Report to: Development Services Committee                              Report Date: June 1, 2010

 

 

SUBJECT:                         Train Anti-Whistling at Rail Crossings/Uxbridge Subdivision Rail Status Update

 

PREPARED BY:              Alan Brown, Director of Engineering

                                           

 

RECOMMENDATION:

 

1.      THAT the report dated June 1, 2010, entitled “Train Anti-Whistling at Rail Crossings/Uxbridge Subdivision Rail Status Update” be received;

 

2.      AND THAT staff report back to Council in Fall 2010 to provide a status update on the cost of works to be completed, status of the insurance and indemnification agreements, Agency approvals, Region of York funding agreement and project schedules.

 

1. Purpose       2. Background         3. Discussion        4. Financial      5. Others (Strategic, Affected Units)        6. Attachment(s)

 

 

PURPOSE:

The purpose of this report is to provide Council with an update on the status of train anti-whistling at rail crossings on the Uxbridge Subdivision rail line in Markham.

 

BACKGROUND:

Uxbridge Line - Description

The Uxbridge Line runs generally in a north-east direction and is owned by GO Transit and operated by CN on their behalf. The most southerly rail crossing is located on Steeles Avenue and the most northerly rail crossing is located on 19th Avenue. In total, there are 16 level rail crossings of which seven are under the jurisdiction of York Region, one is under the jurisdiction of the City of Toronto and the remaining eight crossings are under Markham’s jurisdiction. Most of the rail crossings are fitted with safety features to properly provide advanced warning and restrict road users from entering the rail crossing while in operation. Some of the key safety features include bells, gates, and flashing lights. Other safety features includes traffic signs, pavement markings and fences.

 

In October 2008 the Town received the completed Whistle Cessation Study from Aecom outlining the existing safety deficiencies and the mitigation measures recommended at the level rail crossings.  The principle findings of this report were presented to the Development Services Committee on March 3, 2009 and can generally be summarized as follows:

 

    1. General mitigation measures required:

                                                              i.  signs and pavement installations / relocations

                                                            ii.  sightlines to be corrected

 

    1. Specific mitigation measures required:

                                                              i.  Eureka Street – Sightline Issues (Driveway/Garage Obstruction)

                                                            ii.  Bur Oak Avenue –Re-grade existing approaches ( 2% grade maximum)

 

 

 

 

 

OPTIONS/ DISCUSSION:                                            

Engineering Issues

As part of the status update report to Development Services Committee on March 3, 2009, staff were requested to proceed with the next steps identified within the March update report and to provide Council with a status update.   The following is a brief list of the activities undertaken since the Spring of 2009.

 

·      In April 2009, staff met with representatives of GO Transit and Region of York to review the next steps of the anti-whistling study.

·      Following the April 2009 meeting, and through consultation with GO Transit and Transport Canada, it was confirmed that a Pedestrian Study would also be required for each of the crossing locations required.

·      In May/June 2009, staff prepared a Terms of Reference and retained a consultant to complete the Pedestrian Study.

·      In June 2009, staff provided notification to the required relevant organizations as required under the Railway Safety Act of Markham’s intent to pass a resolution forbidding the use of train whistles along the Uxbridge Train Line.

·      In July 2009, staff met with the homeowners of 16 Euclid Street to discuss the options for the possible relocation of the homeowner’s driveway and garage which front on to Eureka Street immediately south of the rail line.

·      In July/August 2009 the field work required for the Pedestrian Study was completed.

·      In late September 2009, the completed Pedestrian Study report was provided to the Town.

·      In the Fall of 2009, copies of the completed Whistle Cessation Study and Pedestrian Study were provided to the required stakeholders (CN, GO Transit, and the Region).

·      The Town has retained Aecom to identify and develop the specific upgrades required at each crossing and to assist the Town with "negotiations" with major rail stakeholders, including GO Transit, Transport Canada, and Canadian National Railway.

 

Specific Mitigation Issues

 

Eureka Street

Following the meeting with the home owner of 16 Euclid Street and based on the findings of the two completed studies (Whistle Cessation and Pedestrian Study), the following was identified:

·      The homeowner is prepared to review and explore options with the Town to address the safety concern identified within the Whistle Cessation Study, including the possible relocation of their driveway and garage currently fronting onto Eureka Street.

·      Aecom, the Town’s consultant, estimates the cost to relocate/reconstruct the driveway and garage to be in the order of $50,000-60,000.

·      The need to address the driveway and garage on Eureka Street was first identified in the Whistle Cessation Study.  Upon further work completed by Aecom for the Pedestrian Study Aecom has provided a figure (See Attachment “A”) that illustrates the existing and required sightlines in this area.  The figure notes that the sightlines in this area are “at the minimum level” based on Transport Canada’s minimum sight line requirements for this type of crossing.

 

Pending the outcome of the Stakeholders Meeting planned for Spring 2010 (See “Schedule” below), the Town will hold further discussions with both the homeowners of 16 Euclid Street and Aecom so that staff can report back to Council on a recommendation to deal with the driveway and garage adjacent to the rail line.

 

Bur Oak Avenue

Staff have discussed the need to re-grade a portion of the approach to the rail crossing at Bur Oak Avenue with GO Transit and the Region since the current grade exceeds the maximum allowable by Transport Canada Guidelines (i.e. 2%).  This issue will also be reviewed and addressed at the planned Stakeholders Meeting.

 

Schedule

The Town has completed the Whistle Cessation Study and the Pedestrian Study required by the stakeholders.  The Town has also met with some of the key stakeholders such as GO Transit and the Region of York to review the crossing options available at each of the crossings and has provided notification to the CN Labour Unions.  The following activities, including reports to Council for approved, are planned for 2010 (subject to agency approvals and report back to Council in the Fall of 2010):

 

·      Meet with key stakeholder group (Transport Canada, CN, GO Transit, and the Region) to review the findings from the completed reports and to agree on the items to be mitigated at each of the crossings.  An “Upgrade List”, summarizing all of the works to be completed, will be prepared from the stakeholders meeting and used by the Town to design and implement the upgrades required.  The Town is trying to schedule this meeting for June 2010.

·      Prepare and issue formal public notification (Late June 2010).

·      Following the stakeholder meeting, and upon development of the Upgrade List, the Town will then work with CN and GO Transit to complete the insurance and indemnification if any of the Town’s and Region’s crossings.  The upgrade list will also confirm the extent of the Bur Oak re-grading requirements as well as detail the works required on Eureka Street (Summer 2010).

·      Proceed with crossing improvements (Late 2010/Spring 2011) subject to council and funding approval.

·      Transport Canada railway safety inspection of crossings (Summer/Fall 2011).

·      Implementation of anti-whistling by-law and whistling cessation (Late Fall 2011).

 

For a complete updated schedule see Attachment “B”. 

 

FINANCIAL TEMPLATE

The amount of $446,180 has been budgeted for the train whistle cessation project in accounts 640-101-5699-6501 ($128,280) and 640-101-5699-9288 ($317,900) for capital works associated with train whistle cessation. Staff will update the cost estimates in the September 2010 report based on Transport Canada requirements.

 

 

 

DEPARTMENTS CONSULTED AND AFFECTED:

The Finance Department have reviewed and as presented at the June 10, 2008 Development Services Committee meeting, from a Risk Management perspective Finance staff and the

Town’s insurer do not support anti-whistling.  According to the Railway Association of Canada, train whistles are vital safety features that protect motorists and pedestrians from collisions at public roads and pedestrian rail crossings. Finance staff, our insurer and the Railway Association of Canada believe that train whistles save lives.

 

 

 

 

 

RECOMMENDED BY: 

 

 

 

 

 

________________________                                    ________________________

Alan Brown, C.E.T.                                                    Jim Baird, M.C.I.P., R.P.P.

Director, Engineering                                                  Commissioner, Development Services

 

ATTACHMENTS:

Attachment “A” – Eureka Street Sightlines

Attachment “B” – Updated Project Schedule