Report to: General Committee                                Date Report Authored: December 10, 2009

 

 

SUBJECT:                          Application to Building Canada Fund Stimulus Fund for the Birchmount Energy Centre

PREPARED BY:               Barb Cribbett, Treasurer

                                            Ext 4735

 

 

RECOMMENDATION:

1)                  That the report entitled “Application to Building Canada Fund Stimulus Fund the Birchmount Energy Centre” be received;

 

2)                  And that the Commissioner of Corporate Services be directed to submit an application for the Birchmount Energy Centre project as outlined in the report to the Government of Canada and the Province of Ontario under the Building Canada Fund Stimulus Fund program

 

3)                  And that the Town proceed with the project at an upset limit of $13,055,000 ($14,624,000 less land cost of $1,569,000) on a 1/3 shared basis with the Province of Ontario, and Government of Canada and the Town of Markham

 

4)                  And that the Town of Markham’s share of $4,351,667 for the project be funded from the Lifecycle Replacement and Capital Reserve Fund

 

5)                  And that staff report back to Council with a draft lease agreement for the Birchmount Energy Centre with Markham District Energy Inc. 

 

6)                  And that Staff be authorized and directed to do all things necessary to give effect to this resolution

 

 

PURPOSE:

 

To obtain approval to submit a request for funding to the Federal and Provincial governments under the Building Canada Fund (BCF) Stimulus Fund grant program for the Birchmount Energy Centre

 

 

BACKGROUND:

The Birchmount Energy Centre was one of the potential projects considered by staff in the spring of 2009 for Stimulus Funding.  Although this project was not considered among the top priorities submitted to Council in March of 2009, due in part to the expectation that the facility would be owned by Markham District Energy (MDE), this project is a priority as an element of the overall district energy system in Markham. 

 

Obtaining external debt financing for the Birchmount Energy Centre is proving to be challenging.  Staff is proposing a model whereby MDE owns the land upon which the Birchmount Energy Centre is situated, but the Town owns the constructed energy centre facility.  The Town’s investment of $4,351,667 can then be recovered through a long term lease to Markham District Energy. 

 

OPTIONS/ DISCUSSION:

 

Stimulus Funding is Still Available

The Town has had several discussions with both the Federal and Provincial governments and has identified that there is still uncommitted stimulus funding available.   Although the timeframes for an application for the BCF funding is unknown at this time, it is thought that we need to start the process immediately.

 

The Birchmount Energy Centre project had not started at the time that the Stimulus Grant applications were submitted in April 2009, however, the construction has recently begun (December 7th).  This may result in the project being ineligible for Stimulus funding, although the Infrastructure Stimulus Fund agreement indicates that costs incurred prior to June 5, 2009 are ineligible, suggesting that costs incurred after June 5, 2009 are eligible.   That being said, the deadline of March 31, 2011 makes it almost impossible for a project that has not started to be substantially complete by the deadline.  Staff recommend that this project be submitted in spite of the commencement of construction, as:

 

·        The construction did not commence prior to June 5, 2009 (commencement date for eligible costs in the Infrastructure Stimulus Grant agreement)

·        The benefits listed below are significant

·        The project is on track to be completed no later than March 31, 2011

 

The following is a more detailed description of the project:

 

The Birchmount Energy Centre will be a district energy plant to produce hot and chilled water which are supplied via underground pipes to provide heating and cooling services to customers east of Warden Avenue in downtown Markham Centre.  The hot and chilled water are produced from high efficiency boilers and high efficiency chillers.

 

The major equipment consists of:

a)      two high efficiency electric 1450 ton chillers each

b)      two high efficiency natural gas 5 MWth boilers each

 

The plant is located in Birchmount Road and is expected to cost $14.624M, excluding the land cost the construction cost is $13.055M.  It is sized to accommodate the addition of two chillers and two boilers at a future date.

 

 

 

 

 

 

 

Birchmount Energy Centre Budget

Item Description

Costs

% of Total

1.         Land Acquisition & Closing Costs

$1,569,000

10.7%

2.         Owner Supplied Equipment

$2,885,000

19.7%

3.         PowerStream Costs

 

 

                        Pole Relocation

$500,000

3.4%

                        Connection Costs

$300,000

2.1%

4.         Engineering & Professional Services

$1,500,000

10.3%

5.         Construction Costs

$7,370,000

50.4%

6.         Contingency

$500,000

3.4%

Total

$14,624,000

 

Note: Construction interest, financing and associated legal costs and commissions not included in above total.

 

 

 

Project Start Date

Construction commenced December 7, 2009 (the concrete footings for the building was poured) and the plant is expected to be substantially completed November 30, 2010.

 

Project Benefits

The district energy system utilizes higher efficiency boilers and chillers providing an efficiency resource improvement.  Further benefits of district energy include:

1.      Energy efficient.  When hot water or chilled water arrives at a customer's building, the thermal energy is “ready to use”.  It is 100 percent efficient "at the door," compared with 80 percent or lower efficiencies when burning natural gas at a building. The less energy used, the less emissions expelled into the environment.

2.      Environmentally sound.  District energy enables building owners to conserve energy, improve operating efficiency and protect the environment.  With district energy, building managers no longer need to burn fuels or store or use refrigerants on site, so the site is safer and more environmentally sound.   District energy plants can employ stringent emission controls - more so than individual buildings - and this provides air-quality benefits.  

3.      Easy to operate and maintain.  District energy is worry-free heating and/or cooling delivered directly to a customer's building - ready to use.  Customers do not need boilers or chillers, so there is less maintenance, monitoring and equipment permitting.  And that allows occupants, rather than energy operations, to be the focus.  District energy customers also eliminate the need for fuel deliveries, handling and storage so there are fewer safety and liability concerns for employees and building occupants.

4.      Reliable. Building owners and managers can count on district energy systems since energy professionals operate around-the-clock and have backup systems readily available. 

5.      Comfortable and convenient.  District energy is available whenever a building needs heating or cooling.   In addition, district energy reduces vibrations and noise problems that could annoy building occupants and frees up building space so more room is available to meet increasing tenant storage needs.

6.      Design flexibility.  No stacks, boilers or cooling towers means greater building design flexibility.  Architects can easily design or renovate buildings to be more versatile and aesthetically pleasing for both potential occupants and the community.

7.      Fuel flexibility. District energy system facilitates fuel flexibility for all connected customers. Renewable fuels such as biomass, biogas and concentrated solar thermal can be easily integrated into the energy centre plant.

8.      LEED.  Buildings served by a district energy system receive LEED (Leadership in Energy and Environmental Design) points.

 

FINANCIAL CONSIDERATIONS AND TEMPLATE:

The funding formula is based on a 1/3 shared basis with the Province of Ontario, Government of Canada and the Town of Markham. The Town’s share ($4,351,667) is recommended to be funded from the Life Cycle Replacement and Capital Reserve. The investment of $4,351.667 (plus lost interest) would then be recovered through a lease to Markham District Energy. 

 

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

 

 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

 

 

RECOMMENDED

                            BY:

 

______________________                               ________________________

Barb Cribbett                                                      Andy Taylor

Treasurer                                                             Commissioner, Corporate Services

 

 

 

ATTACHMENTS:

N/A