was established which included ratepayer groups, regulatory agencies, neighbouring municipalities, Councillors and Town’s staff. Four Liaison Committee meetings were held to review the study findings.
Notice of Commencement, and
notices for
After the presentation of alternative solutions to Council
on March 23 and to the public at the
·
Technical
and Engineering Considerations – minimize potential for basement flooding /
protection of human and built environment / reduce cost of flooding for
residents;
·
Economic
Environment Considerations – Minimize capital, operating and maintenance costs;
·
Natural
Environment Considerations – Minimize impacts to natural habitats / peak flow /
creek erosion / sediment transport / water quality; and
·
Social
and Cultural Environment. – Minimize community disruption.
Extensive
technical analysis and evaluation was conducted. Following the presentation of the draft
preferred alternative, the 100 year level of protection, at the
·
downspout disconnections,
·
Installations of inlet control devices (to
reduce surface flows into storm sewers where these is limited capacity),
·
Installation of new catchbasins (to increase
surface flow into storm sewers where there is capacity) and
·
New infrastructure (twinning or diversion) for
flood prone areas only.
The cost estimated
for the preferred alternative is $40 millions as shown on Attachment C.
The recommended
alternative of raising the level of service to 100 year design storm in the
flood prone areas within West Thornhill has a number of implications:
TOWNWIDE IMPLICATIONS: The majority of the storm system
infrastructure in West Thornhill, like many other older areas across the Town,
was built accommodate a 2 year storm with no provision for overland flow
routes. This was the accepted and
affordable design criteria at the time the homes that were developed. Although the design standards for stormwater
systems have changed significantly, these systems have performed reasonably
well over the past 50 years. However,
due to the severe rainfall event on August 19, 2005, West Thornhill encountered
flooding problems in certain areas. If
the other older areas across the Town were to experience the same rainfall,
similar flooding problems would likely occur.
It is assumed that if the West Thornhill area is upgraded to a higher
level of protection then a similar
program would be adopted by Council to upgrade other older areas of Town. This would require significant additional
funding. Further discussions regarding Town-wide implication will be part of a
future implementation report.
SANITARY
IMPROVEMENTS: Basement flooding is also caused by surcharge in the sanitary
sewers. The estimated cost for sanitary
improvements required in West Thornhill is estimated to be $37.5M, which
includes sanitary sewer replacements and inflow / infiltration (I/I) reductions. This will have a corresponding financial
impact if adopted across the Town.
Upon approval of the
Class EA and as per Council direction, staff will report back to
General Committee on an implementation strategy including resource requirements,
financing options, Town-wide implications, phasing strategies, value
engineering, and a detailed design and construction schedule for the initial
phases.
The precedent of raising the level
of protection to 100 year design storm in flood prone areas within
Level of Protection |
West Thornhill |
Rest of Town (Projected) |
Total Cost |
Stormwater – 100 year level of protection |
$40 Million |
$ 77 Million |
$117 Million |
Sanitary |
$37.5 Million |
$ 72 Million |
$109.5 Million |
Total |
$77.5 Million |
$149 Million |
$226.5 Million |
The cost associated with the rest of Town is an estimate only, based on prorating the cost of the Thornhill area and applying it to the rest of the Town. The actual cost may be substantially different depending on the results of future detailed studies.
Not applicable
This report is consistent with the Building Markham’s Future Together strategic priority on the “Environment” as it considers sustainability on the built environment.
Not applicable
RECOMMENDED
BY:
________________________ ________________________
Steve
Andrews Brenda
Librecz
Director,
Attachment A – Study Area
Attachment B – Preferred Alternative Solution – 100 Year Level of Protection
Attachment C – Preliminary Cost Estimate for 100 Year Level of Protection