Report to: General Committee Date of Meeting: March 29, 2010
SUBJECT: Status of Capital
Projects as of
PREPARED BY: David Milenkovski, Senior Financial Analyst
RECOMMENDATION:
1)
THAT the report entitled “Status
of Capital Projects as of
2) AND THAT $1.12M from closed capital projects be transferred to the sources of funding as listed on Exhibit A;
3) AND THAT $200,000 be transferred from the Waterworks Stabilization/Capital Reserve account to fund the Relocation of Waterworks Operations from Miller Avenue to 8100 Warden Avenue (account # 053-5350-9502-005);
4) AND THAT the Capital Budget Control Policy section 3.1 be amended to grant authority to Staff to approve funding transfers (within limits defined in Expenditure Control Policy section 6.03),
5) AND THAT the Capital Budget Control Policy section 3.2 be amended to grant authority to the CAO to approve refinements to activities within approved scope of the project,
6) AND THAT the Capital Budget Control Policy section 3.3 be amended to grant authority to the Treasurer to approve project consolidations, as long as the projects involved are of a similar scope;
7) AND THAT the CAO be delegated authority to make any future administrative changes to the Capital Budget Control Policy;
AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Capital Projects to be Closed
There are 101 capital projects recommended for closure with a total
budget remaining of $1.12M as of
DCA $0.20M
Capital Budget Gapping $0.31M
Total $1.12M
The majority of the projects listed in Exhibit B are projects that were completed within budget. Projects that were under spent will have the balance transferred back to the original source(s) of funding.
Status of Open Capital Projects
There are 592 projects that have been requested to remain open, with
a total budget of $403.84M as of
Open Capital $403.84M
Total Encumbered $180.44M 45%
Unencumbered/Uncommitted $223.40M 55%
This indicates that 45% of the total approved open capital project budget is encumbered by expenditures and outstanding purchase orders. These totals do not include the 102 capital projects recommended for closure in this report.
Amendment of the Capital Budget Control Policy
Currently, Section 3.1 of the Capital Budget Control Policy states “Requests for additional funding to an approved project are governed by the Expenditure Control Policy”. Section 3.1 also states “Requests for additional funding will be included in the semi-annual report to Council for approval”. Staff recommends that section 3.1 of the Capital Budget Control Policy be amended such that Staff be given authority to approve funding transfers and scope changes, within limits as defined in the Expenditure Control Policy (section 6.03), as follows:
Staff Member |
Authorization Limit |
Director |
$10,000 and less than 10% contract value |
Commissioner |
$25,000 and less than 10% contract value |
Treasurer |
$50,000 and less |
CAO |
$100,000 and less |
Council |
Greater than $100,000 |
This alignment with the Expenditure Control Policy will eliminate the inconsistencies with the request for additional funds.
Staff also proposes amending section 3.2 of the Capital Budget Control Policy to allow for refinements to activities within approved scope of the project subject to approval of the CAO. Changes in the nature of work of a project must continue to be approved by Council.
Additionally, Staff recommends that section 3.3 of the Capital Budget Control Policy be amended so that the Treasurer can approve consolidations of projects with a similar scope.
Amended sections 3.1 to 3.3 of the Capital Budget Control Policy can be found on exhibit C pages 2 to 4.
PURPOSE:
To inform Council about the status of capital projects
as of
BACKGROUND:
CAPITAL PROJECTS TO BE CLOSED
There are 101 capital projects recommended for closure. Of the total budget of $17.85M for these projects, $1.12M was not spent and will be returned to the original sources of funding as listed in Exhibit A.
STATUS OF OPEN CAPITAL
PROJECTS
The total capital budget for open projects at
Staff has conducted a compliance review on all open capital projects. In accordance with the Capital Budget Control
Policy Section 4.1, projects that remain inactive for a period of twenty-four
months or longer are subject to closure. The non-compliant projects were
discussed and reviewed by the business units, of which a majority of these
inactive projects are being closed and are included in Exhibit A.
FINANCIAL
CONSIDERATIONS:
CAPITAL PROJECTS TO BE CLOSED
A detailed listing of capital projects with unexpended funds totaling $1.12M, to be closed upon approval of this report, is outlined in the following Exhibits:
Exhibit A “Summary of Closed Capital Project Funding
to be Transferred” summarizes where the closed capital
project balances will be transferred;
Exhibit B “Closed Capital Projects – With Funds to be Returned to Original Sources of Funding” provides a detailed
summary by project where the closed capital project balances will be
transferred.
Exhibit A summarizes the return of funds from the closed capital projects to the original sources of funding. In accordance with the Capital Budget Control Policy, the remaining funds from the closure of operating budget and life cycle replacement and capital reserve funded capital projects will be transferred as follows;
The capital contingency is topped up to a maximum of $250k from closed projects. Since the balance of the contingency is currently $185k, only $65k needs to be transferred to the contingency from Life Cycle and Operating Budget funded projects.
As part of the Town’s commitment to achieve a 0% net tax rate increase in 2010, the budget had pre-committed $315,000 of capital budget gapping funds to cover for the 2010 budget shortfall. As such, dollars remaining from the closure of Operating Budget and Life Cycle Replacement and Capital Reserve will be transferred to the capital budget gapping. As shown on Exhibit A, the total available to be transferred is sufficient to cover this pre-commitment.
Similarly, there are Planning Development
Charge (DC) and
In summary, the net amount of $1.12M as outlined in Exhibit A will be transferred back to the original sources of funding as follows:
DCA $0.20M
Capital Budget Gapping $0.31M
Total $1.12M
The majority of the projects listed in Exhibit B are projects that were completed within budget. Projects that were under spent will have the balance transferred back to the original source(s) of funding. There are some projects listed on Exhibit B that did not begin and thus are returning their entire budgets to the original sources of funding. The following are the reasons:
Facility Assets
Project # 8642 – Operations Facilities Improvements – West Parks Paint
Shop –Budget of $20,400 : This project was requested for
painting the
Waterworks
Project # 8319 – Sanitary Trunk Sewer Inspection Program – Budget of $60,000 : This was the 2008 annual budget request for
sanitary trunk sewer inspections but the project was delayed due to a lack of
staff resources at the time. The project was eventually tendered in 2009 and
the 2009 annual budget request was sufficient to complete the project.
Therefore, these funds are no longer required.
Project # 8430 – Water System Hydraulic Modeling (Flushing Module) –
Budget of $18,000 : A module was purchased with funds
from ITS project # 8674 (Water System Modeling) instead of this project, therefore
these funds are not required.
Engineering
Project # 7270 – Mid-Block Crossing at Highway 404 between Elgin Mills
and
Projects with over expenditures (or negative balances remaining) will be offset against other identified closed projects with the same funding source(s), as per guidelines established in the Expenditure Control Policy.
STATUS OF OPEN CAPITAL
PROJECTS
As of
The following summarizes the status of open capital:
Open Capital $403.84M
Total Encumbered $180.44M 45%
Unencumbered/Uncommitted $223.40M 55%
This indicates that 45% of the total approved open capital project budget is encumbered.
These totals do not include the 101 capital projects recommended for closure in this report.
The
total encumbered of $180.44M includes commitments of $34.94M and expenditures
of $145.50M.
Commitments refer to purchase orders (
PROJECT
REQUIRING ADDITIONAL FUNDING
The following details a funding shortfall that was encountered by one project and a proposal for ensuring adequate funding is available;
Project
# 9502 – Relocation of Waterworks Operations from Miller to
A staff award dated
AMENDMENT OF CAPITAL BUDGET
CONTROL POLICY
Currently, Section 3.1 of the Capital Budget Control Policy states “Requests for additional funding to an approved project are governed by the Expenditure Control Policy”. Section 3.1 also states “Requests for additional funding will be included in the semi-annual report to Council for approval”. Staff recommends that section 3.1 of the Capital Budget Control Policy be amended such that Staff be given authority to approve funding transfers and scope changes, within limits as defined in the Expenditure Control Policy (section 6.03), as follows;
Staff Member |
Authorization Limit |
Director |
$10,000 and less than 10% contract value |
Commissioner |
$25,000 and less than 10% contract value |
Treasurer |
$50,000 and less |
CAO |
$100,000 and less |
Council |
Greater than $100,000 |
This alignment with the Expenditure Control Policy will eliminate the inconsistencies with the request for additional funds.
Staff also proposes amending section 3.2 of the Capital Budget Control Policy to allow for refinements to activities within the approved scope of a project, subject to approval of the CAO. Changes in the nature of work of a project must continue to be approved by Council.
Staff is also proposing that section 3.3 of the Capital Budget Control Policy be amended to allow consolidations of projects of a similar scope to be reviewed and authorized by the Treasurer on a periodic basis, in order to reduce the total number of open capital projects and simplify the reporting of similar projects. Projects considered for consolidation must be of a similar scope. Requests for consolidation of projects with different scopes must continue to be approved by Council.
A copy of the Capital Budget Control Policy is attached in Exhibit C and the revised sections 3.1 to 3.3 are highlighted in pages 2 to 4 of the exhibit.
ATTACHMENTS:
Exhibit A Summary
of Closed Capital Project Funding to be Transferred
Exhibit B Closed Capital Projects – With Funds
to be Returned to Original Sources of Funding
Exhibit C Amendment to Capital Budget Control Policy