Report to: General Committee                                                    Report Date: May 05, 2010

 

 

SUBJECT:                         Award of Tender # 103-T-10 2010 Relining of Cast Iron and Ductile Iron Watermains

 

PREPARED BY:              Ernie Ting                       Ext: 3650

                                            David Huynh                              Ext: 2400

                                            Rosemarie Patano           Ext: 2990

 

RECOMMENDATION:

 

1) THAT the report entitled “Award of Tender # 103-T-10 2010 Relining of Cast Iron and Ductile Iron Watermains” be received; and

 

2) THAT the contract for 2010 relining of cast iron and ductile iron watermains be awarded to the lowest priced bidder, Fer-Pal Construction Ltd., in the total amount of $995,335.32 inclusive of HST; and

 

3) THAT a contingency in the amount of $99,533.53 inclusive of HST, be established to cover any additional construction costs, and that the General Manager of Waterworks be authorized to approve expenditure of this contingency amount up to the specified limit; and

 

4) THAT this contract be funded from the 2010 Capital Budget Account 053-6150-10321-005 “Cement Relining of Iron Watermains”; and

 

5) THAT upon completion of the project the remaining funds be returned to the original funding source; and further

 

6) THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

EXECUTIVE SUMMARY:

Not Applicable.

 

PURPOSE:

The purpose of this report is to award the contract for 2010 relining of cast iron and ductile iron watermains.

 

BACKGROUND:

A 20-year program to cement line ductile iron watermains was approved and adopted by Council in 1997. Recent field verification in the Town of Markham water distribution system confirmed a total length of 82.0 km of unlined ductile iron watermains. Most of these watermains are in good structural condition, but have poor water quality due to internal corrosion. Currently 72.0 km of watermains have been relined.

The 2010 relining project will occur on the following streets: East Drive, South Drive, Royal Orchard Boulevard, Doncrest/ Poinsetta Drive, Main Street Unionville, and Bullock Drive. The location of these streets is shown on the attached map.

 

Approximately 2.1 km of watermains will receive relining this year. The remaining unlined ductile iron watermains will be completed in the next two years.

 

Cement relining program extends the life expectancy of the watermains and results in:

·         Restoring water quality to meet the Ontario Ministry of Environment Drinking Water Quality Standards.

·         Reducing costs for watermain rehabilitation and replacement.

·         Extending watermain life expectancy to +50 years, in terms of water quality control.

·         Improving supply capacity (better water flow) for domestic usage and fire demand.

·         Minimizing unnecessary disturbance and inconvenience to water customers.

 

OPTIONS/ DISCUSSION:

Not Applicable.

FINANCIAL CONSIDERATIONS AND TEMPLATE:

Bid Information:

Advertised, place and date

ETN

Bids closed on

April 16, 2010

Number of Bidders picking up bid documents

5

Number of Bidders responding to bid

4*

* Two (2) bidders were disqualified after bid opening. 

One (1) bidder after bid opening was disqualified for submitting non-compliant bid.  The bidder had mathematical errors that resulted in an uncertain bid price

“The Town in its sole discretion may reject as non-complaint Tender which contains omissions, erasures: is ambiguous or unclear as to meaning or intent”.

 One (1) bidder after bid opening was disqualified for not meeting the mandatory bonding requirements.  The “Bid Bond” and the “Agreement to Bond” are not valid unless they are executed by the surety company and submitted in the original form.

 

Detailed Pricing Information:

Company

Total Price, Inclusive of HST

Fer-Pal Construction Ltd.

$                           995,335.32

Main Rehabilitation C. Ltd.

$                        1,210,776.00

 

Based on similar unit items in the 2009 contract, the pricing has increased by an estimated amount of 3%.

The bid documents have been verified for accuracy and compliance with the tender specifications and staff are satisfied that all terms, conditions and bid prices comply with the Town’s requirements.

 

Financial Considerations:

The following table is a summary of the financial considerations for this report:

 

Original Budget and Account #

 

$1,380,000

 

053-6150 -10321- 005 Relining of Cast Iron and Ductile Iron Watermains

Current Budget Available (unspent)

 

$1,380,000

 

 

Less Cost

 

($995,335)

 

Awarded to Fer-Pal Construction Ltd.

Less Contingency

 

($99,534)

 

 

 

 

 

 

 

Budget Remaining

 

$285,131

 

 

 

Upon completion of the project the remaining funds shall be returned to the original funding source. Note: Contract will be managed by internal staff, therefore no external contract administration fees are required.

 

HUMAN RESOURCES CONSIDERATIONS:

Not Applicable.

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

Not Applicable.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

·         Purchasing – Be part of the tendering and award process.  Upon receipt of the signed report, Purchasing will initiate the execution of Purchase Orders for the Contract.

·         Communication and Community Relations – Residents to be informed of the project schedule and work to be done on each street.

·         Fire & Emergency Services – To be informed of limited fire flow during construction.

·         The Finance Department has been consulted and has provided input and reviewed this report.

·         Legal was consulted on the two bid disqualifications.

 


RECOMMENDED

                           BY:   

Microsoft Office Signature Line...Microsoft Office Signature Line...Microsoft Office Signature Line...

 

ATTACHMENTS: 

2010 Cement Relining of Cast Iron and Ductile Watermains – Project Location

2010%20Cement%20Relining.pdf