Report to: General Committee Report
Date:
SUBJECT: Award of Tender 023-Q-10
PREPARED BY: Prathapan Kumar, Ext. 2989
Patti Malone, Ext. 2239
1) THAT the report entitled “Award of Tender 023-Q-10 Rouge River Community Centre Sanitary Sewer Pumping Sump Replacement” be received;
2)
AND
THAT the contract for 023-Q-10 Rouge River Community Centre Sanitary Sewer
Pumping Sump Replacement be awarded to the lowest priced bidder, Robert R.
Somerville in the amount of $119,802.00 exclusive of GST;
3)
4)
5)
6)
7)
AND
THAT Staff be authorized and directed to do all things necessary to give effect
to this resolution.
The purpose of this report is to obtain Council approval to award the construction tender 023-Q-10 Rouge River Community Centre Sanitary Sewer Pumping Sump Replacement and Consulting Engineering Services Related to Contract Administration and Construction Inspection.
The existing sanitary sewer pumping station at Rouge River Community
Centre developed numerous problems since August 2009. The pumps were clogging frequently and the
existing sump structure is buried at about 1.2 metre below grade with a
vertical shaft of 600mmx 600mm for access.
The entry access does not conform to confined space entry and the
electrical junction box was located inside the sump which was a safety
hazard. The existing 75mm diameter PVC
discharge line is considered to be too large for the small capacity pumps
resulting grits settlement along the pipe.
In order to correct the safety hazards, confined space entry and grit
settlement on pipe, a new sump structure of 2.4m x 2.4m with proper access
opening was proposed next to the existing sump with a new 50mm diameter
forcemain connection to the existing manhole.
Advertised |
ETN |
Bids closed on |
|
Number picking up bid documents |
7 |
Number responding to bid |
5 |
Company |
Prices
(excluding GST) |
Robert B.
Somerville Co. Limited |
$ 119,802.00 |
R. Chad General
Contracting Inc. |
$ 130,800.00 |
Todd Brothers
Contracting Limited |
$ 131,679.39 |
Dig-Con International
Limited |
$ 172,264.68 |
G.C. Romano Sons ( |
$ 221,400.00 |
This project was unforeseen and was not included in the 2010 Capital Budget. Therefore a new Recreation Capital Budget needs to be established and to be funded from the Lifecycle Reserve.
The final cost estimate to correct for the condition was not determined until after the capital budget was finalized. Hence, in order to fund the replacement of the Rouge River Community Centre Sanitary Sewer Pumping Sump, the following sources were reviewed:
The following table is a summary of the financial considerations for this report: |
||
Funded from Life Cycle Reserve: (AC#
087-2800-200) |
|
|
Construction Cost |
$119,802.00 |
|
Construction and
Consultant Contingency costs |
$18,770.00 |
|
Contract
Administration and Construction Inspection |
$8,000.00 |
Awarded to R.V. Anderson Limited |
Geotechnical Services |
$1,000.00 |
|
Total Budget Required |
$147,572.00 |
|
|
Not applicable
Not applicable
The Finance Department has been consulted, provided input and reviewed this report.
None