Report to: Development Services Committee                              Report Date: January 12, 2010

 

 

SUBJECT:                          RECOMMENDATION REPORT

                                            Ontario Municipal Board Appeal

                                            2 Tang’s Automotive Centre

                                            210 Old Kennedy Road, Main Street Milliken

                                            Site plan application to facilitate the expansion of an existing motor vehicle repair garage.

 

                                            File No:   SC 05 024524

 

PREPARED BY:               Stacia Muradali, Planner

                                            Central District, Ext. 2008

 

 

 

RECOMMENDATION:

 

1)                  That the staff report dated January 12, 2010, titled “RECOMMENDATION REPORT, Ontario Municipal Board Appeal, 2 Tang’s Automotive Centre, 210 Old Kennedy Road, Main Street Milliken, Site plan application to facilitate the expansion of an existing motor vehicle repair garage, File No: SC 05 024524”, be received; and

 

2)                  That Council endorse the site plan (File No: SC 05 024524), subject to the conditions attached in Appendix ‘A’, and

 

3)                  That Council direct the Town Solicitor and Staff to attend the Ontario Municipal Board Hearing on January 28, 2010, to ensure that the conditions of site plan approval attached in Appendix ‘A’ are imposed by the Ontario Municipal Board; and

 

4)                  That Council authorize the Mayor and Clerk to execute a site plan or other development agreement with the Owner of 210 Old Kennedy Road, in a form satisfactory to the Town Solicitor; and

 

5)                  That Staff be authorized to do all things necessary to give effect to these resolutions;

 

 

 

 

 

 

EXECUTIVE SUMMARY:

Not applicable.

1. Purpose                     2. Background                      3. Discussion                        4. Financial        

 

5. Others (HR, Strategic, Affected Units)                                   6. Attachment(s)

 

 

PURPOSE:

The purpose of this report is to obtain Council’s direction in connection with a site plan appeal to the Ontario Municipal Board (OMB) by 2 Tang’s Automotive Centre.  The appeal concerns a proposed expansion to an existing motor vehicle repair garage located at 210 Old Kennedy Road.  The appeal was initiated for lack of decision respecting the site plan application.  The OMB has scheduled a one (1) day hearing on January 28, 2010, for this appeal.

 

 

BACKGROUND:

Subject property and area context

210 Old Kennedy Road (the “subject property”) is located on the south-west corner of Old Kennedy Road and Victory Avenue, south of Denison Street, north of Steeles Avenue, east of Kennedy Road, in Main Street Milliken (Figure 1).  2 Tang’s Automotive Centre owns and operates a motor vehicle repair garage at 210 Old Kennedy Road.  The subject property has an area of 0.26 hectares (0.64 acres).

 

The motor vehicle repair garage was in operation prior to the adoption of the Main Street Milliken Secondary Plan (OPA 144) (the “Secondary Plan”) in 2006.  2 Tang’s Automotive Centre appealed the Secondary Plan, which prohibited automotive commercial uses, including gas stations, automobile repair, car washes and automobile sales, within the Secondary Plan Area.  As a result of the OMB appeal, the existing motor vehicle repair garage is recognized as a permitted use.

 

To the east, there are single family residential homes, backlotted on the east side of Old Kennedy Road.  Large lots with older single family detached dwellings are located on the north side of Victory Avenue, and an industrial and commercial development to the south, with a residential and mixed use development proposed to the south of that development (Figure 3).

 

Proposed expansion to the existing motor vehicle repair garage

A site plan application was submitted in 2005 to facilitate an expansion to the existing motor vehicle repair garage.  The current operation has a gross floor area of 192.38 square metres (2,070 square feet).  The owner is proposing to expand the existing operation by adding more repair bays, and undertaking certain site-servicing upgrades (Figure 4).  The proposed gross floor area is 537.04 square metres (5,780 square feet).  There are two (2) existing accesses on Old Kennedy Road.  The owner will close the most northerly access. The owner is also proposing to clean up the site and enhance the landscaping.

 

 

 

Secondary Plan and Zoning

210 Old Kennedy Road is designated “Community Amenity Area – Main Street” in the Main Street Milliken Secondary Plan, which provides for mixed-use development, including small to moderate scale retail, personal service, restaurant and business uses on the ground floor of a building, with residential uses above. This designation typically prohibits automobile repair uses, however, the existing motor vehicle repair garage is recognized by the Secondary Plan, as the result of an Ontario Municipal Board decision to allow the existing use, further to the owner’s appeal of the Main Street Milliken Secondary Plan.  Expansions to the existing operation can occur, provided they are consistent with the applicable zoning standards.  As noted below, the proposed expansion will be consistent with the applicable development standards.

 

210 Old Kennedy Road is zoned “Community Amenity Two [CA2 *284 (H) *278]” (Figure 2).  The existing zoning recognizes the existing motor vehicle repair garage as a permitted use, and establishes development standards specific to this use.  The proposed expansion of the existing operation complies with the existing zoning.

 

 

OPTIONS/ DISCUSSION:

Environmental clean-up and engineering improvements proposed

There is an existing oil tank, a well and a septic tank on the subject property, which will all be removed as part of this site plan application.  The owner had prepared an Environmental Site Assessment which has since been revised, and now meets Town standards.  In addition, the owner will be connecting to municipal servicing and will improve the storm drainage on site.  The owner will be required to prepare a stormwater management report, design and drawings for the extension of the Town infrastructure (sanitary, storm and watermain) to the satisfaction of the Town, and in conformity with the Main Street Milliken Servicing Study.  The owner has provided a Noise Study which demonstrates that the proposed expansion should not negatively impact adjacent properties.  A small portion of land required for a road widening at the corner of Victory Avenue and Old Kennedy Road will be conveyed to the Town.  These matters have been resolved with Staff, and form part of the conditions of site plan approval  (see Appendix ‘A’ attached) to be presented to the OMB.

 

Requirement to join the Main Street Milliken Developers Group

There is a Developers Group in the Main Street Milliken Secondary Plan area.  Section 9.1.9 in the Main Street Milliken Secondary Plan states that “property owners shall be required to either enter into one or more Developers Group Agreements, or implement alternative arrangements to address the sharing of common costs of development, as a condition of the development of their lands.”

 

The owner is required to join the Developers Group and sign the cost sharing agreement to pay its proportionate share of additional sanitary and watermain work which the Group is required to complete for the Main Street Milliken community.  The owner will not be responsible for costs related to parks and schools for the area. 

 

At this time, the owner has not resolved the cost sharing matters with the Developers Group.  The Trustee of the Developers Group intends to request status at the upcoming OMB hearing, in the event that this matter is not resolved prior to the hearing.

 

The owner has been requested to pay recoveries

The Town has requested that the owner pay its proportionate share of “best effort” recoveries for the area.  The Town has entered into agreements with Cedarland Properties and Krashnik Investments Limited, to collect recoveries on their behalf for oversizing of infrastructure that will benefit the subject property.  Staff have provided the owner with the recovery items (see ‘Appendix ‘B’ attached), in favour of historical front-ending landowners.

 

At this time, the owner has agreed to pay some of the recoveries, but are challenging certain recovery items.  The Town has been advised that Cedarland Properties will attend the OMB Hearing in support of its claims, and staff are still waiting for confirmation from Krashnik Investments Limited.

 

Site plan, landscaping and building elevation improvements

The owner will be consolidating the accesses on Old Kennedy Road into one main access.  The external garbage enclosure which is currently located in the parking area, will be removed, and the garbage will be stored internal to the building.  The owner has agreed to enhance landscaping around the perimeter of the subject property by planting more trees and increasing the north landscape strip to 6m, as required by the zoning by-law.  The owner will also be adding hedges around the easterly parking area and fencing around the westerly parking area to screen the parked cars.  The owner is working with staff to improve the façade fronting onto Victory Avenue (Figure 5).

 

Conclusion

Staff have been working with the owner to resolve certain issues, including soil remediation, site servicing, building facades, landscaping and screening, prior to reporting on the site plan application.  However, there are still some outstanding issues, specifically with respect to the owner’s obligations to the Landowners Group, and payment of recoveries, which the owner opposes.  Staff are generally satisfied with the proposed site plan and building elevations, subject to the revisions previously discussed, and subject to the conditions in Appendix ‘A’.  Therefore, it is recommended that Council endorse the site plan application, subject to the conditions attached in Appendix ‘A’, and that the Town Solicitor and Staff be authorized to attend the OMB Hearing, to ensure that the conditions of site plan approval are imposed (Appendix ‘A’), and the outstanding issues be appropriately resolved.

 

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

Not applicable.

 

HUMAN RESOURCES CONSIDERATIONS

Not applicable.

ALIGNMENT WITH STRATEGIC PRIORITIES:

The proposed site plan application will assist in improving the environmental impacts of the existing operation by cleaning up the site, and removing the existing septic and oil tanks and well.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

This application has been circulated to Town departments and external agencies and their requirements have been incorporated into this report.

 

 

RECOMMENDED  BY: 

 

 

 

 

 

______________________________                      _______________________________

Biju Karumanchery, M.C.I.P., R.P.P                        James Baird, M.C.I.P., R.P.P

Senior Development Manager                                  Commissioner, Development Services       

 

 

ATTACHMENTS:

 

Figure 1:                     Location Map

Figure 2:                     Area Context/ Zoning

Figure 3:                     Aerial Photo

Figure 4:                     Proposed Site Plan

Figure 5:                     Proposed Building Elevations     

 

Appendix ‘A’:            Conditions of Site Plan Approval

Appendix ‘B’:             Statement of Recoveries

 

 

 

File path: Amanda\File 05 024524\Documents\Recommendation Report

 

 

 

 

 

 

 

 

 

 

 

 

APPENDIX ‘A’

 

CONDITIONS OF SITE PLAN APPROVAL

 

1.         That the Owner execute a site plan agreement, which incorporates the following conditions, in addition to the Town’s standard clauses:

 

Revisions to the Site Plan and Building Elevations and Provision of Additional Plans:

           

            a)         That the Owner revise the site plan to provide:

1.                  the required 6m north landscape strip width; and

2.                  to relocate the external garbage enclosure internal to the building.

 

b)         That the Owner revise the north building elevation drawing fronting onto Victory Avenue, to the satisfaction of the Director of Planning and Urban Design; and

           

c)                  That the Owner provide a landscape plan, to the satisfaction of the Director of Planning and Urban Design; and

 

d)                  That the Owner provide a stormwater management report to the satisfaction of the Director of Engineering; and

 

e)                  That the Owner provide a plan and profile for the extension of the Town’s infrastructure (storm, sanitary and watermain), to the satisfaction of the Director of Engineering, and in conformity with the Main Street Milliken Servicing Study.

 

Screening

 

f)                    That the Owner erect a fence to screen the westerly portion of the parking area.

 

Site Servicing

 

g)                  That the Owner undertake all site servicing works, in accordance with the stormwater management report, design and drawings for the extension of the Town’s infrastructure, to be approved by the Director of Engineering.

 

Recoveries and Additional Fees

 

h)                  That the Owner pay all applicable fees, recoveries (see Appendix ‘B’ attached), development charges and cash-in-lieu of parkland.

 

Main Street Milliken Developers Group

 

i)                    That the Owner enter into one or more Developers Group agreements, or implement alternative arrangements to address the sharing of common costs of development, as a condition of the development of their lands.

 

Environmental Site Assessment

 

j)          That the Owner provides a clearance and reliance letter from the Environmental Consultant, in regard to the Environmental Site Assessment, to the satisfaction of the Director of Engineering.