MEMORANDUM
To: Mayor Scarpitti and Members
of Council
From: Jim Baird, Commissioner of
Development Services
Alan Brown, Director of
Engineering
Biju Karumanchery,
Senior Development Manager
Date: May 18, 2010
Subject: Angus Glen Village Ltd – West Village
Phase 2
Plan of Subdivision
19TM-03004 (Phase 2)
South side of Major
Mackenzie Drive, west of Kennedy Road
4071 Major Mackenzie
Drive
SU
03 109045 001
RECOMMENDATION
That
the draft Zoning By-law Amendment attached to the report entitled “Recommendation
Report, Angus Glen Village Ltd. – West Village (Phase 2), south side of Major
Mackenzie Drive and West of Kennedy Road – Angus Glen Community. Implementing zoning by-law amendments for the
final phase of a draft plan of subdivision 19TM-03004, File Numbers ZA
08-120708 and SU 03-109045” be revised to include the following additional Hold
removal conditions:
That
the Conditions of Draft Plan Approval for Angus Glen Phase 2 (West Village)
19TM-03004 (draft plan approved December 1, 2009) be revised to include the
following additional conditions of draft plan approval:
·
The Owner acknowledges and understands that 2011 servicing
allocation is dependent on the Owner constructing a bridge crossing of Angus
Glen Boulevard connecting the East Village to the West Village prior to
December, 2010.
·
The Owner shall provide the Town with an updated
construction schedule and cost estimate for the construction of the bridge
crossing of Angus Glen Boulevard.
·
The Owner acknowledges and understands that the Town may
require additional securities for the construction of the bridge crossing of
Angus Glen Boulevard.
·
The Owner acknowledges and understands that building permits
will not be issued for lots within Phase 2 with 2011 servicing allocation until
a letter confirming that a tender has been issued for the construction of the
bridge crossing of Angus Glen Boulevard and updated construction schedule and cost
estimates have been provided to the Town, to the satisfaction of the Director
of Engineering.
BACKGROUND
Further
to the staff report on this matter dated May 18, 2010, this memo provides staff
comments with respect to the construction of the bridge connecting Angus Glen
West Village and the East Village.
The
Servicing Allocation report requires Angus Glen to construct the bridge between
East and West Village by December 2010 in order to qualify for 2011 servicing
allocation for Phase 2. Angus Glen agreed
to construct the bridge as part of the West Village Phase 1 subdivision
agreement executed in July, 2008. To
secure for the construction of the bridge, the Owner posted a financial security
of $1.8 million plus a 10% contingency.
The
bridge design has been peer reviewed and approved by the Town and the Toronto
and Region Conservation Authority (TRCA) has agreed to the location of the
bridge. The construction of the bridge
was scheduled to commence in July 2010 and to be completed this fall. The Owner has applied for subdivision
agreements and applied for building permits for lots within Phase 2 lands.
However, on May 6, 2010 the Town
received a letter from the applicant’s consultant advising that due to the recent
issues around Redside Dace and its endangered species designation, the Ministry
of Natural Resources would require additional permits for works within Bruce
Creek. The current permitting process is
upwards to six months or more and the work can only be done within the fisheries
window (July 1 to September 15) thereby making it difficult to commence bridge
construction this year. A number of
projects throughout the Town have been experiencing similar delays. The construction of the bridge is expected to
commence in the Spring of 2011, partly due to the
fisheries window. Staff
were not aware of this issue at the time the May 18 recommendation
report was being drafted.
Given recent events, and in order to ensure
timing of this bridge related to Phase 2, staff recommends that additional hold
provisions be added and that conditions of draft plan approval be revised
accordingly.
Additional Hold Provisions
The draft
Zoning By-law currently contains hold provisions related to servicing
allocation as required by the Region of York and site plan approval
requirements. The condition associated
to servicing allocation requires that the bridge be constructed. The Engineering Department has advised that
they would be agreeable to building permits being issued for Phase 2 lands if
the Director of Engineering is satisfied with the following additional
information being provided:
The
Zoning By-law will be revised to reflect these additional requirements before
it is brought forward for Council approval.
Draft Conditions to be added
Draft
plan approval has been issued for Phase 2 lands in December, 2009. The draft plan conditions will be revised to
include the following additional draft conditions:
The Owner
acknowledges and understands that 2011 servicing allocation is dependent on the
Owner constructing a bridge crossing of Angus Glen Boulevard connecting the
East Village to the West Village prior to December, 2010.
The Owner shall
provide the Town with an updated construction schedule and cost estimate for
the construction of the bridge crossing of Angus Glen Boulevard.
The Owner
acknowledges and understands that the Town may require additional securities
for the construction of the bridge crossing of Angus Glen Boulevard.
The Owner acknowledges
and understands that building permits will not be issued for lots within Phase
2 with 2011 servicing allocation until a letter confirming that a tender has
been issued for the construction of the bridge crossing of Angus Glen Boulevard
and updated construction schedule and cost estimates have been provided to the
Town, to the satisfaction of the Director of Engineering.