Report to: General Committee                               Date Report Authored: November, 23, 2009

 

 

SUBJECT:                          Application to Building Canada Fund Stimulus Fund for Demonstration Project - Sanitary Mainline and Sewer Connection Relining in West Thornhill

PREPARED BY:               Peter Loukes, P.Eng., Director, Operations

                                            Ext. 4894

 

RECOMMENDATION:

 

1)                  That the report dated November 23, 2009 entitled “Application to Building Canada Fund Stimulus Fund for Demonstration Project - Sanitary Mainline and Sewer Connection Relining in West Thornhill” be received;

 

2)                  And That the Commissioner of Community and Fire Services be directed to submit an application for a demonstration project as outlined in the report to the Government of Canada and the Province of Ontario under the Building Canada Fund Stimulus Fund program;

 

3)                  And That if the application in recommendation 2) is successful that the Town proceed with the project at an upset limit of $7,500,000 on a 1/3 shared basis with the Province of Ontario, and Government of Canada and the Town of Markham;

 

4)                  And That if the application in recommendation 2) is successful that the Town of Markham’s share of $2,500,000 for the project be funded from the 2010 Sanitary Sewer System Upgrade/Rehabilitation Program budget, and the remaining budget from 2009 and 2008 Sewer System Upgrade Program;

 

5)                  And That staff be authorized to release a Request for Proposal (RFP) to the market place for construction of Sanitary Mainline and Sewer Connection Relining in West Thornhill;

 

6)                  And That Council delegates the award authority for the construction of the Sanitary Mainline and Sewer Connection Relining in West Thornhill to the Chief Administrative Officer (CAO);

 

7)                  And That if the application in recommendation 2) is successful, that the authority for the approval of tendered Consulting Services for design, contract management, project administration and inspection be delegated to the Commissioner of Community and Fire Services.

 

8)                  And That if the application in recommendation 2) is successful, that the authority for the approval of the Third Party Evaluator Consultant be delegated to the Commissioner of Community and Fire Services.

 

9)                  And Further that Staff be authorized and directed to do all things necessary to give effect to this resolution.

 


PURPOSE:

1.            To obtain approval to submit a request for funding to the Federal and Provincial governments under the Building Canada Fund (BCF) Stimulus Fund grant program for a demonstration project to reline sanitary sewer connections in West Thornhill.

 

2.            To obtain approval from Council, if application for funding is successful, to issue a Request for Proposal (RFP) for the demonstration project utilizing new innovative product and installation methods of sewer relining and award authority for the construction of the Sanitary Mainline and Sewer Connection Relining in West Thornhill to the Chief Administrative Officer (CAO).

 

3.            To obtain approval from Council, if application for funding is successful, that the authority for approval of consulting services RFP for design, contract management, project administration and inspection of the Sanitary Mainline and Sewer Connection Relining in West Thornhill project be delegated to the Commissioner of Fire and Community Services.

 

4.            To obtain approval from Council, if the application for funding is successful, that the authority for approval of the Third Party Evaluator consultant for this project be delegated to the Commissioner of Fire and Community Services.

 

BACKGROUND:

The West Thornhill area has been flooded in recent years by major rainfall events. While the Town is currently undertaking an Environmental Assessment Study to determine the appropriate level of flood protection for the area, Waterworks has implemented an inflow and infiltration (I/I) reduction strategy for the sanitary sewer system that will provide adequate capacity even for a 100 year storm events.

 

One area identified for improvement was controlling storm water from entering the sanitary sewers in flood prone areas so that those sewers do not become overwhelmed during major storms and flood basements.  

 

Pilot programs such as the “Every Downspout Counts”, which helps residents disconnect roof downspouts identified as being connected to the sanitary sewer, have helped to reduce the flow of storm water directly into the sanitary sewer.  However, in the older areas of Town it has been shown that storm water can infiltrate the ground and find its way into the sanitary sewers through various cracks and leaks in the mainline sewers as well as in the service connections to each house.  Spot repairs can help to stop the infiltration, but if cracks and fractures continues, eventually sewers and especially service connections will need to be relined or replaced.

 

Waterworks has implemented an Inflow and Infiltration (I/I) Reduction Strategy. Evaluation of the various I/I reduction measures are being tested in the Grandview Avenue pilot area shown in Appendix “A”. This pilot area has been observed to have high I/I equivalent to over three (3) times the I/I design allowance during an equivalent 5 year storm condition.

 

The multi-stage remedial inflow / infiltration (I/I) Reduction Strategy in this pilot area have an estimated potential peak extraneous flow rate reduction as follows:

 

               Roof Downspout Disconnection Program – 10-15%

               Manhole Lid and Chimney Sealing – 30-35%

               Lining of Mainline Sanitary Sewers and Laterals – 35-40%

 

During major storm events, roof downspout disconnection from sanitary system and manhole sealing remedial measures have the biggest impact on reduction of the peak I/I in the system (from 50 to 70%). In order to provide the Town design standard level of service protection against basement flooding, it is essential that all three I/I reduction measures be implemented.

 

Roof downspout disconnection program and manhole lid sealing has been completed in the pilot area. The lining of both sanitary mainline sewers and laterals up to the house is estimated to reduce at a maximum 20-30% of the annual volume in the sewer system.  With improved hydraulic pipe conditions existing pipe flow capacity will be increased. Further, sewer lining is expected to extend the life expectancy of the sanitary collection system by a minimum of 50 years.

 

When completed, the three strategy measures should reduce up to 80% of the extraneous flows on the sanitary sewers system and should provide basement flooding protection independent of the storm events. Approximately, 20% of flow from various minor sources cannot be fully eliminated.

 

OPTIONS/ DISCUSSION:

 

Stimulus Funding is Still Available

The Town has had several discussions with both the Federal and Provincial governments and has identified that there is still uncommitted stimulus funding available. Senior management and staff determined that the funding from the BCF Stimulus program would be beneficial for the I/I reduction project for lining of mainline sanitary sewers and laterals within the pilot area project. This will complete the strategies for I/I reduction within the pilot area.

 

Organizing and executing the relining work is straight forward and is deemed repair/maintenance work so it does not require an EA or other such approval.  The work can be done year round and the March 31st 2011 deadline is not an issue provided that decisions on funding and contract awards are done expeditiously.

 

The Demonstration Project could be up to $7.5M in scope

Appendix ‘A’ shows the proposed “Pilot” project area. The area consists of 9,014 m of sanitary sewers and 760 laterals. The estimated cost of $7.5M includes the relining of the sanitary mainline and lateral sewers, consulting services for design and contract administration and inspection, including third party project post evaluation. In anticipation of I/I reduction projects in the Thornhill area, Waterworks held off on their sewer rehabilitation projects for 2008/ and 2009. The remaining budget amount for these projects including the 2010 Sanitary Sewer System Rehab Annual Program will meet the $2.5M share towards this funding application.

 

As a demonstration project, it is intended that new eco friendly materials for trenchless sanitary sewer relining installation will be specified. A new method of relining sewer laterals from the mainline without intervention or excavation will be established and specified. Various liner design parameters and materials will be tested and installed. Post evaluation of the liners will be conducted to determine the best relining solution for various sewer conditions and to determine the estimated lifecycle extension. Improvement in the flow capacity due to increase in pipe flow coefficient will also be verified.

 

The proposed work for this Stimulus Funding project for sanitary mainline and sewer connection relining will complete the strategy of I/I reduction within the Grandview pilot area. It will allow staff to measure and evaluate the impact of the I/I reduction strategies and will verify any sewer pipe capacity improvements. From the conclusions and results of the various strategies, staff will have the ability to determine the most effective solution for reduction of inflow and infiltration that will provide the best return on investment and will bring the sanitary sewer system to Town standard level of protection.

 

This will position the Town as a leader in green technology of trenchless rehabilitation methods for I/I reduction by using environmentally friendly products. It will also demonstrate the complete trenchless method of sanitary sewer lateral rehabilitation from the mainline to the house.

 

External Consulting Services Requirements

To complete this project on time as required under the Stimulus Funding program, external consultants for design, contract management, project administration and inspection including third party project evaluation will be contracted. An RFP or tender will be issued for this external consultant needs. To expedite the contract award process, authority is recommended to be delegated to the Commissioner of Community and Fire Services for award of the consulting services contracts. The cost for consulting services for design, contract management, project administration and inspection for construction contract is about 12% of the construction cost.

 

Third Party Project Review and Assessment

To assure independent assessment of the lining technologies, material strength and calculated capacity improvement, Waterworks is proposing to engage University of Waterloo staff led by associate professor Mark Knight. Their service will include pre and post lining in field pipe flow capacity, assessment of final product for various liner gauges and preparation and submission of final report. This third party independent assessment cost estimated to be 0.5% of the project cost. $50K is accounted for this service and approval is also recommended to be delegated to the Commissioner of Community and Fire Service.

 

FINANCIAL CONSIDERATIONS AND TEMPLATE:

The funding formula is based on a 1/3 shared basis with the Province of Ontario, Government of Canada and the Town of Markham. The following table outlines the Town’s Funding Sources:

 

Project Acct#

Project Name

Budget

Actual

Budget Remaining

53 6150 8334 005

Sewer System Upgrade Program

              1,300,000

                    413,450

                     886,550

53 6150 9282 005

Sewer System Upgrade/Rehabilitation Program - Annual

              1,300,000

                         -  

                   1,300,000

53 5350 10330 005

Sanitary Sewer System Upgrade/Rehab Program - Annual

              1,328,000

                         -  

                   1,328,000

 

 

              3,928,000

                    413,450

                   3,514,550

 

Under this new application to Building Canada Fund, works on storm sewers rehabilitation for West Thornhill are not included as all proposed measures such as downspout disconnection, flow balancing, sewer upgrades relates to each other and should be implemented together based on project phasing which cannot meet the funding completion deadline of March 31, 2011.

 

HUMAN RESOURCES CONSIDERATIONS

Not Applicable

 

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

This project aligns with the strategic priorities of Environment and Municipal Services as it addresses flooding issues and concerns

 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Finance

 

 

RECOMMENDED

                            BY:    ________________________          ________________________

                                      Brenda Librecz                                 Peter Loukes, P.Eng.

                                      Commissioner, Community and           Director, Operations

                                      Fire Services                                     

 

ATTACHMENTS:

Appendix ‘A’ – Proposed Thornhill Sewer Relining CBF Demonstration Project

 

 

Q:\Commission Share\Operations and Asset Management\ Reports\ 2010\ Waterworks\ Application to Building Canada Fund Stimulus Fund for Demonstration Project – Sewer Connection Relining in West Thornhill