Report to: General Committee                                  Date Report Authored: April 19, 2010

 

 

SUBJECT:                         Award of Contract for 083-R-10 250kW Grid Tie Solar Photovoltaic System at 8100 Warden Ave.

PREPARED BY:              John Southwood, O.P. McCarthy & Associates

                                            Atiq Rahman, Asset Management

                                            Graham Seaman, Sustainability Office

                                            Tony Casale, Senior Buyer, Purchasing

 

 

RECOMMENDATION:

1)                  THAT the report titled. “Award of Contract 083-R-10 – 250kW Grid Tie Solar Photovoltaic System (PV) at 8100 Warden Ave.” dated April 19, 2010 be received;

 

2)                  AND THAT Council authorize the installation of a 250kW solar PV panel system on the roof of the 8100 Warden Ave. warehouse, as shown in Figure #1;

 

3)                  AND THAT Staff be authorized to award Contract 083-R-10 to the highest ranked / 2nd lowest priced supplier Carmanah Technologies Corporation in the amount of $1,592,640.67 inclusive of HST and exclusive of GST;

 

4)                  AND THAT a separate purchase order in the amount of $152,640.00 inclusive of HST and exclusive of GST be issued for contingency to cover any additional fees and that the Director of Asset Management be authorized to approve expenditure of this contingency amount up to the specified limit in accordance with the Expenditure Control Policy and a monthly expenditure status be provided to the Town Treasurer;

 

5)                  AND THAT Staff be authorized to acquire applicable permits as well as to retain a qualified professional to inspect the system during construction for an upset limit of $20,352.00 inclusive of HST and exclusive of GST in accordance with the Town’s purchasing bylaws;

 

6)                  AND THAT the awards be funded with $1,028,660.00 from capital budget account 056-5350-9517-005 (Facility Energy Retrofits – Stimulus) and $736,972.67 from capital budget account 056-5350-9540-005 (Photovoltaic Solar Panel System at 8100 Warden – Supplemental Funding);

 

7)                  AND THAT the annual Feed-In-Tariff revenue of approximately $178,000 be directed back to Life Cycle Reserve Fund until $736,972.67 is paid back.

 

8)                  AND THAT a policy on energy retrofit savings and renewable energy revenues be developed to address the remaining revenues from the Feed-In-Tariff after the $736,972.67 from the Life Cycle Reserve is replenished;

 

 

9)                  AND THAT the CAO be delegated authority to sign-off and complete this Feed-In-Tariff contract with the Ontario Power Authority.

 

10)              AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

PURPOSE:

The purpose of this report is to report back to General Committee with the budget and design details for all proposed and recommended solar PV panel systems at 8100 Warden Ave., as per the Resolution of Council Meeting held on December 15, 2009 and to obtain council approval to award Contract 083-R-10.

 

BACKGROUND:

At the Council Meeting held on December 15, 2009, staff was directed to complete design, contract documents and tender for construction of a photovoltaic solar panel system on 8100 Warden Ave. warehouse roof.  This project was brought forward as part of the federal and provincial stimulus funded energy retrofit project.

 

OPTIONS/ DISCUSSION:

Implementing a solar PV project at a Town owned building will demonstrate the Town’s leadership in renewable energy generation, will generate revenue through the Ontario Power Authority’s Feed-In-Tariff (FIT) program and will serve to increase the Town’s profile in this field while securing our commitment to champion renewable energy opportunities.  A 250kW grid tie solar photovoltaic (PV) system is proposed to be designed, installed and commissioned on the rooftop of 8100 Warden Avenue warehouse.  There is approximately 57,000 sq. ft. of roof top above the warehouse that is available for the installation of a solar PV system.

 

In order to accelerate project timelines to meet the deadline of the stimulus funding, the Town will engage Carmanah Technologies in a design/build contract.  Carmanah Technologies will supply, install, and commission an operational, grid tied solar photovoltaic system.  The solar system will be a maximum 250kWp as defined by the FIT rules to ensure the Town of Markham will be eligible to receive $0.713/kWh as payment for FIT solar production.  Annual revenue from the FIT program is estimated to be $178,000.  This revenue will be directed to Life Cycle Reserve until the $736,972.67 that was originally withdrawn to supplement the project is paid off (in approximately 5 years)  Once the Life Cycle Reserve is replenished, the annual revenue of $178,000 will be dealt with based on a new policy on energy retrofit savings and renewable energy revenues.   Any carbon credits generated by this system will be the property of the Ontario Power Authority under the rules of the FIT program.

 

Construction of the system will start no later that September 1, 2010 and will be complete for a “Commission On Date” of November 30, 2010.

Inverter Location

Outside

 
Text Box:        


Area 3 dimensions
    90 ft x 100ft

Text Box:     Area 1 dimensions
    145 ft x 105ft
Text Box: Area 2 dimensions
    145 ft x 60ft

Figure #1 – Aerial view of the 8100 Warden Ave warehouse with the preliminary planned areas for installation of photovoltaic solar panels.

 

 

PROPOSAL INFORMATION:

Advertised, place and date

Biddingo.com – March 12, 2009

Tender Closing Date

March 31, 2009

Number of contractors taking tender documents

19

Number of contractors responding to tender

4

 

PROPOSAL EVALUATION:

 

The evaluation team was comprised of staff from Asset Management Department, Sustainability Office, Enviro-Energy Technologies and O.P. McCarthy & Associates.  The evaluation was based on pre-established evaluation criteria as listed in the Request for Proposal: 45% for cost performance, 20% for past experience of Contractor and Consultant Team, 20% for Qualification for Project Team Members and 15% for Project Delivery, with resulting scores as follows:

 

Contractor

Score (out of 100)

Rank Results

Carmanah Technologies

85.45

1

AEG Power Solutions Inc.

83.5

2

Ontario Electrical Construction Company Ltd.

82.5

3

Ainsworth Inc.

57.8

4

 

Prices received from the four (4) bidders ranged from $1.47 million to $2.23 million.

Carmanah Technologies Corporation is the highest ranked and second lowest priced proponent.  Staff believes that Carmanah Technologies Corporation has provided the best proposal to the Town for executing this project.  Carmanah Technologies Corporation earned their selection by scoring more points for their past experience in similar projects  and by having a more qualified design and project management team.

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

The following table is a summary of the financial consideration of this report:

Original Budget and Account #

$1,125,515.00

056-5350-9517-005

Supplemental Budget and Account #

$1,400,000.00

056-5350-9540-005

Less Consultant Commitments to Date

$33,755.00

Enviro-Energy Technologies

Less Project Management Commitment to Date

$63,100.00

O.P. McCarthy & Associates

Budget Available for this Award

$2,428,660.00

 

Less Design/Build of PV Solar System

 

$1,592,640.67

 

Award to Carmanah Technologies for Design/Build $1,565,095.00 plus $27,545.67 HST

Less Inspections & Permits

$20,352.00

$20,000.00 plus $352.00 HST

Less  Contingency

$152,640.00

$150,000.00 plus $2,640.00 HST

Total Costs of Awards

$1,765,632.67

 

Budget Remaining

$ 663,027.33

 

 

Remaining budget will be returned to the original funding sources upon payment of the final invoice.

 

 

HUMAN RESOURCES CONSIDERATIONS

Not applicable.

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

This project would support “Building Markham’s Future Together” goals and in particular is well aligned with the “Environment” area of strategic focus.  Additionally, Markham is one of the very few Municipalities to make an investment in Solar PV of this size, reinforcing the Town’s leadership position in Ontario. 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

1)      Finance

2)      Sustainability Office

 

 

ATTACHMENTS:

None

 

RECOMMENDED

 

Microsoft Office Signature Line...Microsoft Office Signature Line...


 

COMMITTEE/COUNCIL ITEM TRACKING FORM

Revised: September 2009

COUNCIL

 

DEVELOPMENT SERVICES

Planning                    

Economic Dev.          

Transportation           

GENERAL

Community Services   

Environment & Sustainability    

Finance & Administrative          

Lands, Building & Parks Construction   

TARGET MEETING DATE

May 10, 2010

DATE REPORT AUTHORED

 

April 19, 2010

ITEM TITLE

Award of Contract for 083-R-10 250kW Grid Tie Solar Photovoltaic System at 8100 Warden Ave.

 

AGENDA SECTION

TIME TO BE ALLOCATED

Presentation/Deputation            Consent                             Regular

5 minutes

CONFIDENTIAL REPORTS

For in camera reports, please indicate appropriate subsection of  s239(2) Municipal Act ( all applicable):

(a) Security of Property           (e) Litigation or potential litigation          

(b) Personal matters about  individual                          (f) Solicitor-client privilege         

(c) Acquisition/disposition of land                              (g) Legislated authority to be in camera   

(d) Labour relations/Employee negotiations

 

ORIGINATOR

John Southwood, OP McCarthy Associates,  

416-471-8518               Ext.

CONTACT

Atiq Rahman             Ext. 2231

DOES THE REPORT, PRESENTATION, BY-LAW AFFECT OTHER DEPTS:

Yes    No  (List all departments impacted and being consulted on this report.)

 

Finance Department

 

Electronic Approval Required by:

Department

Individual

Obtained

Asset Management

Steve Andrews

Community & Fire Services Commission

Brenda Librecz

Finance

Veronica Siu

Finance

Joel Lustig

Corporate Services

Andy Taylor

Chief Administrative Officer