Report to: General Committee                                  Date Report Authored: February 17, 2010

 

 

SUBJECT:                          Award of Tender 027-T-10, Additions and Renovations of Thornhill Community Centre and Library

PREPARED BY:               Glen Taylor, Ext.  3180

                                            Tony Casale, Ext. 3190

 

 

RECOMMENDATION:

1)                  That staff report entitled “Award of Tender 027-T-10, Additions and Renovations of Thornhill Community Centre and Library” be received;

 

2)                  And That the contract for Tender 027-T-10, Additions and Renovations of Thornhill Community Centre and Library be awarded to the lowest price bidder, Charterhouse Projects Inc. in the amount of $3,140,000 exclusive of GST;

 

3)                  And That a construction contingency be established in the amount of $471,000 (15% of construction award) exclusive of GST be established to cover any additional construction costs and that the Director of Recreation Services be authorized to approve the expenditure of this contingency amount up to the specified limit and to provide a monthly statement of these expenditures to the Town Treasurer;

 

4)                  And That a architectural services contingency be established in the amount of $47,000 (13 % of architectural services award) exclusive of GST to cover any additional consultant costs and awarded to W.K. Lim Architect, and that the Director of Recreation Services be authorized to approve the expenditure of this contingency amount up to the specified limit and to provide a monthly statement of these expenditures to the Town Treasurer;

 

5)                  And That an additional amount of $50,000 exclusive of GST be allocated to FF&E budget (increasing from $710,000 to $760,000);

 

6)                  And That staff be authorized to retain a contractor(s) for landscaping and site security to an upset limit of $200,000 in accordance with Purchasing By-Law 2004-341;

 

7)                  And That the Commissioner, Community & Fire Services be authorized to re-allocate the funds identified within recommendations 3,4,5,6 such that the total expenditures do not exceed the allocated funds of $768,000;

 

8)                  And that Staff report back to General Committee on the use of the $539,000 balance remaining prior to June 21, 2010, in compliance with the Infrastructure Stimulus Fund agreement;

 

9)                  And That the Award of Tender 027-T-10 be funded from 070-5350-9515-005 Thornhill CC & Library Renovation;

 

10)              And that Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

PURPOSE:

The purpose of this report is to award the contract for the Additions and Renovations of Thornhill Community Centre and Library through the Building Canada Infrastructure Stimulus Fund.

 

BACKGROUND:

As part of the Federal Stimulus Fund Project, the Town of Markham (Town) received approval for a 1/3 cost sharing agreement with the Province of Ontario, Government of Canada and the Town to construct a new addition and renovate the  Thornhill Community Centre and Library.

 

The scope of work involves the construction of a new extension of approximately three thousand six hundred forty square feet (3,640 sq .ft.) on the south east corner of the Thornhill Community Centre, renovations to the basement (lower level) of approximately ten thousand eight hundred eighty square feet (10,880 sq.ft.), and renovations to the library of approximately five thousand five hundred square feet (5,500 sq.ft).

 

OPTIONS/ DISCUSSION:

Prequalification

Due to the scope of the project, contractors were pre-qualified to ensure that all bidders would have the necessary qualifications, experience and resources to complete the works in accordance with Town of Markham requirements within the specified timelines. Prequalification No. 194-P-09 was issued to the market place in accordance with the Purchasing By-law 2004-341.

PREQUALIFICATION INFORMATION (194-P-09)

Advertised, place and date

October 6, 2009

Prequalification closed on

October 28, 2009

Number of contractors picking up bid documents

82

Number of contractors responding to bid

16

Number of contractors prequalified

4

 

Construction Tender

The construction tender # 027-T-10 was issued in accordance with the Purchasing By-law 2004-341 to the four (4) pre-qualified contractors.

BID INFORMATION (027-T-10)

Tender release

February 3, 2010

Bids closed on

February 17, 2010

Number of contractors picking up bid documents

4

Number of contractors

3

DETAILED PRICING INFORMATION                                                              

 

Contractors

Bid Price*

1

Charterhouse Projects Inc.

$3,140,000.00

2

Struct-Con Construction Ltd

$3,900,000.00

3

Buttcon Limited

$5,026,000.00

*Exclusive of GST

 

Construction, Architectural Services & Project Manager Contingency

Staff recommend a contingency for this project to cover any additional unforeseen requirements that arise during the construction phase.  This project encompasses major renovations to the existing building and based on Staff experience with similar projects, it is prudent to ensure contingency is sufficient to ensure no delays during construction.  Additionally, due to tight timelines of project completion date, Staff may be required to accelerate the schedule.

 

FF & E allocation

Due to favourable pricing received from the construction tender, Staff recommend increasing the FF & E allocation to allow for other components to be purchased (i.e. Security cameras, PA system) that were removed from the construction tender due to cost concerns.

 

Landscaping and Site Security

Certain trees and shrubs will be removed during the construction phase and staff are recommending allocation of funds for enhanced landscaping on-site (i.e. Tree planting) after construction completion.  Due to recent concerns raised regarding traffic, parking and construction site security (i.e. Vandalism), staff recommend hiring a full time site security firm during the construction phase.

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

The following table is a summary of the financial considerations for this report:

 

 

 

 

 

Budget for Construction & Construction Contingency and Architectural Services

 

    $4,800,000

 

070-5350-9515-005  Thornhill CC & Lib Reno

Budget Available  for Construction & Construction Contingency and Architectural Services

 

       $4,447,000

 

 

Less Construction

 

     ($3,140,000)

 

Awarded to Charterhouse Projects

Less Construction Contingency

 

     ($   471,000)

 

Awarded to Charterhouse Projects

Less Architectural Services Contingency

 

     ($     47,000)

 

Awarded to W.K. Lim Architects

Budget Remaining

 

     $   789,000

 

 

Allocation to FF&E Budget Increase

 

                        ($     50,000)

 

 

Allocation to Landscape & Site Security Budget Increase

 

   ($   200,000)

 

 

Balance Remaining

 

$    539,000

 

 

 

The use of the balance remaining of $539,000 will be reported back to General Committee prior to June 21, 2010 in compliance with the Infrastructure Stimulus Fund Agreement.

 

Below is a table to detail the awards and budget reallocation and its financial impacts:

 

 

HUMAN RESOURCES CONSIDERATIONS

Not Applicable

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Finance, Recreation and Library Staff

 

RECOMMENDED

                            BY:    ________________________          ________________________

                                      Mary Creighton                                  Brenda Librecz

                                      Director, Recreation Services  Commissioner,

                                                                                                Community & Fire Services

 

 

ATTACHMENTS:

Not Applicable