Report to:  General Committee                        Date Report Authored:  November 24, 2010

 

 

SUBJECT:                         Award of Tender 006-T-10 Steelcase Road East Sanitary Sewer Repair

 

PREPARED BY:              Daniel Liu, Infrastructure Analyst Engineer, ext. 6210

                                            Patti Malone, Senior Buyer, ext. 2239

 

 

RECOMMENDATION:

1)             THAT the report entitled “Award of Tender 006-T-10 Steelcase Road East Sanitary Sewer Repair” be received;

 

2)             THAT the contract for tender 006-T-10 Steelcase Road East Sanitary Sewer Repair be awarded to the sole bidder, Tectonic Infrastructure Inc., in the amount of $396,813.84 inclusive of HST;

 

3)             THAT a contingency be established in the amount of $29,603.40 inclusive of HST to cover any additional construction costs;

 

4)             THAT the award be funded from the Sewer System Upgrade Program account #053-6150-8334-005 of the Town’s 2008 Capital Budget in the amount of $426,417.24 inclusive of HST;

 

5)             AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

PURPOSE:

The purpose of this report is to obtain Council approval to award the contract for Steelcase Road East Sanitary Sewer Repair.

 

BACKGROUND:

Two (2) sections of sanitary sewer pipes on Steelcase Road East from Victoria Park Ave eastward (167 meters) have been severely damaged by the corrosive wastewater effluent discharged, believed to be from the nearby property owner.  Further to actions to recover the total cost of the repair through legal process from the property owner, Waterworks is recommending to proceed with repairing the sewers to mitigate further damage and risks.

 

Tender number one (1) (106-T-10) for open-cut replacement was issued in April 2010, and two (2) bids were received with prices more than 50% higher than the budget amount. Both bidders, failing to provide an Agreement to Bond within the bid submissions were disqualified, and the tender was cancelled accordingly.

 

To bring down the repair cost, alternative construction methodologies were discussed with the consultant and a trenchless technology method was chosen.  The project was re-tendered in September, 2010 under 006-T-10.

 

 


 

BID INFORMATION: 

Advertised, place and date

ETN

Bids closed on

September 24, 2010

Number of contractors picking up bid documents

9

Number of contractors responding to bid

1

 

Note:  Purchasing received feedback from a number of companies who picked up the bid document but did not provide a submission:  Two (2) bidders could not perform a portion of the work.  One (1) bidder offered a price as a sub to another contractor.  One (1) bidder felt they did not have enough experience to be considered by the Town.  One (1) bidder felt the job was too difficult. One (1) bidder could not meet the Town’s specifications.

 

PRICE SUMMARY:

Supplier

Price (Inclusive of HST)

Tectonic Infrastructure Inc.

$396,813.84*

* Price does not include the contingency amount of  $29,603.40 for provisional items that may or may not be required: (Paid duty officer, reinstate pavement markings, Restore boulevards including supply and place topsoil and sod, grading, rolling and staking and test pits for utility and service locates).

 

DISCUSSION:

 

For the first tender (106-T-10) for sanitary sewer repair utilizing an open-cut replacement, the two (2) bid prices of $854,031.00 and $620,478.00 were significantly higher than the anticipated repair cost of $400,000.00. Town staff recognized the price for open-cut construction was too high and consulted with the Town’s consultant to investigate alternative construction methodologies to reduce the total construction cost.

 

Trenchless technology by Cured-in-Place Pipe (CIPP) relining method with pipe bottom grouting was chosen and specified in the contract requirement. This has been determined as the best acceptable method of repair that will restore the structural integrity and flow capacity of the existing pipe at reasonable costs. This chosen trenchless repair method will significantly reduce traffic disruptions, minimize social and environmental impact.

 

A revised tender was issued in September, 2010 under 006-T-10.  One (1) bid was received by Tectonic Infrastructure Inc., who submitted a price very close to the budget. Feedback from other companies who picked up the tender document but did not provide bid submissions is shown above in the Bid Information section.

 

Prior to moving forward with the award, Town staff and the consultant met with the sole bidder (Tectonic) and its sub-contractor to ensure the proposed repair method provided by the bidder is acceptable to all.    Town staff and the consultant have  reviewed the technical aspects of the proposal and recommend that the Town accept the bid submitted by Tectonic.

 

 

 

FINANCIAL CONSIDERATIONS AND TEMPLATE:

The following table is a summary of the financial considerations for this report:

 

Original Budget and Account #

 

$ 1,300,000.00

 

053-6150-8334-005

Sewer System Upgrade Program

Spent to Date

 

-$      23,957.25

 

 

Committed

 

-$      20,890.98

 

 

Budget Available

 

$ 1,255,151.77

 

 

Amount to Allocate to this Project

 

-$    426,417.24

 

Awarded to Tectonic Infrastructure Inc.

Budget Remaining

 

$    828,734.53

 

 

 

Note: The remaining budget will be used for other sewer upgrades as identified under account 053-6150-8334-005.

 

HUMAN RESOURCES CONSIDERATIONS

Not applicable

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

Not applicable

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Purchasing and Legal department have been consulted during this process of moving forward with a sole bidder  and the recommendation to proceed with signing an agreement with Tectonic to undertake this project.

 

 

RECOMMENDED BY: 

 

 

Microsoft Office Signature Line...        Microsoft Office Signature Line...

 


COMMITTEE/COUNCIL ITEM TRACKING FORM

Revised: September 2009

COUNCIL

 

DEVELOPMENT SERVICES

Planning            

Economic Dev.

Transportation  

GENERAL

Community Services                              

Environment & Sustainability                 

Finance & Administrative                       

Lands, Building & Parks Construction    

TARGET MEETING DATE

January 17, 20110

DATE REPORT AUTHORED

November 24, 2010

ITEM TITLE

006-T-10 Steelcase Road East Sanitary Sewer Repair

AGENDA SECTION

TIME TO BE ALLOCATED

Presentation/Deputation            Consent                           Regular

5 minutes

CONFIDENTIAL REPORTS

For in camera reports, please indicate appropriate subsection of  s239(2) Municipal Act ( all applicable):

(a) Security of Property                                                   (e) Litigation or potential litigation        

(b) Personal matters about  individual                              (f) Solicitor-client privilege                    

(c) Acquisition/disposition of land                                  (g) Legislated authority to be in camera 

(d) Labour relations/Employee negotiations

 

ORIGINATOR                                         Ext.

Patti Malone                                                    2239

CONTACT                                   Ext.

Daniel Liu                                          6210

DOES THE REPORT, PRESENTATION, BY-LAW AFFECT OTHER DEPTS:

Yes    No  (List all departments impacted and being consulted on this report.)

Electronic Approval Required by:

Department

Individual

Obtained

General Manager, Waterworks

Jerry Klaus

Director, Operations

Peter Loukes

Commissioner, Community & Fire Services

Brenda Librecz

Commissioner, Corporate Services

Andy Taylor

CAO

John Livey

 

Attachments:

 

 

 

Comments & Questions:

 

Raj Raman comments: “Report alludes to a trenchless technology that only one vendor has submitted a bid. Is this method a way forward for all future similar projects or just a one-off scenario?

 

Daniel Liu answered: “The proposed trenchless method is not a one-off scenario, we are willing to use the proposed method on a trial basis, and if it proves successful, especially if the remote grouting method can be done to the full satisfaction to Town staff, then this type of construction method – remote grouting plus CIPP lining – will be adopted for future similar projects or at least as an option for similar projects.

 

Furthermore, Town has been a consistent advocate for trenchless technology, and the success of this project will enhance Town staff confidence in the application of different types of trenchless technology”

 

Lisa Riegel comments:

The first paragraph under the “Background” section contains the following statement:  “Further to actions to recover the total cost of the repair through legal process from the property owner, Waterworks is recommending to proceed with repairing the sewers to mitigate further damage and risks.”

 

Please confirm whether Operations has:  (1) confirmed the source of the sewer damage; (2) (if confirmed to be the source of the sewer damage) commenced discussions with the property owner to recover the costs of repair; and (3) ( if discussions with the property owner were not successful) consulted with Legal to assess the option of commencing a legal process against the property owner to recover the costs.  If this has not occurred, this statement should be revised as follows:  “Town staff will confirm the source of the sewer damage and the option of recovering the total cost of the repair from the property owner.  However, Waterworks recommends that the Town proceed with repairing the sewers to mitigate further damage and risks.”

 

Daniel Liu’s Answer:

 

After consultation with Shu Min Gao from System Engineering, all the 3 questions had been confirmed, and the item (3) is still ongoing. For further details, please contact Shu Min, Gao, ext. 6230, or Karen Dennison, ext. 2519 from System Engineering.