Report to: General Committee – Finance & Administrative   Date of Meeting: 2011-01-17

 

 

SUBJECT:                         Proposed 2011 Water/Wastewater Rate Increase

PREPARED BY:              Andrea Tang, Manager of Financial Planning

 

 

RECOMMENDATION:

That the report dated January 17, 2011 entitled “Proposed 2011 Water/Wastewater Rate Increase” be received;

 

AND THAT staff be authorized to hold a public meeting on February 1, 2011 at 6:45p.m. on the proposed 2011 Water/Wastewater rate increase;

 

AND THAT the 2011 Town of Markham’s (“Town”) Water/Wastewater rate increase be equivalent to the Region of York’s (“Region”) monetary increase of $0.1352 per cubic metre (m3) based on Region’s estimated increase of 10%;

 

AND THAT in addition to the Region’s increase, the 2011 Water/Wastewater rate increase includes a surcharge of $0.0683/m3;

 

AND THAT effective April 1, 2011, the 2011 Water/Wastewater rate will be $2.4164/m3, an increase of $0.2035/m3.

 

AND THAT Staff be authorized to present the “2011 Proposed Water/Wastewater Rates” presentation (Appendix A) at the February 1, 2011 Public Meeting.

 


PURPOSE:


The purpose of the report is to obtain approval:

 

1.      to hold a public meeting on February 1, 2011 at 6:45p.m. to discuss the 2011 proposed Water/Wastewater rate increase;

 

2.      to increase the Town of Markham’s Water/Wastewater rate by $0.2035/m3 from $2.2129/m3 to $2.4164/m3.

 


BACKGROUND:


 

Markham owns and operates the water and wastewater system, and purchases water supply and wastewater treatment from the Region of York.  Region of York purchases water from the City of Toronto and the Region of Peel.  Region of York’s current wholesale rate is $1.3521/m3 and Markham’s current retail rate is $2.2129/m3.  Revenues are used to fund regional purchases (i.e. water and wastewater costs) and Waterworks costs (i.e. operating and capital).

 

As in previous years, a public meeting will be held before passing a by-law imposing a Water/Wastewater fee or charge.  The public meeting will be held on February 1, 2011 at 6:45p.m. to discuss the 2011 proposed Water/Wastewater rate increase.  Similar to previous years, following approval of this report, staff will advertise notice of the public meeting via the “Town Page” in local newspapers and the Town’s webpage.

 

OPTIONS/DISCUSSIONS:

 

Region’s Increase

The York Region report dated December 18, 2008 identified a 10% increase in the 2011 water and wastewater rates based on a multi-year plan.  Each year, the increase as identified in the plan is reviewed and confirmed by Regional Council as part of the budget process.  A presentation was made to Regional Council on the estimated rate increase in December 2010.  A report on the 2011 Regional rate increase will be brought forward to Regional Council for approval in February 2011. 

 

Therefore, as per the Town’s policy, the Town will match the Region’s monetary increase of $0.1352/m3 based on Region’s forecasted increase of 10%.

 

Water/Wastewater Surcharge

In addition to the Region’s estimated increase, the 2011 rate will include a surcharge of $0.0683/m3 that comprises of the followings:

­   The fourth year of the approved 10 year phase-in of the Water/Wastewater Infrastructure Surcharge to address the ongoing replacement & rehabilitation requirements for Waterworks infrastructure;

­   Cost increases due to inflation;

­   Population growth adjustment

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FINANCIAL CONSIDERATIONS:

 

The 2011 proposed Water/Wastewater rate will be increased by $0.2035/m3 from $2.2129/m3 to $2.4164/m3.  The breakdown of the proposed 2011 rate is outlined below:

 

TABLE A – Water/Wastewater Rate

 

 

 

Impact to Residents & Industrial, Commercial and Institutional (ICI) Customers

An average household has water consumption of 300m3 per year.  With a total increase of $0.2035/m3 (Region’s estimated increase of $0.1352 and Town’s increase of $0.0683) in 2011, there will be an annual increase of approximately $61.05 to an average household bill.  The impact on the top 10 ICI customers, including a health care provider, manufacturers, and hospitality providers, will range from $11K to $31K per year (Region’s estimated increase $7K to $18K and the Town’s increase $4K to $13K).


 

RECOMMENDED BY: 

 

Microsoft Office Signature Line...Microsoft Office Signature Line...


 

Attachment:

Appendix A – 2011 Proposed Water/Wastewater Rates Public Meeting Presentation

 


 

COMMITTEE/COUNCIL ITEM TRACKING FORM

Revised: September 2009

COUNCIL

 

DEVELOPMENT SERVICES

Planning            

Economic Dev.

Transportation  

GENERAL

Community Services                              

Environment & Sustainability                 

Finance & Administrative                       

Lands, Building & Parks Construction    

TARGET MEETING DATE

January 17, 2011

DATE REPORT AUTHORED

January 5, 2011

 

ITEM TITLE

2011 Proposed Water & Wastewater Rate Increase

AGENDA SECTION

TIME TO BE ALLOCATED

Presentation/Deputation            Consent                           Regular

5 minutes

CONFIDENTIAL REPORTS

For in camera reports, please indicate appropriate subsection of  s239(2) Municipal Act ( all applicable):

(a) Security of Property                              (e) Litigation or potential litigation                      

(b) Personal matters about  individual                   (f) Solicitor-client privilege   

(c) Acquisition/disposition of land                       (g) Legislated authority to be in camera    

(d) Labour relations/Employee negotiations

 

ORIGINATOR: Andrea Tang                  Ext. 2433

CONTACT: Andrea Tang             Ext. 2433

DOES THE REPORT, PRESENTATION, BY-LAW AFFECT OTHER DEPTS:

Yes    No  (List all departments impacted and being consulted on this report.)

Electronic Approval Required by:

Department

Individual

Obtained

Finance

Joel Lustig

Finance

Andy Taylor

CAO’s Office

John Livey

 

 

 

 

 

Attachments:

 

 

 

Comments & Questions:

 

 

Q:\Finance\Executive Staff\Sharepoint Reports\2011 Water Wastewater Rate Increase_V3.Doc