Report to: Development Services Committee                                 Report Date: March 2, 2010

 

 

SUBJECT:                          STATUS UPDATE

                                            Shops on Steeles Redevelopment Proposal

                                            Application for Official Plan (Secondary Plan) Amendment.  2900 Steeles Avenue East

                                            File No.: OP 07 130802

                                           

PREPARED BY:               Sally Campbell, Senior Planner – Zoning & Special Projects

 

 

RECOMMENDATION:

1)                  THAT the report entitled “ Status Update, Shops on Steeles Redevelopment Proposal, Application for Official Plan (Secondary Plan) Amendment, 2900 Steeles Avenue East, File No.: OP 07 130802” be received;

 

2)                  AND THAT a Public Meeting be held to consider the Official Plan Amendment submitted by Bayview Summit Development Ltd., which seeks to permit a full range of retail, service commercial and office uses as well as high density residential uses at the property municipally known as 2900 Steeles Avenue East;

 

3)                  AND THAT the resident Working Group (established in May 2008 to provide input from local residents, relay information back to the community and explore urban design and development principles) continue to meet for the balance of the Official Plan Amendment application process;

 

4)                  AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

 

EXECUTIVE SUMMARY:

In October 2007 Bayview Summit Development Limited made an application for an Official Plan Amendment to permit a mixed-use retail, office and residential development on the subject property.  The project was previously referred to as Markhamgate Summit, but has reverted to the property’s original name of Shops on Steeles.  An application for a Zoning By-law Amendment was submitted to implement the proposed Official Plan Amendment; however, the applicant has requested that this application be held in abeyance until the Official Plan Amendment application has been dealt with.  Following a series of meetings with the applicant, Town staff and the Working Group held over the past two years, which are detailed below, a revised Official Plan Amendment application was formally resubmitted on December 22, 2009 and is presented in this report together with suggested next steps.

 

The applicant has generally been receptive to comments from staff and from the Working Group and the revised masterplan concept starts to address several critical elements of function, layout and design.  For instance, the internal street grid pattern has been improved to provide small development blocks and better permeability.  Residential units have been provided across the site and fronting Don Mills Road and Steeles Avenue East.  All buildings, except for the easternmost residential towers, have retail / commercial uses at grade to promote pedestrian activity at street level.  Sidewalks and landscaping along driveways are wide enough to provide a comfortable pedestrian environment and opportunities for good tree planting and street furniture.  The westerly access driveway from Steeles Avenue East had been retained and a further driveway access onto Don Mills Road had been provided to improve vehicular circulation.  Residential point towers have been reoriented and separated by open space to provide an improved relationship with adjacent residential areas to the north.

 

The outstanding matters that staff continue to address with the applicant relate to achieving an appropriate development density for the site given the local character and context; the height of the residential point towers and the need to create an acceptable transition in built form between the proposed development and existing neighbouring residential areas; reinforcing the retail function of the internal main street to create a vibrant pedestrian-oriented shopping/commercial environment; providing good connectivity with the existing communities to the south and west (pedestrian connections to the residential area to the north are provided); providing an appropriate amount of open space available for use by the existing community visiting the development and new residents / tenants; committing to the provision of sustainable development practices, including LEED, FLAP, transit-oriented development, traffic demand management; and, agreeing to an appropriate provision of affordable and special needs housing.

 

 

1. Purpose                     2. Background                      3. Discussion                        4. Financial        

 

5. Others (HR, Strategic, Affected Units)                                   6. Attachment(s)

PURPOSE:

The purpose of this report is to:

 

a)advise members of the Development Services Committee of the ongoing work and negotiations that have taken place over the past 2 years;

b)            introduce the revised redevelopment masterplan concept that has been submitted by the applicant as well as summarize the prevalent issues for consideration;

c)seek authorization to hold a statutory Public Meeting; and

d)            reaffirm the ongoing role of the Working Group in the application process.

 

 

BACKGROUND:

 

Area Context

The subject property is approximately 7.1 hectares (17.7 acres) in area and is located on the northeast corner of Don Mills Road and Steeles Avenue East (Figure 1 & 2).

 

The subject lands are bounded by the following uses:

·        To the north and west are low density residential homes;

·        To the south, across Steeles Avenue East in the City of Toronto are townhouses and six-storey apartment buildings; and,

·        Highway 404 to the east and employment uses beyond.

 

Existing Uses

The site, which is zoned Community Commercial and designated Major Commercial Area in the Official Plan, currently supports a shopping centre, three additional commercial buildings on pads located adjacent to Steeles Avenue East, and a gas station at the intersection of Don Mills Road and Steeles Avenue East.  The existing enclosed mall contains 22,634 m2 (243,638 ft2) of retail space, including a food supermarket and a Sears Outlet store, and 2,829 m2 (30,448 ft2) of office space.

 

The subject site is currently served by three access driveways.  Two are located along Steeles Avenue East.  The most eastern of these accesses is fully signalized and accommodates full turning movements, whereas the western access is a right-in/right out access.  The third access, located on Don Mills Road, has full moves, however, is not signalized.  The gas bar is also served by a right-in/right-out access on Don Mills Road (Figure 3).

 

Initial Official Plan Amendment Application

The intent of the initial Official Plan Amendment application submitted in October 2007 was to gradually phase the redevelopment of the existing mall and provide a comprehensively planned, mixed use development with a balanced mix of retail, office and residential.  The general concept of the proposal was inspired by a Lifestyle Shopping Centre model that favours an unenclosed main street shopping experience and steers away from the automobile oriented suburban mall.

 

The applicant originally proposed 18,990 m2 (204,410 ft2) of retail space and 2,617 m2 (28,169ft2) of office space along a central shopping street running east/west through the subject site, with additional retail space extending along the two entrance streets from Steeles Avenue East.

 

The residential component was to comprise a gross floor area of approximately 157, 948 m2 (1,700,199 ft2) and contained in 2,057 units.  Seven, mid to high rise buildings ranging from 10 to 32 storeys in height were proposed on the periphery of the subject site with the taller buildings proposed on the eastern portion of the site.  The overall proposed floor space index was 2.5.  In addition to the process chronology provided below the table attached at Figure No. 8 illustrates the evolution of the development proposal in terms of revisions to gross floor area, floor space index and building heights that have been made over the course of the application.

 

Chronology

The following list summarizes key events of the past two years:

 

·        January 29, 2008 - Community Information Meeting was hosted by Councillor Shiner (City of Toronto).

·        January 30, 2008 – applicant hosted a Community Information Meeting.

·        February 26, 2008 - Community Information Meeting was hosted by Councillor Shapero at which time local residents were given the opportunity to volunteer to participate in a working group.

·        March 18, 2008 - a preliminary report regarding the Official Plan Amendment application was brought to Development Services Committee and motions were carried including authorization for a Public Meeting to be held to consider the application when issues identified in the preliminary report had been sufficiently addressed and that a resident working group, including the Thornhill Sub-Committee members, be established.

·        March 13, 2008 - an application for Zoning By-law Amendment was submitted to implement the proposed Official Plan Amendment.

·        May 6, 2008 - preliminary report and status update was brought to Development Services Committee advising that a statutory Public Meeting was anticipated to be convened in October or November 2008.  In the interim the Working Group was established the Terms of Reference for which were agreed at the May 6th DSC meeting (see Appendix ‘A’).

·        A series of meetings were held with applicant and the Working Group, as follows:

1)      May 21, 2008 – Introduction & Background

2)      June 18, 2008 – Built Form

3)      September 10, 2008 – Alternative Built Form

4)      November 26, 2008 – Transportation & Servicing

5)      February 18, 2009 – New architects, Kirkor Architects & Planners, were introduced and presented a revised masterplan concept

·        Staff met with the applicant, architect and planning consultant team several times during the early part of 2009 to discuss the proposed master plan concept submitted in support of the Official Plan and Zoning By-law Amendment application.

·        July 2009 – staff provide status update to working group members.

·        August 2009 – revised applications were submitted.  However, the detailed proposal and master plan concept did not sufficiently reflect past discussions and directions.  Therefore, with the support of the Ward Councillor, further talks with the applicant and project architect took place.

·        December 22, 2009 – Revised Official Plan Amendment application resubmitted and circulated to Town Departments and external agencies for review and comments.

 

Staff have reaffirmed redevelopment principles

Throughout discussions with the applicant over the course of the past two years, during which a number of alternative masterplan concepts have been reviewed, staff have presented the key principles considered vital to the successful redevelopment of the subject site.  With specific reference to the masterplan concept, these principles include appropriate scale of intensification (density), contextual building height, at-grade retail to frame streets, incorporating retail/commercial uses at the base of residential buildings, redeploying residential density across the site, appropriate transition in heights across the site in relation to adjoining neighbourhoods, pedestrian connectivity and comfort through exemplary public realm design and minimized surface parking lots.  These and other prominent issues will be discussed later in this report.

 

The current redevelopment proposal

As noted above, a revised Official Plan Amendment application with supporting masterplan concept and technical study addenda was submitted on December 22, 2009.  The planning consultant acting on behalf of the applicants also provided written confirmation that consideration of the Zoning By-law Amendment application is to be deferred while the Official Plan Amendment application is processed.

 

The main focus of the proposed development, as set out in the Planning Rationale Report submitted in support of the application, is the reinvention and redevelopment of the retail, commercial and service uses on the site, with the main shopping street running through the centre of the site being the focus of new development.  The total proposed gross floor area (GFA) is 179,557 square metres (1,932,735sq.ft), which translates into an overall Floor Space Index (FSI) of 2.5 for all uses in total.

 

Retail

The total proposed retail gross floor area is 22,736 square metres (244,728sq.ft) and includes the existing two storey Sears Canada Outlet store, which will be renovated to include a new relocated food store, an enlarged relocated drug store with potentially an associated medical clinic, and new retail uses proposed to occupy the second storey.

 

Retail uses are also proposed in the ground floors of buildings situated along Steeles Avenue East, in those flanking the entrance driveways into the development, in the base of three of the residential podiums and along the southern edge of the proposed parking structure fronting the internal main street.

 

Office

The total proposed office space is 8,928 square metres (96,100sq.ft), which is an increase of 2,829 square metres (30,451sq.ft) to the existing amount of leasable office space.  The proposed redevelopment also includes potential for community amenity space on site, with current consideration for the provision of approximately 930 square metres (10,000sq.ft) of space, the location and details of which have not yet been determined.  A portion of the proposed office space (5,227 square metres (56,267sq.ft)) is to be located in a future phase where the gas station is currently located.

 

Residential

Five high-rise residential point towers are proposed ranging in height from 18 to 32 storeys on the eastern portion of the site closer to the Highway 404 / Steeles Avenue East intersection.  Three mid-rise podiums of 8, 9 and 10 storeys respectively provide a transition to the point towers with the 8 storey component closest to the northern property line adjacent to existing low-rise, medium density homes.

 

A portion of residential units would be provided above retail / commercial ground floor space facing Steeles Avenue East across the front of the development.  A further residential building may be provided at a later phase of the development, located at the western edge of the site adjacent to Don Mills Road.

 

The number of residential units is estimated at 1,787, which was arrived at using an estimated average unit size of 81.5 square metres (877sq.ft).  The Planning Rationale Report submits that the unit count estimate is viewed as a maximum number of residential units for analytical purposes in order that trip generation and parking requirements could be assessed.  The total proposed residential GFA is 147,892 square metres (1,591,896sq.ft). 

 

A table summarizing the site statistics of the latest application compared to the existing situation is attached as Figure No.6.  The chart attached as Figure No. 8 indicates the evolution of the application since the original submission and the key components of the latest proposed development are illustrated on the masterplan concept submitted in support of the application, which is attached as Figure No.4.

 

Traffic and Parking

The Traffic Impact Study (TIS) dated August 2009 and the addendum thereto concludes that the projected traffic volumes associated with the redevelopment proposal can be satisfactorily accommodated by the boundary road network and intersections.  Other than minor traffic signal timing improvements no roadway or intersection improvements are proposed.  Markham Transportation staff are currently reviewing the TIS.

 

The proposal provides a total of 1,968 residential parking spaces and 983 non-residential spaces.  The Parking Assessment submitted as part of the TIS asserts that the site is in an excellent location with frequent transit service, which supports other non-automotive modes of transportation, with future plans to introduce higher-order transit on Don Mills Road and Steeles Avenue.

 

In this regard, the Regional Transportation Plan that was adopted by Metrolinx in November 2008 includes a Light Rail Transit (LRT) line in the Don Mills Road / Leslie Street corridor, which directly abuts the subject site to the west.  This project is identified in the 15 year plan of the Metrolinx RTP and is scheduled to occur by the year 2021.  In the mean time, the 10 Year Construction Program of the Region of York indicates a widening of Don Mills Road to a six-lane cross-section between Steeles Avenue and Highway 7.  It is understood that this project is planned for 2013 and will provide two new high occupancy vehicle lanes.  The inner lanes of the roadway would ultimately be converted for the proposed LRT.

 

A Class Environmental Assessment for the Don Mills / Leslie Street LRT project commenced in 2007 and according to a recent Viva update the Environmental Project Report is temporarily on hold pending input from local municipalities.

 

The Metrolinx RTP 16 to 25 year plan identifies Steeles Avenue to receive rapid transit by 2033, which is approximately thirteen years after the anticipated completion date of the proposed Shops on Steeles development.

 

The Parking Assessment provides a comparison of the Town’s requirements, (Parking Standards By-law 28-97) with those of the City of Toronto, which abuts the site to the south.  The outcome of the comparison is that the proposed total site parking supply is about 21 percent lower than the Town of Markham requirement and 17 percent higher than the City of Toronto requirement.  The location of proposed parking is generally as follows:

 

Residential – 1,968 total spaces provided below grade (rate of 1.1 spaces per unit).

 

Non-residential – 983 spaces provided:

                                                            199 – existing Sears store roof parking

                                                            114 – proposed parking structure roof

                                                            320 – within proposed parking structure

                                                            153 – split between three surface parking lots

                                                            50 – on-street space

                                                            147 – below grade

                                                            983

 

In earlier discussions staff advised that, given the mixed-use nature of proposal and the aim to provide transit-oriented development, there may be a logic in applying similar parking requirements as applied in Markham Centre.  In this regard the proposed parking compares with the Markham Centre requirements, as set out in the chart below.  Applying the Markham Centre parking requirements for supermarkets would result in a reduction of 75 parking spaces to the current proposed parking numbers.

 

Use

Markham Centre Parking Requirements

Shops on Steeles Proposed Parking

Residential

1.2 spaces per unit (incl. visitor)

1.1 spaces per unit (incl. visitor)

Retail

1 space per 30 m2 net floor area

1 space per 30 m2 net floor area

Supermarket

1 space per 30 m2 net floor area

1 space per 18 m2 net floor area

Office

1 space per 37 m2 net floor area

1 space per 37 m2 net floor area

 

 

Open Space and Public Realm

An area of open space is proposed towards the eastern portion of the development site.  The masterplan concept shows a park of 4,422 square metres (1 acre) built at grade over structured parking.  The park will be publicly accessible; however, the future ownership, maintenance and parkland credit arrangements have not yet been determined.

 

All vehicular routes within the development have sidewalks on both sides of the driveway.  Key pedestrian connections are between five and eight metres wide (16 to 26 ft) with street trees and enhanced plantings.  Two existing pedestrian connections to the north will be maintained and enhanced.  The private streets will be publicly accessible and designed to resemble a public street system.

 

 

OPTIONS/ DISCUSSION:

The following section of this report sets out the main issues for consideration during the course of the application process.  These issues have been communicated to the applicants and their consultant team since the first submission.  The revised masterplan concept submitted has responded in part to some of the matters raised.

 

No servicing allocation is available for the residential proposal

The residential portion of this application has not yet received servicing allocation.  The Town has received a servicing allocation request from the applicant’s agent, and the Town will consider this when York Region provides servicing allocation to the Town for 2013 and beyond.

 

Markham Growth Management Strategy (GMS)

Within the context of the Region of York’s Intensification Matrix Framework, as confirmed by the Regional Official Plan (adopted by Regional Council on December 16, 2009 and by the Town’s Intensification Strategy), Markham’s GMS recognizes the subject site for potential intensification under the Town’s Major Corridor category.  In relation to the Region’s Intensification Matrix Framework the Major Corridor category is consistent with the Regional Corridor group of intensification areas.

 

Within the Regional Official Plan hierarchy of identified intensification areas:

·   Regional Centres shall generally achieve a minimum density of 2.5 FSI per development block (3.5 FSI adjacent to the Langstaff/Longbridge Station on the Yonge Subway Extension).

·   Regional Corridors - for lands adjacent to other rapid transit stations and/or other select areas an appropriate FSI per development block shall be determined by the local municipality, in consideration of community character and context.

 

The subject lands fall within lands adjacent to other rapid transit stations and/or select areas identified above.  The current submission indicates a density of 2.5 FSI, the majority of which (1.6) is attributed to the proposed high-rise residential buildings.    Town staff will review the potential impact of the density proposed in relation to the Regional Official Plan Intensification Matrix, the Town’s Growth Management Study exercise for identified intensification areas, and local area context in relation to existing and planned transportation infrastructure.  We will continue to work with the applicant and stakeholders to determine the appropriate density in this specific context.

 

Redevelopment of the site must be phased and linked to delivery of rapid transit

It was suggested to the applicant that residential units should be included in earlier phases to improve the mix of uses on the site and support rapid transit use.  The current proposal has responded to this request and some residential units are proposed as early as phase 2 and 3 of a total of 7 phases.  A breakdown of the phasing is provided at Fig. No.6.

 

Mix and affordability of residential units

There is potential for the proposed development to deliver some residential units for moderate and low income households and for those with particular housing needs.  Any future provision as part of the proposal will be informed by the Affordable and Special Needs Housing Strategy that is currently being prepared.  This strategy will inform growth management practices based on creating sustainable, healthy and complete communities and will determine specific community needs and requirements, as well as actions necessary to implement affordable and special needs housing initiatives.

 

Application of Section 37 of the Planning Act

Depending on phasing and the amount of intensification deemed appropriate, the Town will discuss with the applicant the provision of community benefits associated with increases in height and/or density.

 

Sustainable practices

The Planning Rationale Report describes the retention and reuse of the existing Sears building, which is a well built structure and worthy of renovation.  All new and renovated structures are proposed to be constructed to LEED silver standard and alternative energy sources will be explored for this development.

 

Built Form

A key principle of successful intensification is achieving an appropriate transition of built form, both in terms of the relationship of new building to adjacent areas and the general relationship of existing and proposed buildings, across the development site.

 

Relationship with surrounding residential areas

The relationship between the proposed development (in particular the proposed high-rise residential point towers) and the existing surrounding neighbourhoods has been raised as a concern throughout the course of the discussions and working group meetings.

 

The Yonge Steeles Corridor Study report and guidelines, dated September 2008, provides sound principles of graduation of height and density which can, where appropriate, be applied to other redevelopment proposals and identified intensification areas.  The Town is also currently undertaking a comprehensive Built Form, Massing and Height Study, to be applied to all of the Town’s future intensification areas.  The proposal submitted by the applicant proposes a 45 degree angular plane (1:1) measured from the building face of the nearest residential property to the closest proposed residential building.  An example of the applicants’ proposed angular plane measured from adjacent properties to the north of the application site is illustrated at Fig. No.7.

 

The merit of applying an “angular plane”, and different approaches to measuring angular planes (e.g. the Yonge Steeles Study recommends a 1:2 angular plane for the study area), needs to be considered.  The recommendations of the Town’s current Built Form Study are anticipated to come forward to DSC in April 2010, and should be applied to the subject application.

 

Staff will continue to work with the applicant with regard to applying an appropriate angular plane to create a comfortable transition in the built form that respects the character of the neighbouring residential areas and minimizes adverse impacts, such as overshadowing and visual amenity.

 

Transition across the site

The proposed built form ranges between 2 and 8 storeys across the majority of the site, from west to east.  At a point adjacent to the existing signalized intersection on Steeles Avenue East the high-rise residential point towers are proposed on the easterly portion of the site.  The relationship between these components of the redevelopment proposal is illustrated in the three dimensional view shown at Fig. No.5.

 

The proposal has responded, in part, to requests from staff and the Ward Councillor to increase building height across the Steeles Avenue East frontage and along the Don Mills Road frontage where 1 and 2 storey building heights were initially proposed.  Staff will continue to explore issues of height and transition of built form.

 

Grid street pattern

It is important that the new street pattern within the site can evolve over time in order that certain blocks can be more easily redeveloped in the future as buildings or functions become obsolete.  The ideal minimum block size is approximately 80 metres by 80 metres (260ft x 260ft) and the proposal does illustrate a strengthened pattern of streets and blocks that responds to this design objective.

 

Retail Main Street

It is important that the future development presents a strong built edge facing Steeles Avenue East, which is most effectively achieved by placing appropriately scaled buildings comprising active retail / commercial units at grade with residential units above along the southern edge of the site.  It is equally important to acknowledge that due to the busy nature of Steeles Avenue East and the proximity of the site to Highway 404, the Steeles Avenue East frontage might not present a comfortable pedestrian environment.

 

For this reason it is considered appropriate to strengthen the retail function of the main east west internal street by incorporating additional retail frontages along the south side of this street.  This will create a more comfortable and safe pedestrian setting, encouraging people to walk between stores rather than drive, and will better support the viability of stores and businesses.

 

At the detailed zoning and site plan stages of this redevelopment project the applicant will be asked to demonstrate a more robust retail main street, which will require a different treatment or relocation of ramps serving the underground parking garages and provision of street related retail.  This can be achieved through zoning provisions in the future that require a minimum percentage of the street to be framed by a building edge.  Staff will continue to pursue this objective through discussions with the applicant.

 

Status of masterplan concept

The masterplan concept submitted in support of the Official Plan Amendment application allows Town staff, local residents and decision makers to properly assess the potential function, built form and impacts resulting from the proposed change to the Official Plan designation for the subject site.  This will ensure that a clear vision for the redevelopment of the site is well articulated in the Official Plan Amendment in order that future zoning provisions can be crafted to reflect the vision that will lead to good site plan applications in the future.

 

The master plan concept, dated December 16, 2009, will not be approved as part of the current application and does not necessarily reflect the eventual layout and built form for the site.  In its current form, the masterplan concept would not be supported by staff in its entirety.  However, it does provide the necessary basis to enable technical studies and analysis to be generated and, as stated above, it allows for discussions to take place in order that the Official Plan Amendment the subject of this report can be progressed.

 

Working Group

The chronology provided earlier in this report sets out the topics discussed by the Working Group, and minutes from each Working Group Meeting have been kept.  The repeated concerns from the Working Group relate to height and density of the residential component, traffic impact, pedestrian priority, open space provision and ensuring an attractive and accessible retail environment that will be viable.

 

It is proposed that future Working Group meetings will be convened to review the current revised proposal, the first of which will take place prior to the Statutory Public Meeting.  The number and frequency of future meetings will be finalized by staff in consultation with the group and Ward Councillor.

 

Next Steps

It is proposed that a Working Group meeting take place within a few weeks from the date of this report and prior to the Statutory Public Meeting (April target).

 

Staff continue to receive formal comments from external agencies, including the Region of York, which is the approval authority for this Official Plan Amendment and the City of Toronto, which is responsible for the Steeles Avenue East right-of-way.  Other studies and updates thereto submitted in support of the application include Functional Servicing Study, Traffic Impact Study, Planning Rationale Report and Shadow Study, and these are being reviewed by the appropriate Town departments.  Additional studies will be requested when applications for zoning and site plan are submitted.  These include, but are not limited to: Noise Impact Study, Tree Inventory and Protection Plan, Urban Design Guidelines, Wind Study, Illumination Plan, public open space provision and connectivity.

 

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

Not applicable at this time.

 

 

HUMAN RESOURCES CONSIDERATIONS

Not applicable

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

Subject to revisions, the proposal presents a potentially beneficial redevelopment and intensification project in accord with the Town’s Growth Management objectives (transit oriented development, mixed use, sustainability initiatives, development phasing).

 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The application has undergone a full circulation to obtain comments and conditions from all internal departments and external agencies.

 

 

 

 

 

RECOMMENDED

                            BY:    ________________________          ________________________

                                       Valerie Shuttleworth, M.C.I.P, R.P.P                 Jim Baird, M.C.I.P, R.P.P

                                             Director, Planning & Urban Design                Commissioner, Development

                                                                                                                                Services

 

 

 

ATTACHMENTS:

Figure 1 – Location Map

Figure 2 – Area Context and Zoning

Figure 3 – Air Photo

Figure 4 – Masterplan Concept

Figure 5 – Three Dimensional View

Figure 6 – Site Statistics & Phasing

Figure 7 – Cross Section

Figure 8 – Site Statistics from October 2007 – December 2009