Report to: General Committee                                  Date Report Authored: February 18, 2010

 

 

SUBJECT:                          Contract Extension 014-T-09 Concrete Maintenance

PREPARED BY:               Morgan Jones, Ext, 2285

                                            Patti Malone, Ext, 2239

 

 

 

RECOMMENDATION:

1)                  That the report entitled “Contract Extension 014-T-09 Concrete Maintenance be received”;

 

2)                  And That the contract 014-T-09 for Concrete Maintenance be extended with VTA Construction for Two (2) years (2010 -2011) in the estimated annual amount of $693,276 and at the same 2009 itemized pricing;

 

3)                  And that the tendering process be waived in accordance with Purchasing By-Law 2004-341, Part II, Section 7, Non Competitive Procurement (c) “ When the extension of an existing contract would prove more cost effective or beneficial;

 

4)                  And That the award be funded from Operations and Waterworks Department 2010 Operating and Capital Budgets accounts as detailed in the financial template and the 2011 budget upon approval;

 

5)                  And That Staff be authorized to amend the award amount in 2011 to reflect changes to Operations and Waterworks Department Operating and Capital budget accounts (listed in financial template) approved by Council during the annual budgeting process;

 

6)                  And that Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

 

EXECUTIVE SUMMARY:

N/A

 

1. Purpose  2. Background  3. Discussion  4. Financial 

 

5. Others (HR, Strategic, Affected Units)  6. Attachment(s)

 

PURPOSE:

To obtain Council approval to extend contract 014-T-09 “Concrete Maintenance” for two (2) additional years at the same 2009 itemized pricing.

 

 

 

 

 

 

 

 

 

BACKGROUND:

Contract for the concrete maintenance, No. 014-T-09, was tendered on February 2, 2009 and advertised through the Electronic Tendering Network.  The contract was awarded to VGN Construction Limited (VGN) on May 12, 2009 through Council approval (Attached).  Within the Council extract of May 12, 2009, Staff received authorization to proceed with the next low bidder (Peltar) should VGN not accept the Purchase Order for contract No. 014-T-09. 

 

VGN was acceptable to proceeding with the contract, however, from May 12th to June 10th, 2009 they performed no work and continued to delay the start of the concrete maintenance program. Upon commencement and as a result of poor performance, the contract with VGN Construction was terminated through the appropriate authority levels.

 

The second lowest bidder as outlined within the Council report, Peltar Paving was then contacted to see if they would be willing to commence immediately. Peltar Paving advised Purchasing that due to their work schedule and the late notification, they would be unable to undertake contract 014-T-09. Purchasing then approached VTA Construction (3rd lowest priced bidder, 3% higher in cost than Peltar Paving) to try and secure their services as the successful contractor for this contract.

 

On July 9, 2009, VTA Construction was awarded the contract through a Staff award during Council recess for a one (1) year term.  In order for the Town to meet maintenance objectives, the Operations Department requested two crews instead of the contract implied single crew to start the contract. Two crews were provided and all work required under the first contract year, 2009, was completed by VTA on time/budget and to the full satisfaction of the Town despite the delay.  There were no financial impacts as the two crews required less time to complete the work.

 

OPTIONS/ DISCUSSION:

The bid document for contract No. 014-T-09 had a one (1) year term with a two (2) year option at the Town’s discretion and subject to performance.  Staff recommends extending contract No. 014-T-09 for the two (2) additional years under the same terms and conditions with VTA.  Staff considers the two (2) year extension to be consistent with the intent of the original award of tender for this contract.

 

Staff have reviewed the option to cancel the extension term and go back to the market place, however, due to the increased demand for concrete/asphalt contractors to service road improvements through the federal infrastructure projects across the GTA (over $200 million identified), staff are concerned with the potential for significant increase prices as a result of the market supply and demand.  Additionally, the Operations Department are very satisfied with the  quality of work and commitment made by VTA on behalf of the Town to complete all concrete maintenance work in 2009, despite the two (2) month delay in start of construction.

 

 

 

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

 

The following table is a summary of the financial considerations for this report:

 

 

 

 

 

Original Budget and Account #

 

$2,159,398

 

Various 

Current Budget Available (unspent)

 

$1,648,874

 

 

Less Cost

 

($693,276)

 

Awarded to VTA Construction

Less Contingency

 

 

 

 

Budget Remaining

 

$955,598

 

 

 

 

 

Budgets provided in this award are also used in separate contracts for road maintenance, interlocking repairs, sidewalk/curb repairs parking lots repairs and Waterworks department operating requirements.  Therefore, the Operations Department will administer this contract and prioritize work in order to manage spending to the approved budgeted amounts.  Should the prioritized work require additional funds beyond the approved budget amounts, staff will follow the expenditure control policy to secure such funding.

 

 

HUMAN RESOURCES CONSIDERATIONS

Not Applicable

 

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

Not Applicable

 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Not Applicable

 

 

 

 

ATTACHMENTS:

Council Extract May 12, 2009