Report to: Development Services Committee                            Report Date: June 15, 2010

 

 

SUBJECT:                         Status Update for the completion of South Unionville Avenue

PREPARED BY:              Alan Brown, Director of Engineering, Ext. 7507

                                            Alain Cachola, Manager, Capital Administration Ext 2711

                                           

 

RECOMMENDATION:

1)      That the report entitled “Status Update for the completion of South Unionville Avenue” be received;

2)      And that staff be authorized to continue to negotiate with the South Unionville Landowners Group / Developers with respect to the funding and construction of the 3rd section of South Unionville Avenue Extension;

3)      And that if the negotiations are not finalized by June 15, 2010 to enable the road to be completed by the end of 2010, the Town provide interim funding for the road construction as follows:

                                i.            Council authorize the Mayor and Clerk to execute a development servicing agreement and reimbursement agreement with Jade-Kennedy Developments, in a form satisfactory to the Chief Administrative Officer and Town Solicitor for the construction of the 3rd Section of South Unionville Avenue including miscellaneous fees.

                              ii.            And that the local component of the 3rd section of South Unionville Avenue extension in the estimated amount of $470,000 be temporarily funded from the Pre-DCA Reserve Account (087-2800-160);

                            iii.            And that the funding of the local component of the road ($470,000) be recovered from the future development fronting the 3rd section of the South Unionville Avenue Extension;

                            iv.            And that the oversizing component (i.e. 3rd and 4th lane) of the 3rd section of South Unionville Avenue in the estimated amount of $130,000 be funded from the Town Wide Hard Development Charges Reserve Account;

                              v.            And that the Engineering Department’s 2010 Capital Budget be amended to include $600,000 for the design, contract administration and construction the 3rd section of the South Unionville Avenue extension to be funded from the Town Wide Hard Development Charges Reserve in the amount of $130,000, and Pre-DCA Reserve Account (087-2800-160) in the amount of $470,000;   

4)      And that staff be directed to do all things necessary to give effect to this report.

 

EXECUTIVE SUMMARY:

Not applicable.

 

PURPOSE:

 

The purpose of this section of the report is to:

 

a)      Seek Council’s authorization to continue to negotiate with the South Unionville Landowners Group / Developers with respect to the funding and construction of the 3rd section of the South Unionville extension;

b)      In the event that the negotiations are not finalized by June 22, 2010 in order to ensure South Unionville Avenue is completed in its entirety (Kennedy Road to McCowan Road) by year end, seek Council’s approval for the Town to upfront the cost of the local road component with subsequent recovery from the abutting developers. A 0.3m reserve would be placed on the abutting lands to restrict access on the future development onto this portion of road until the funds are repaid. In addition, draft plan conditions are to be applied to the abutting lands requiring them to reimburse the Town.

c)      Council authorization for the Mayor and Clerk to execute a development servicing agreement and reimbursement agreement with Jade-Kennedy Developments, in a form satisfactory to the Chief Administrative Officer and Town Solicitor for the construction of the 3rd Section of South Unionville Avenue is recommended;

 

BACKGROUND:

 

South Unionville Avenue is an east-west collector road identified in the Secondary Plan and is approximately 80% completed. There are currently three (3) missing sections in South Unionville Avenue, as noted on Attachment ‘A’, which need to be completed in order to provide a transportation link from Kennedy Road to McCowan Road and provide an alternate east-west route.  

 

1st Section of the South Unionville Avenue Extension (refer to Attachment ‘A’)

 

Jade Kennedy Development Corporation is currently in the process of having their site plan approved for the construction of a mixed used development at 8333 Kennedy Road.

 

As a part of the proposed development, Jade Kennedy has been requested by the Town to construct the 1st section of South Unionville from Kennedy Road to east of Unity Gardens. The works are included in the Construction Agreement for South Unionville Avenue.

 

The Developer requested Development Charge Credits from the Town for the oversizing component (i.e. 3rd and 4th lane) of South Unionville Avenue. Authorization to enter into a Development Charge Credit Agreement for the oversizing portion of this section of South Unionville Avenue has been approved by Council.    

 

The local component of the road (i.e. 1st and 2nd lane) is being financed by Jade-Kennedy Developments who will be receiving credits from the Group Cost Sharing Agreement of the South Unionville Landowners Group.  

 

2nd Section of the South Unionville Avenue Extension (refer to Attachment ‘A’)

 

The Town has recently acquired the lands at 144 and 150 Helen Avenue that is required of the South Unionville Avenue Extension. The Town has negotiated with Jade Kennedy Development Corporation to construct this section of the road as a part of their proposed development. The works are included in the Construction Agreement for South Unionville Avenue.

 

The Developer requested Development Charge Credits from the Town for the oversizing component (i.e. 3rd and 4th lane) of South Unionville Avenue. Authorization to enter into a Development Charge Credit Agreement for the oversizing portion of this section of South Unionville Avenue has been approved by Council.   

 

The local component of the road (i.e. 1st and 2nd lane) is being financed by Jade-Kennedy Developments who will be receiving credits from the Group Cost Sharing Agreement of the South Unionville Landowners Group. 

 

3rd Section of the South Unionville Avenue Extension (refer to Attachment ‘A’)

 

Town staff is continuing to negotiate with the South Unionville Land Developers Group and abutting developers to finalize the funding of the local component of the road. If the negotiations of the funding do not get resolved by June 15, 2010, staff recommends the Town to upfront the cost of the local component of the road ($470,000) from the Engineering Pre-DCA reserve to ensure that the South Unionville Avenue Extension from Kennedy Road to McCowan Road is completed in 2010.  

 

The Town has been in discussions with Jade-Kennedy Developments to include the 3rd portion of the South Unionville Avenue as a part of their proposed construction Contract for the 1st and 2nd road section. Jade-Kennedy Development has agreed in principle that they will construct the road as long as the funding is provided by the Town or the South Unionville Land Developers Group / abutting Developers for the local component (1st and 2nd Lane) of the road. The funding for the oversizing component of the road (i.e. 3rd and 4th Lane), estimated at $130,000, is included in the Town’s 2008 Development Charge Background Study and can be funded from such. In addition to the construction costs, miscellaneous costs such as consultant fees, administration fees, etc. are to be paid.  Jade-Kennedy has advised that Sections 1 and 2 of South Unionville will be under construction in June 2010 and they would need authorization to proceed with Section 3 by June 22, 2010 to ensure that their contractor can undertake this work in July 2010 before leaving the site.

 

FINANCIAL CONSIDERATIONS

 

The estimated cost of constructing the 3rd section of South Unionville Avenue totals $600,000. The funding recommended is $130,000 from the Town Wide Hard DC Reserve and $470,000 from either the South Unionville Land Developers Group or the Town’s Pre-DCA Reserve.

 

There is no net financial impact to the Town if the South Unionville Land Developers Group upfronts the cost of the local component of the road which is estimated at $470,000. There is however a reduction in cash flow and a loss of interest estimated at $5,000 to $10,000 per year if the Town upfronts the local component of the road, until this amount is recovered from the future developers fronting on the road. It is anticipated that servicing allocation and draft plan approval for the abutting lands (Kuznel / Filice) should be available by 2014.  

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

 

The completion of South Unionville Avenue provides a necessary east-west collector road between Kennedy Road and McCowan Road south of Highway 7. The collector road provides the transportation capacity for the development of South Unionville which aligns with the Markham’s strategic focus to Growth Management and Transportation / Transit by providing an alternative route and to alleviate traffic congestion on highway 7.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Planning, Finance and Legal Departments have reviewed and commented on this report.

 

RECOMMENDED BY:

 

 

 

 

___________________________                       ___________________________

Alan Brown, C.E.T.                                              Jim Baird, M.C.I.P., R.P.P.

Director of Engineering                                         Commissioner of Development Services

 

 

ATTACHMENTS:

Attachment ‘A’:        Sections of South Unionville Avenue