Report to: General Committee                            Date Report Authored: December 8, 2010

 

 

SUBJECT:                         Thornhill C.C. & Library (TCC&L) Asbestos Abatement and Reinstatement

PREPARED BY:              Glen Taylor, Senior Manager of Infrastructure and Special Projects, Ext. 3180

 

 

RECOMMENDATION:

 

1)                  That the report entitled “Thornhill C.C. & Library (TCC&L) Asbestos Abatement and Reinstatement” be received;

 

2)                  And That Council approve the reallocation of the uncommitted budget of $539,000 to the Charterhouse Projects Inc. construction contingency purchase order for the purpose of asbestos abatement and the reinstatement of the areas at the TCC&L as outlined in Attachment 2;

 

3)                  And That additional construction contingency in the amount of $539,000 be funded from 070-5350-10511-005 TCC&L Construction Contingency,

 

4)                  And That Staff be authorized and directed to do all things necessary to give effect to this resolution.

1. Purpose   2. Background   3. Discussion   4. Financial  

 

5. Others (HR, Strategic, Affected Units)   6. Attachment(s)

 

PURPOSE:

To seek Council authorization to utilize the $539,000 uncommitted budget of the TCC&L Addition and Renovations with respect to the asbestos abatement and reinstatement, in compliance with the Infrastructure Stimulus Fund (ISF) agreement.

 

BACKGROUND:

In June 2009, the Town of Markham received ISF’s approval of $6,000,000 project cost for the Addition and Renovations at the TCC&L as well as $3,200,000 for Facility Accessibility Retrofits at ten Town of Markham Recreational facilities with TCC&L being identified as one of the locations. Both projects are funded equally by the Federal & Provincial Governments and the Town of Markham.

 

The following 3 projects are currently underway at the TCC&L:

·         Original Project- Additions and Renovations of the Community Centre and Library.

 

·         Facility Accessibility Retrofits – Changes/additions to various areas throughout the facility.

 

·         Asbestos Abatement (Commenced under construction contingency).

 

On February 23, 2010, Council awarded the original construction tender 027-T-10 (Attachment 1, Council Extract) to the low bidder Charterhouse Projects Inc. The construction at TCC&L began on March 31st, 2010 and as per the stimulus agreement, ISF requires the project to reach substantial project completion by March 31st, 2011. While an extension to the stimulus program was just recently announced, Staff intends to achieve the March 31st completion date, so that the community centre can resume normal operations.  As well, the contractor has confirmed in their construction schedule to complete the Library on January 25, 2011, so that Library Staff can start the installation of shelves, books etc.

 

The work of Facility Accessibility Retrofits project at TCC&L began on November 16th and is expected to last between 60 to 90 days. 

 

Prior to TCC&L construction, a Designated Substance Report (DSR) was required & completed prior to construction to identify the presence of any ‘hazardous’ substance as defined by the Province.  The DSR identified areas in TCC&L where construction was to occur.  The report identified that although some areas were of concern, no asbestos was identified within the confines of the affected construction areas.

 

During the construction on Facility Accessibility Retrofits project within the TCC&L, the Town received a second DSR from another environmental company that revealed an asbestos concentration.   The Town issued a stop work notification to the General Contractor (Charterhouse) for TCC&L construction in order to assess and validate this new report.  As a result, a third DSR was conducted by Cardinal Environmental. The results confirmed the presence of asbestos in 7 areas as outlined in Attachment 2.

 

On September 2nd, 2010, TCC&L proceeded with the asbestos abatement under the construction contingency at various areas in the front lobby.  This was to ensure the construction of the new East courtyard entrance would continue.  Town of Markham Health and Safety Coordinator has diligently advised Charterhouse that the asbestos is being removed properly. 

 

The current scope of the asbestos abatement is being completed by Restoration Environmental (REC) and is overseen by Cardinal Environmental.  Charterhouse is coordinating all work in conjunction with the three project schedules occurring within the building.  The abatement has commenced as of Wednesday, November 23rd, 2010 at the cost of $175,000. Funds were provided from the construction contingency account as identified above.

 

Due to the asbestos abatement and in accordance with the Ontario Building Code, the removal of dry wall and stucco ceilings throughout the TCC&L will require the installation of a new fire sprinkler system. The new T Bar ceilings will provide easy access for future maintenance and the new energy efficient light fixtures will provide better lighting levels. 

 

Staff are seeking authorization to utilize the remaining budget balance of $539,000 for the reinstatement (dry wall, ceilings, sprinkler systems, lighting fixtures).   Although the project has realized unforeseen costs, the project remains within the allocated budget as identified under financial considerations.

 

OPTIONS/ DISCUSSION:

Not Applicable

 

FINANCIAL CONSIDERATIONS AND TEMPLATE:

The total abatement and reinstatement cost estimates as provided by the project manager, Sims Moelich Associates Ltd, on November 30, 2010 is as follows:

           

 

Base Cost

Contingency

Total Estimates

Abatement

$175,167

  $60,000

$235,167

Reinstatement, including construction, design & PM

$671,286

  $50,000

$721,286

HST impact at 1.76%

  $14,898

    $1,936

  $16,834

Total

$861,351

$111,936

$973,287

 

 

 

 

 

As per Council report dated February 23rd, 2010, there is an uncommitted budget of $539,000 due to favourable pricing received from the construction tender.  In addition, there is a construction contingency set up in the amount of $471,000 of which approximately $460,000 is unspent.  The total available budget to cover the abatement and reinstatement will be $999,000. 

 

HUMAN RESOURCES CONSIDERATIONS

Not Applicable

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

Not Applicable

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Not Applicable

 

RECOMMENDED BY

 

ATTACHMENTS:

Attachment 1:  Council Extract (1) Award of Tender 027-T-10

Attachment 2:  Affected Areas that requires Asbestos Abatement