Report to: General
Committee Report
Date:
SUBJECT: Contract Extension of Request for Proposal (RFP) # 061-R-09 Consulting Services for Facility Project Management and Space Planning
PREPARED BY: Brian Millar, Ext, 6190
Patti Malone Ext, 2239
RECOMMENDATION:
1) THAT the report entitled “Contract Extension of Request for Proposal (RFP) # 061-R-09 “Consulting Services for Facility Project Management and Space Planning” be received;
2)
3)
4)
5)
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
To obtain approval to extend contract number 061-R-09 for Consulting Services for Facility Project Management and Space Planning.
The contract
encompasses the development of project management plans with Town staff and
includes the following:
·
Developing
and validating the project scope of work.
·
Identifying
project time frame complete with detailed tasks and associated milestones.
·
Provide a
process to manage scope change.
·
Identify
team members and responsibilities.
·
Establish
communication and reporting requirements.
·
Establish
project budgeting and cost management to meet project objectives within
approved budget.
·
Develop,
issue, and award Quotations, Requests for Proposals, and Tenders as may be
required.
·
Source,
contract and supervise vendors engaged in delivering projects approved by the
Town.
·
Provide
‘turn-key’ administrative services for space planning projects including the
processing of invoices relating to project requirements.
·
Confirm
communication requirements and develop plan including staff relocation and
orientation packages.
·
Coordinate
project meetings to be conducted with Town of
·
Identify
corporate project archiving and closure procedures.
Additionally, Mayhew Associates delivers the following:
·
Supply
and install furniture. The cost of furniture is included in the award amount. Furniture is to be acquired in accordance with the
· Identify areas for improvement and opportunities to realize cost savings.
·
Determine
space requirements and develop revised plans that include foreseeable problems,
conflicts, and develop alternate solutions.
·
Develop
project management plans.
·
Identify a
process for managing scope change.
·
Produce
design development and furniture plans. Revise Auto Cad floor plans as
required.
·
Determine
telecommunication and IT requirements. Contact and coordinate external
contractors to perform cabling work.
·
Coordinate
furniture tender and ensure installation tasks and standards are conformed to.
·
Obtain
quotes for move services and coordinate all aspects of departmental moves.
·
Ensure
municipal permits are applied for and approved (if required).
·
Ensure all
environmental workplace safety policies and procedures are adhered to during
construction, relocation and installation.
·
Supervise
and coordinate trades.
·
Provide
‘turn key’ administrative services (verify and process invoices for payment).
·
Conduct
furniture inventories.
When tenders are called by the Consultant on behalf of the
Town, the Town’s
In 2009, Staff awarded
RFP 061-R-09 for a one (1) year term to Mayhew
Associates (Highest ranked and 2nd lowest priced bidder); however,
the proposal document and bid submissions had an option to renew for four (4)
additional years at the same terms and conditions. In
Mayhew’s original bidding submission, they included a 5% increase for year 3 of
the contractual term.
The following is an overview of the bid information in 2009 and the ranking of the RFP evaluation.
Advertised, place and
date |
|
Bids closed on |
|
Number of bidders
picking up bid documents |
89 |
Number of bidders
responded to bid |
11 |
EVALUATION SCORING
Consultants |
Score
of 100 |
Ranking |
Mayhew & Associates |
91 |
1 |
Britacan Facilities
Management Group Inc. |
72 |
2 |
Sweeney Dale Interior
Design Inc. |
63 |
3 |
Blackthorn
Construction Management Incorporated |
59 |
4 |
Onespace Unlimited
Inc. |
53 |
5 |
Jones Lang LaSalle |
51 |
6 |
SMA Project &
Construction Management |
48 |
7 |
MHPM Project Managers
Inc. |
46 |
8 |
Shields &
Associates |
44 |
9 |
Urbacon |
42 |
10 |
Denmar Cost
Consultants |
37 |
11 |
Mayhew Associates
the recommended proponent was the highest ranked and second lowest priced
proponent in RFP 061-R-09 having the 2nd lowest administration pass
through costs of 2% compared with a range of 0% to 17% from our bidders. Further, the hourly rates range identified
for Principal designer, Project Manager, Junior Designer, Technical Auto Cad and
clerical support was the 2nd lowest amongst all bidders. Mayhew Associates have provided ongoing
support and combined with excellent customer service for the previous four years
has resulted in space planning projects being delivered on time and on budget. The move of several Town departments in three
separate phases to
The following
table is a summary of the financial considerations for this report: |
||||
|
|
|
|
|
Original Budget and Account # |
|
$200,000 |
|
750-101-5399-10247 Corporate Accommodation |
Current Budget Available (unspent) |
|
$200,000 |
|
|
Less Cost |
|
($200,000) |
|
Awarded
to Mayhew Associates |
Less Contingency |
|
|
|
|
Budget Remaining |
|
$0 |
|
|
Not applicable
Not applicable
Not applicable
RECOMMENDED
Not applicable