|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Alan Brown, Director of
Engineering |
|
|
|
|
PREPARED BY: |
Simon Hung, Development Engineer |
|
|
|
|
DATE OF MEETING: |
September 23, 2003 |
|
|
|
|
SUBJECT: |
Markham Centre Shoring Encroachment Agreement |
|
|
|
RECOMMENDATION:
That
the September 23, 2003 report entitled “Markham Centre, Shoring Encroachment
Agreement”, be received,
That
the encroachment of shoring into public right-of-way for development with
underground structures be authorized subject to conditions satisfactory to the
Town.
And that Mayor and Clerk to be authorized to execute the Shoring
Encroachment Agreements to the satisfaction of the Town Solicitor and Director
of Engineering.
PURPOSE:
This
purpose of this report is:
EXECUTIVE SUMMARY:
BACKGROUND:
The
goal to provide a pedestrian friendly environment in the downtown setting of
Markham Centre encourages buildings to be closer to the public road allowance
with minimal setback. One challenge
that emerges from this concept is that very little space is available for the
excavation of underground structures with proper sloping. Vertical support during excavation to
prevent lateral earth movement is therefore inevitable in order to construct
the underground structure while protecting the public right of way. The proposed
Tridel Circa development has two levels of underground parking structure which
will be 10 metres below existing ground.
An engineering solution is therefore necessary to support the earth on
the public road allowances during the excavation so that the existing boulevard
with sidewalk, utilities or other infrastructure may continue to function.
OPTIONS/DISCUSSION:
The
anchor/tie-back system is being proposed for the Tridel Development (refer to
Fig. 1 and Fig. 2 for details). Prior
to excavation, vertical steel piles are installed along the perimeter of the
excavation at pre-determined intervals and to depths below the base of the
excavation. Excavation will then
proceed to the first anchor level while horizontal timber laggings are
installed between steel piles to support the earth. Inclined holes are drilled into the right-of-way behind the steel
piles in which concrete is poured to form the anchors. Steel cables connecting the concrete anchors
and the steel piles are stressed to provide resistance to the earth pressure
from the un-excavated side. After the
anchors are installed, excavation will proceed to the next anchor level (if
more than one layer of anchors is required, the process will be repeated) or to
the base of the excavation.
The anchor system is the technique of choice by the construction industry and the accepted choice by most municipalities for the following reasons.
· Better control of excavation movements by adjusting the tension in the anchors and the number of anchors.
· The area to be excavated is totally un-obstructed, thus allow uninterrupted earth removal and expeditious construction of the permanent structure. This offers significant saving in cost and time.
· Once the underground structure is completed, lateral support will be provided by the permanent structure and hence renders the anchors redundant.
· The anchors are located sufficiently deep to clear all existing and future utilities and services. In rare occasions, removal of the anchors may be necessary when they conflict with other installations. Removal can be achieved by simply cutting through the anchors. Otherwise, the anchors may be left in place permanently.
The principles of the encroachment agreement shall include all the conditions outlined on page 2 and the following additional requirements.
· Movement of the shoring system shall be monitored by the consulting engineer throughout the entire construction process and work shall be stopped once a 12mm horizontal displacement is reached .
· Piles that encroach into the public right-of-way shall be cut down to depths as specified to provide clearance for utility installation (within 0.3m from the street line, pile shall be cut down 1.5m; more than 0.3m from the street line, pile shall be cut down 2.5m)
· The Owner shall obtain permission from all the utility companies prior to the construction
· The Town may at any time, at its sole discretion, terminate the Agreement upon delivery of Notice to the Owner.
· The encroachment agreement shall be registered on title.
The Encroachment Agreement shall be finalized to the satisfaction of the
Senior Management. A sample agreement
from the City of Toronto is attached for reference.
FINANCIAL
CONSIDERATIONS:
The Owner is responsible for all the costs for processing the
application.
Although it is not anticipated that the piles or anchors will conflict
with existing or future infrastructure, individual assessments may be necessary
to determine if financial compensation is required.
ENVIRONMENTAL
CONSIDERATIONS:
It is not expected that there would be environmental implications.
BUSINESS UNITS
CONSULTED AND AFFECTED:
The Street Services Department have been involved in the analysis and
concur with the recommendations.
The Legal Department and Street Services Department
will provide input into a standard encroachment agreement.
ATTACHMENTS:
Fig. 1 Typical cross section with
anchors
Fig. 2 Photographs of excavation
with anchors
Sample “Tie-back Piling and Shoring Agreement” from City of Toronto
|
|
|
Alan Brown, C.E.T. Director of Engineering |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
Q:\Development\Engineering\SITEPLAN\Con
4\411SC2317\Shoring Report.doc