Report to: General Committee                                                     Report Date: March 01, 2010

 

 

SUBJECT:                     Delegation of Authority to execute Release between the Town and Suncor Energy Inc. - Sanitary Sewer Extensions in Thornhill Area (Contract 144-T-09)

 

PREPARED BY:          Prathapan Kumar, Acting Manager of Capital ROW, Ext. 2989

Lisa Riegel, Assistant Town Solicitor, Ext. 3582

 

RECOMMENDATION:

1)      THAT the report entitled “Delegation of Authority to execute Release between the Town and Suncor Energy Inc. - Sanitary Sewer Extensions in Thornhill Area (Contract 144-T-09)” be received; 

 

2)      AND THAT the Mayor and Clerk be authorized to execute the Release between the Town and Suncor Energy Inc. in consideration for cost reimbursements in the amount of $73,067, in a form satisfactory to the Town Solicitor;

 

3)      AND THAT the Mayor and Clerk be authorized to execute future releases that represent a reimbursement of costs by third parties to the Town, upon approval of the applicable Commissioner or the Chief Administrative Officer and in a form satisfactory to the Town Solicitor;

 

  AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

EXECUTIVE SUMMARY:

Not Applicable

 

2. Background   3. Discussion   4. Financial  

PURPOSE:

The purpose of this report is to seek Council’s approval to execute the Release between the Town and Suncor Energy Inc.

 

BACKGROUND:

As part of the Waterworks Department’s effort to improve the capacity of the local sewer system in the Baythorn area of Thornhill, sanitary sewer extensions were carried out along Colonsay Road and Silver Aspen Drive.  The contract was awarded to Tedescon Infrastructure in June 2009, and construction work commenced in August 2009.

 

While excavating for the installation of the sanitary sewer, contaminated soil was found within the trench (approximately 40 metres in length) at the intersection of Silver Aspen Drive/Colonsay Road (refer Schedule “A”).  Lab tests (conducted by the Town’s consultant, Trow Associates Inc.) indicated that the soil was contaminated with petroleum hydrocarbon and benzene (refer Schedule “C”).  A total of 1040 tonnes of contaminated material was removed and disposed at an approved dump site as per Ministry of Environment requirements.

 

OPTIONS/ DISCUSSION:

Investigation revealed that the likely cause of the soil contamination was due to an abandoned fuel oil distribution system owned by Gulf Oil Company.  Gulf Oil Company was acquired by Petro Canada, which amalgamated with Suncor Energy Inc.

 

Staff contacted Suncor Energy and requested them to reimburse the additional costs incurred by the Town due to the presence of contaminated soil, in the amount of $89,626.23 (which includes additional costs associated with work stoppage, testing, removal/disposal of contaminated soil, backfill, and additional contract administration).  Suncor Energy acknowledged that the abandoned oil supply lines were the likely cause of the contaminated soil and, following negotiations with Asset Management Department, agreed to reimburse the majority of the additional costs incurred by the Town, in the amount of $73,067.30, in order to settle this matter.  In return, Suncor Energy requested that the Town execute a release.  

 

The form of release attached to this report as Schedule “B” (the “Release”) has been reviewed and approved by the Town’s Legal Department.  The scope of the Release has been reduced significantly from the form of release originally requested by Suncor Energy.  The Release is limited to the costs associated with the removal and offsite disposal of petroleum hydrocarbon and benzene contaminated soil located at the sites identified by the Town’s consultant in connection with Contract 144-T-09.  The Release does not preclude the Town from pursuing a claim against Suncor Energy for any costs, expenses, damages, etc. outside of this limited scope as a result of the presence of contaminated soil.

 

Since no delegated authority has been approved by Council to execute a release of this nature on behalf of the Town, Staff requests Council to authorize the Mayor and Clerk to execute the Release between the Town and Suncor Energy Inc. in a form satisfactory to the Town Solicitor; and the Mayor and Clerk to execute future releases that represent a reimbursement of costs by third parties to the Town, upon approval of the applicable Commissioner or the Chief Administrative Officer and in a form satisfactory to the Town Solicitor.

 

 

FINANCIAL CONSIDERATIONS AND TEMPLATE:

Shortfall of $16,344 driven primarily by the difference between Town’s cost to clean up the contaminated soil ($89,626.23) and reimbursement from Suncor ($73,067) and will be funded from budget allocated within project 9278 for construction of 3 siphon maintenance chambers in Woodbine area  ($150,000 available).

 

HUMAN RESOURCES CONSIDERATIONS:

Not applicable

 

ALIGNMENT WITH STRATEGIC CONSIDERATIONS:

Not applicable

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Legal Department has been consulted, provided input and reviewed this report. 

 

                                     

                                                                                   

ATTACHMENTS:

Schedule “A” - Key Plan

Schedule “B” - Release

Schedule “C” - Lab Test Report