Report to: Development Services Committee Date Report Authored: June 1, 2010
SUBJECT:
PREPARED BY: Gabor Szakter, Engineering
Elizabeth Wimmer, Senior Planner, Urban Design
RECOMMENDATION:
1) Report
entitled “
2) That the final detailed design for the reconstruction of Warden Avenue from 16th Avenue to Major Mackenzie Drive by the Region of York be endorsed, as outlined in this report;
3) And that the following works and funding be approved;
4) And that a new 2010 Capital project be created within the Operations Department to include $156,600 for the diversion of existing storm flow from an existing culvert at 14 Cachet Parkway to the sewers on Warden Avenue, to be funded from the Life Cycle Replacement Capital Reserve;
5) That the streetscape design “Option B” prepared by the Region of York be endorsed;
6) That staff be authorized to submit an application to the Municipal Streetscape Partnership Program offered by Region of York and that the Town allocate funding of $65,000 from Town account 640-101-5699-7076 towards the installation of enhanced streetscape planting for this area;
7) That the Director of Engineering and the Director of Planning and Urban Design be authorized to finalize any future revisions to the streetscape plans as prepared by the Region of York;
8) And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
1. Purpose 2. Background 3. Discussion 4. Financial
The purpose of this report is to:
·
Update Council on the conditions in the
· Update Council on the status of the project and construction schedule.
· Obtain approval to issue a purchase order to the Region for the sidewalk, multi use pathway, illumination and storm sewer works to divert existing storm flow based on the actual tender prices.
· Seek endorsement for the enhanced streetscape plan and to apply to the Region of York for the Municipal Streetscape Partnership Program award funding.
The widening of Warden Avenue from 16th Avenue to Major MacKenzie Drive, as shown on Attachment ‘A’, by the Region is the last phase of the road widening based on the recommended improvements in the June 2001 Environmental Study (EA) for Warden Avenue from Steeles Avenue to Major MacKenzie Drive. The Region’s detailed design has been completed and construction is to commence in Fall 2010 with completion in late 2012. Approval from Ministry of Ministry of Natural Resourses may delay the creek crossing structures until 2011 but site preparation and some road works may start this year.
DISCUSSION
Council Resolution
The staff report, dated June 26, 2001 entitled, “Region of York Environmental Assessment Warden Avenue Improvements – Steeles Avenue to Major Mackenzie Drive – North Section 16th Avenue to Major Mackenzie Drive” was approved by Council subject to the conditions discussed in this report:
· The impact of the proposed construction on the Warden Hemlock Woods, Berczy Creek and Carlton Creek be reviewed in greater detail and that measures to minimize these impacts be incorporated into the detailed designs for the project, including opportunities for continuous pedestrian pathway systems.
· The Region be requested to fund the construction of raised, landscaped center medians throughout the project where feasible and that the location and extent be determined in consultation with the Town during the detailed design.
· The feasibility of providing pedestrian cross-overs with median refuge islands to be reviewed in consultation with the Town during the detailed design phase of the project.
· That the Region conduct public meetings prior to the start of construction to provide residents with details of the proposed construction activities, project schedule and mitigating measures to be implemented.
A)
Widening of
The widening of
· The construction of a four-lane cross-section. The installation of left turn lanes are only proposed where required, instead of a continuous centre left lane, which reduces the grading impact within the right-of-way (R.O.W.) and decreases the impact on the Warden Hemlock Woods, Carlton Creek and Berczy Creek.
· The installation of a 0.6m wide coloured concrete strip on both sides of the boulevard behind the curb at the Region’s cost, to minimize unnecessary winter salt damage to the boulevard landscaping.
· The installation of a 2.5m wide concrete Multi Use Pathway (MUP) in the east boulevard, from 16th Avenue to Major Mackenzie Drive, at the Town’s cost.
· The installation of 1.5m wide concrete sidewalk in the west boulevard from 16th Avenue to Calvert Road and from Cachet Parkway to Major Mackenzie Drive at the Town’s cost.
· The installation of streetlights on both sides of the road at the Town’s cost.
· The re-alignment of Glenbourne Park Drive to reduce the sharp angle at the Warden Avenue intersection and improve safety at the intersection. Since the re-alignment affects access to #4 and #6 Glenbourne Park Drive, a cul-de-sac is proposed to branch off from Glenbourne Park Drive to provide access. Region and Town staff have contacted the residents at #4 and #6 Glenborne Park Drive and are continuing the consultation process.
Based on the
As outlined in the
B)
Streetscape Design
The streetscape design on Warden Avenue, as shown in Attachment ‘C’, highlights the following measures to be implemented by the Region:
· The impact of the proposed construction on the Warden Hemlock Woods, Berczy Creek and Carlton Creek have been reviewed in greater detail, and measures were introduced to minimize these impacts, such as reducing the footprint of the road and boulevard, where possible.
In the June 26, 2001 Council
resolution, the Region was requested to review if raised landscaped centre
medians could be provided throughout the project. Staff examined the feasibility of this item
and recommend that islands not be considered.
Staff has worked with the Region to eliminate the continuous centre turn
lane, and provide left turn lanes only where required. The only opportunity for
a landscaped median is from
Existing Vegetation
A detailed Tree Preservation
Report has been prepared by Ecoplans on behalf of the Region. Urban Design staff has reviewed the report
and are satisfied with the proposal to achieve significant planting to mitigate
and offset the overall loss of vegetation in this area.
The Warden Hemlock Woods is a
locally significant area as described in the Town of
Streetscape Options
The widening of Warden Avenue from 16th Avenue to Major Mackenzie will have an impact on the existing vegetation on the west side of Warden Avenue. In order to mitigate the impact of this street widening on the natural features, The Region has prepared two streetscape design options for Warden Avenue. In both options, the tree planting strategy is in addition to the vegetation that will be replaced due to the vegetation loss, resulting from the road widening.
· “Option A” identifies regular street tree planting with limited naturalized planting adjacent to the Berczy Creek watercourse and the edge of the Warden Hemlock Woods.
·
“Option B” identifies an enhanced planting
scheme which identifies additional vegetation along the length of the R.O.W.
from
Streetscape Fund
The Region has established a “Municipal Streetscape Partnership Program” which enables communities within the Region to apply for enhanced streetscape on Regional roads. It is the requirement of the Region that the Town applies to the streetscape fund prior to the end of June of each year. In order to apply for the streetscape fund the Region has the following requirements:
a) The municipality is to provide 50% of the cost of the work to be undertaken.
b) The municipality is responsible to prepare design drawings and a cost estimate for review and evaluation by the Region. In anticipation that the Town is applying for the streetscape funding, the Region has completed the streetscape design and cost estimate.
c) A Council resolution is required to accompany the application.
The Region’s budget for Streetscape Option “A” is approximately $200,000. Urban Design recommends Streetscape Option “B”, which utilizes the “Municipal Streetscape Partnership Program”. The Town will fund $65,000 of the enhancement and, in turn, will apply for an additional $65,000 of funding through the Region. Therefore, Option “B” will have an estimated budget of $330,000.
There was a Public Information Centre held by the Region on March 30, 2009 to provide an overview of the project.
Prior to and during construction, the Region will be consulting with individual residents, on an as-needed basis, to provide details of the proposed construction activities, project schedule and mitigating measures to be implemented.
D)
Cachet Storm Sewer Diversion
During the construction of Cachet Estates, in the 1960’s, a block of land owned by the Town was established between #12 and #14 Cachet Parkway, as per Attachment ‘D’, for the construction of a storm sewer outfall from a ditch inlet catchbasin (on the east side of Cachet Parkway) to the natural watercourse running behind these properties. Instead of the storm sewer outfall being constructed in this block, it was constructed through private property at 14 Cachet Parkway as shown on Attachment ‘D’. The owner of 14 Cachet Parkway has approached the Town on several occasions requesting removal and relocation of the storm outfall to the Town-owned block of land (originally secured for the storm outfall) located adjacent to the north property line.
The relocation of the outfall to the existing easement would cost approximately $200,000 and require removal of several mature trees which are located in the back of these properties. Through discussions with the Operations Department and the Region, a more desirable solution to divert this storm water runoff and outfall towards the proposed storm sewer at Warden Avenue was recommended.
The cost estimate for the storm sewer diversion is $156,600. This storm sewer diversion is not included in the Operations Department’s current life cycle reserve study but will be added to the reserve study update, to be presented to Council in the Fall, 2010. Staff is recommending that a new 2010 Capital project be created within the Operation Department to include $156,600 for the diversion, to be funded from the Operations Department storm sewer life cycle reserve.
The following financial considerations are required:
Warden Avenue is an important arterial route that provides a high volume of daily commuters through York Region. By respecting the adjacent vegetation, the footprint of the widening has been minimized through the elimination of a continuous left-turn lane and providing a narrower boulevard. By utilizing a multi-use path and enhanced landscaping, the corridor is improved for pedestrian and cyclist use. The project supports the Town’s strategic priorities including Growth Management, Transportation/Transit, and Environmental Sustainability.
The
RECOMMENDED BY:
________________________ ________________________
Alan Brown, C.E.T. Jim Baird,.M.C.I.P., R.P.P.
Director of Engineering Commissioner of Development Services
‘A’ – Key Map of Proposed
‘B’ – Cross-sections of
‘C’ - Streetscape Option ‘B’
‘D’ - Town-owned block at #14 Cachet Parkway
Q:\Development\Engineering\REPORTS\2010\June\Warden Ave Widening June 1, 2010.doc