Report to: Development Services Committee                              Report Date: January 12, 2010

 

 

SUBJECT:                          RECOMMENDATION REPORT

                                            Draft Plan of Subdivision and zoning applications by

                                            Springhill Macwood Homes Inc to permit a residential and mixed-use development north of Highway 7, west of Cornell Centre Boulevard in the Cornell Community

                                            7128, 7170, and 7186 Highway 7

                                            File Numbers: SU 04-028274 (19TM-040016) and ZA 04-028028

PREPARED BY:               Doris Cheng, Senior Planner – East District, ext. 2331

 

 

RECOMMENDATION:

1)                  That the report dated January 12, 2010 entitled “Recommendation Report.  Draft Plan of Subdivision and zoning amendment applications by Springhill Macwood Homes Inc. to permit a residential and mixed-use development north of Highway 7, west of Cornell Centre Boulevard in the Cornell Community, 7128, 7170, and 7186 Highway 7, File Numbers: SU 04-028274 (19TM-040016) and ZA 04-028028” be received;

 

2)                  That the record of the Public Meeting held on November 21, 2006, regarding the applications for approval of Draft Plan of Subdivision and implementing Zoning By-law be received;

 

3)                  That draft plan of subdivision (19TM-040016) submitted by Springhill Macwood Homes Inc. to permit residential and mixed use development in the Cornell Community, be draft approved subject to the conditions set out in Appendix ‘A’ to this report;

 

4)                   That the application submitted by Springhill Macwood Homes Inc. to amend Zoning By-law 304-87 and 177-96, as amended, be approved and the draft by-laws attached as Appendix ‘B’ be finalized and enacted without further notice;

 

5)                  That the Owner provide the Town with the required payment of 30% processing fees in accordance with the Town’s applicable Fee By-law;

 

6)                  That the draft plan approval for plan of subdivision 19TM-040016 will lapse after a period of three (3) years from the date of issuance in the event that a subdivision agreement is not executed within that period;

 

7)                  And that Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

 

 

 

 

EXECUTIVE SUMMARY:

This report recommends approval of plan of subdivision and zoning by-law amendment applications by Springhill Macwood Homes Inc to permit medium and high density residential development on their lands in Cornell.  The subject lands consist of approximately 7.1 hectares (17.5 acres) located on the north side of Highway 7, west of Cornell Centre Boulevard. 

 

The draft plan of subdivision consists of four main development blocks containing approximately 1,400 medium and high density units, accessed by a network of public roads.  The plan also includes a small public park and a partial elementary school block at the north limit of the subdivision.  A heritage building within the property (Francis Pike House) is proposed to be relocated to a centralized location on the site. 

 

Development within all of the blocks in the proposed subdivision is subject to site plan approval, at which time details regarding the built form and number of units will be confirmed.  The proposed land uses, road configuration, and residential density of the proposed draft plan of subdivision generally conforms to the land use designations and policies of the Cornell Secondary Plan.

 

Servicing allocation for 289 apartment units (549 population) has been assigned to this property by Council for high density development fronting on Highway 7.  The allocation is intended to be used toward the proposed 300-unit apartment building currently under site plan application at the northwest corner of Cornell Centre Boulevard and Highway 7.   Allocation for this apartment building and all other phases of development will be confirmed at site plan approval.

 

The proposed plan of subdivision is acceptable and staff recommend that the plan be draft approved subject to the conditions listed in Appendix ‘A’.  Staff also recommend that the draft implementing zoning by-laws attached as Appendix ‘B’ be finalized and enacted.

 

 

1. Purpose                     2. Background                      3. Discussion                        4. Financial        

 

5. Others (HR, Strategic, Affected Units)                                   6. Attachment(s)

PURPOSE:

The purpose of this report is to recommend approval of a residential plan of subdivision and implementing zoning for the lands north of Highway 7, west of Cornell Centre Boulevard in the Cornell Community.

 

BACKGROUND:

Property and Area Context

The subject lands consist of approximately 7.1 hectares (17.5 acres) on the north side of Highway 7, west of Cornell Centre Boulevard, municipally known as 7128, 7170 and 7186 Highway 7 (Figure 1).   The lands are generally flat tableland and unvegetated with the exception of a number of mature trees in the vicinity of the dwellings and outbuildings near Highway 7 on each of the three properties.  The dwelling at 7170 Highway 7 (Frances Pike House) is identified in the Cornell Secondary Plan as a building of significant cultural heritage interest in the Town of Markham.

 

The lands are surrounded by vacant lands to the west and north, intended for residential and community park purposes.  To the south across Highway 7 are vacant lands intended for high density residential and a mixed-use retail centre.   To the east across Cornell Centre Boulevard are vacant lands intended for residential development as well as a large woodlot (Figures 2 and 3).

 

The plan of subdivision consists of medium and high density mixed-use development

The draft plan of subdivision consists of four main development blocks accessed by a network of public roads, as detailed in Table 1 and shown in Figure 4.   

 

Table 1: Land Use Summary – 19TM-040016

Block

Area (ha)

FSI

Use

Units (Proposed)

Block 1

0.69

 

2.6

Medium/high density

residential

201

Block 2

0.65

2.5

Medium/high density

residential

200

Block 3

1.58

2.1

Medium/high density

residential

400

Block 4

0.3

 

Park

 

Block 5

1.62

3.2

Mixed-use, high density residential

600

2,970 m² of commercial/retail uses

Block 6

1.02

 

Elementary

School (partial)

 

TOTAL

 

 

 

1,401 units

2,970 m² of commercial/retail

 

Approximately 1,400 medium and high density units are proposed within the four residential blocks.  These units consist of approximately 600 apartment units in Block 5 fronting Highway 7, and approximately 800 multiple and apartment units within Blocks 1 through 3 in the interior of the site. 

 

The plan also includes a small public park and a partial elementary school block at the north limit of the subdivision.  The heritage building (Francis Pike House) is proposed to be relocated to a centralized location on the site within Block 3. 

 

The primary north-south roads include Cornell Centre Boulevard immediately to the east and a new north-south road at the west limit of the subdivision.  Three new east-west roads are also provided within the subdivision.

 

Development of all blocks subject to site plan approval

Development within all of the blocks in the proposed subdivision is subject to site plan approval, at which time details regarding the built form and number of units will be confirmed.  A site plan application for one of the proposed apartment buildings in Block 5, at the northwest corner of Highway 7 and Cornell Centre Boulevard, is currently under review by staff, and will be brought before Committee for approval under a separate report.  A conceptual site plan for the entire site is attached as Figure 5. 

OPTIONS/ DISCUSSION:

The proposed plan of subdivision is generally consistent with the Cornell Secondary Plan

The subject lands are entirely within the area described as ‘Cornell Centre’ in the Cornell Secondary Plan.  Cornell Centre, encompassing lands on both sides of Highway 7, is intended to function as the central community focus for the Cornell community, providing a range of high density residential, commercial, institutional and employment uses centred on a planned regional transit service (VIVA) along Highway 7.   

 

The lands within the proposed plan of subdivision are designated ‘Residential Neighbourhood–Cornell Centre’ (Blocks 1 through 3) and ‘Avenue Seven Corridor-Mixed Residential’ (Block 5).  The ‘Avenue Seven Corridor-Mixed Residential’ designation is intended to accommodate high density residential development, incorporating retail, service and office uses at grade.  Building heights in this designation range from a required minimum of 4 storeys to a maximum of 12 storeys, with a required minimum FSI of 2.5.  The minimum height of buildings that front Highway 7 in this designation is 8 storeys. The Secondary Plan also requires non-residential uses on the ground floor of apartment buildings along this section of Highway 7.

 

The ‘Residential Neighbourhood-Cornell Centre’ designation is intended to accommodate medium and high density housing forms that support the regional transit service along Highway 7, and to provide a transition in height and density from Highway 7 to the lower density residential neighbourhoods that adjoin Cornell Centre.   Permitted uses included multiple unit and apartment building ranging from a minimum of 4 storeys to a maximum of 6 storeys, at a minimum FSI of 1.5.

 

The proposed apartment building development in Block 5 is generally consistent with the ‘Avenue Seven Corridor-Mixed Residential’ designation, providing for two 300-unit 12-storey buildings fronting Highway 7. The proposed buildings taper down to 8 storeys along the north-south streets. Commercial uses are provided for on the ground floor of the buildings along Highway 7.  The FSI of the proposed buildings, calculated over the total area of Block 5 is 3.2. 

 

The proposed development in Blocks 1 through 3 are also generally consistent with the ‘Residential Neighbourhood-Cornell Centre’ designation.  Proposed residential building types include a mix of multiple unit and apartment buildings, at a minimum height of 4 storeys and a maximum height of 6 storeys.  The overall FSI of the proposed buildings within Blocks 1 through 3 is 2.4.   The implications for the school boards of the proposed overall FSI within the blocks, will be assessed during site plan approval.

 

Staff have worked with the applicant to ensure a road and block pattern consistent with the Cornell Secondary Plan.  ‘Street A’, running parallel to Highway 7, has been aligned with a future vehicular access on the east side of Cornell Centre Boulevard, south of the woodlot, to be developed by others.  The northerly east-west street dividing the school block from the residential lands respects the alignment of a future east-west street extending from 9th Line.

 

The proposed land uses, road configuration, and residential density of the proposed draft plan of subdivision generally conforms to the land use designations and policies of the Cornell Secondary Plan.   

 

Proposed parkland consistent with Cornell Master Parks Agreement

The public park block has been located to provide an open space link from the elementary school site to the interior of the development.  The 0.3 hectare park is being provided as part of the additional contribution required for high density development within the Highway 7 corridor in accordance with the Cornell Master Parks Agreement.  

 

Heritage building to be integrated within the proposed development

The applicant is proposing to relocate the heritage building (Frances Pike House) currently at 7170 Highway 7 to a location within a development block internal to the site (Block 3).  The building at its proposed location will form a visual terminus to open space links from the elementary school site to the north and from Highway 7 to the south.   

 

The heritage building will be incorporated within the residential development, and the ultimate use of the building is still under discussion.   Heritage staff are satisfied with the proposed location of the building subject to, among other things, site plan approval.  The requirements of Heritage staff are included in the conditions of draft plan approval attached as Appendix ‘A’.

 

Limited servicing allocation has been assigned

Servicing allocation for 289 apartment units (549 population) has been assigned to this property by Council for high density development fronting on Highway 7.  The allocation is intended to be used toward the proposed 300-unit apartment building currently under site plan application at the northwest corner of Cornell Centre Boulevard and Highway 7.   The remaining 11 units of allocation are intended to be obtained through the Region’s ‘Sustainable Development through LEED’ program by meeting LEED Silver certification requirements.  Allocation for this apartment building and all other phases of development will be confirmed at site plan approval.

 

The York Region District School Board is satisfied with the future school site block

The 1.02 ha school block provides just under half of the required school site. The size and configuration of the partial school site provided in this plan is dictated largely by the larger road pattern.  The remainder of the lands required for the school block will be obtained when the adjacent lands to the north are developed.  The YRDSB’s conditions are included in the conditions of approval attached as Appendix ‘A’.

 


Issues identified at the Public Meeting have been addressed

The statutory public meeting to consider the draft plan and rezoning applications was held on November 21, 2006.  Since that meeting, staff have contacted the surrounding landowners, informing them that the recommendation report for this application is being brought forward for Committee consideration.

 

The concerns raised at the Public Meeting and through the review of the application have been addressed as follows:

 

Height of the high density residential proposal and appropriate infrastructure

A representative of the Cornell Ratepayers’ Association requested a maximum height of ten storeys and that appropriate infrastructure be in place prior to development.  The proposed heights of 12 storeys along Highway 7, and six storeys in the interior of the subdivision, are consistent with the Secondary Plan, and will be confirmed through site plan approval. 

 

The plan of subdivision provides for portions of the required infrastructure including segments of the ultimate road network in Cornell, a partial school site and public open space.   Although the lands are located within an as yet undeveloped area of Cornell, the lands immediately to the south of Highway 7 have been site plan endorsed and zoned for a mixed-use commercial centre, and are expected to be developed in the near future.

 

Integration of remnant lands from the construction of old Markham By-Pass (Cornell Centre Boulevard)

Staff are in discussions with the applicant regarding the acquisition and integration of the remnant land parcels (see Figure 4) resulting from the construction of the old Markham By-Pass (Cornell Centre Boulevard) right-of-way, which are still in Town ownership.   The resolution of the issue will be confirmed at the time of site plan approval.

Zoning By-law amendments are required

The lands are currently zoned Rural Residential Four (RR4) in By-law 304-87, as amended.  Amendments are required to delete the subject lands from By-law 304-87 and to incorporate the lands within the Town’s Urban Expansion Area By-law 177-96, with appropriate zones to permit the proposed development.  

 

The residential zone categories will require Hold Provisions which will be removed once the following are satisfied:

 

  • adequate water and sanitary sewer allocation is available;
  • pre-requisite agreement with the Town of Markham not to pre-sell units within the draft plan until a specified date (one year prior to the required Regional servicing infrastructure being available); and
  • an indemnity agreement with the Region in such case that the servicing infrastructure is not delivered in the anticipated timeframe have been executed.

 

Draft zoning by-laws to implement the proposed plan of subdivision are attached as Appendix ‘B’.   Staff are finalizing by-laws in consultation with the applicant.

 

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

Not applicable.

 

HUMAN RESOURCES CONSIDERATIONS

Not applicable.

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

The proposal aligns with several Town of Markham Strategic Priorities, including but not limited to, Growth Management, Transportation/Transit, Environment, Municipal Services and Parks by:

 

  • providing for development blocks, and park and school blocks consistent with the Cornell Centre policies of the Cornell Secondary Plan;
  • providing for Transit Oriented Development along Avenue 7 and Bur Oak Avenue;
  • providing portions of the public road network identified in the Cornell Secondary Plan; and
  • ensuring the alignment of new public roads have regard for preservation of natural features outside of the limits of the subdivision.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The applications have been circulated to various departments and external agencies, including the Toronto and Region Conservation Authority and the Region of York.  Requirements of the Town and external agencies have been reflected in the preparation of this report and the conditions of draft plan approval.

 

CONCLUSIONS

The proposed plan of subdivision is acceptable and staff recommend that the plan be draft approved subject to the conditions listed in Appendix ‘A’.  Staff also recommend that the implementing Zoning By-law Amendments contained in Appendix ‘B’, be finalized and enacted without further notice.

 

RECOMMENDED BY:

 

 

____________________________                            ____________________________

Biju Karumanchery, M.C.I.P, R.P.P                               Jim Baird, M.C.I.P, R.P.P

Senior Development Manager                                        Commissioner, Development Services

 

ATTACHMENTS:

Figure 1 – Location Map

Figure 2 – Air Photo

Figure 3 – Zoning and Area Context

Figure 4 – Proposed Draft Plan of Subdivision

Figure 5 – Conceptual Site Plan

 

Appendix ‘A’ – Conditions of Draft Plan Approval

Appendix ‘B’ – Draft Zoning By-laws

 

APPLICANT:                                                   AGENT:

Mr. Ignazio Giardina

Springhill Macwood Homes Inc.

35 Pearce Street, Unit 9

Richmond Hill, ON L4B 3A9

Telephone: 905-882-2320

Mr. Sal Crimi

S.C. Land Management Corporation

40 Vogell Road, Unit 14

Richmond Hill, ON  L4B 3N6

Telephone: 905-787-1542

Email:  scland@rogers.com

 

FILE PATH: Amanda\File 04 028274\Documents\Recommendation Report

 

Figure 1 – Location Map