DEVELOPMENT SERVICES COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Jim Baird, Commissioner of Development Services

Valerie Shuttleworth, Director of Planning & Urban Design

 

 

 

 

PREPARED BY:

Markham Centre Team

Richard Kendall, Senior Project Co-ordinator, extension 6588

 

 

 

 

DATE OF MEETING:

2004-Jan-20

 

 

 

 

SUBJECT:

Ruland Properties Inc. (The Remington Group)

Public Amenity Feature for Downtown Markham

 

 

 


 

RECOMMENDATION:

That the report dated January 20, 2004, entitled “Ruland Properties Inc. (The Remington Group)

Public Amenity Feature for Downtown Markham”, be received;

 

That staff  report back with a Terms of Reference for a process to create an open space amenity feature within Block OS4 of the approved draft plan, including a design charrette to obtain public input;

 

That staff report back with the draft terms of  a Memorandum of Understanding with the applicant, to address the process and financial matters as outlined in this report;

 

And that staff also report on any revisions to the draft approved plan and conditions of Draft Plan Approval resulting from the introduction of a new open space amenity feature.

 

PURPOSE:

This report is a follow up to the discussion at Development Services Committee on December 9, 2003 in regard to the originally proposed lake feature on the Remington Downtown Plan. Ruland Properties Inc. (Remington Group) advised Committee on December 9 of their decision to make a design change to delete their originally proposed lake feature for technical reasons, and to work with the Town to create an alternate open space amenity feature.  The purpose of this report, as requested by Committee, is to provide additional information regarding agency concerns with respect to the functioning of the proposed lake feature, and to discuss options related to the introduction of a new amenity feature within the Remington Group’s Downtown Markham Plan to replace the lake feature.

 

 

BACKGROUND:

In July, 2003, Council granted draft plan approval to the Remington Group for their Downtown Markham Plan.  This plan provided for the comprehensive development of approximately 98.3 ha. (243 acres) of land, representing the future downtown core of Markham Centre.

 

The Downtown Markham project, at full build-out would provide for approximately 3,900 residential units, 362,750 square metres of office and business park uses, as well as 33,755 square metres of retail floor area.  This project also serves to deliver much of the infrastructure required to support Markham Centre, including the easterly extension of Enterprise Boulevard through to the GO line, the extension of Birchmount Road south from Enterprise Boulevard and the delivery of lands within the Rouge River valley to the Town. 

 

A key component of the Remington proposal was the approximately 2.4 ha. (6 acre) water feature referred to as “Park Lake”.  Bounded by the Rouge River Valley to the north, the proposed Civic Square to the south, the downtown shopping district to the west, and a relocated Tributary 4 and residential district to the east, Park Lake was strategically located to serve as a central focus for the plan and Markham Centre.  At the time of preparation of the July 7, 2003, staff report on the Remington Plan a number of technical issues remained to be resolved concerning flows between Tributary 4 and the lake, and whether the lake would ultimately be approved by the environmental approval agencies.

 

In recognition of some of these technical challenges, the draft plan conditions contained policies to deal with issues related to the lake, the need for environmental agency approval, and the long term ownership and maintenance of the lake if approved for construction.  The conditions also spoke to the owner undertaking studies to develop, and construct an alternative form of central, publicly accessible open space amenity within Markham Centre, if, prior to final approval of the draft plan it was determined that the lake was not sustainable.

 

Subsequent to the granting of draft plan approval and further discussions with the regulating agencies and the Town, the applicant has concluded that the lake is not a viable amenity within Downtown Markham.  The applicant made a presentation to Development Services Committee on December 9, 2003, at which time they outlined their position (see letter from applicant, Attachment No. 1), the nature of concerns raised by the Department of Fisheries and Oceans, and Ministry of Natural Resources, and other constraints within the utility corridor on the south side of Highway 407, where the reconfigured Concanmar Pond would have to be located.  Council referred this matter back to staff to work with the applicant to identify an alternate amenity feature for Downtown Markham, commensurate to the value of the lake feature.  The Committee also requested written confirmation from the regulatory agencies regarding their position with respect to the status of the lake.

 

This matter was also reviewed at the December 11th meeting of the Markham Centre Advisory Committee, with the applicant and the TRCA representative on the Advisory in attendance.  In considering this matter, it was suggested that an extra meeting of the Advisory be held to discuss options for an appropriate amenity feature and the steps required to move forward.  This meeting was held on January 8, 2004, at which time the Advisory Committee supported the concept of a design charrette process, with public participation, to create plans for an alternate open space amenity feature.  The Advisory Committee expressed a strong interest in being involved in the planning and delivery of the design charrette process.

 

DISCUSSION:

 

Staff has followed up to obtain further TRCA comments

The Toronto and Region Conservation Authority (TRCA) serves as the Town’s liaison with regulatory agencies representing senior levels of Government on certain environmental matters (i.e. Ministry of Natural Resources and Department of Fisheries and Oceans).  TRCA provides input to the Town regarding requirements of those agencies and facilitates the review, approvals and permitting processes as the lead environmental agency on development matters.   Toronto and Region Conservation Authority staff advise (see letter from TRCA, Attachment No. 2) that although the applicant has undertaken extensive studies to support their Downtown Plan, questions of the viability of the lake feature remain unanswered. TRCA concerns are further compounded by recent constraints being placed on the use of the Hydro corridor on the south side of Highway 407,  which impacts the relocation and expansion of Concanmar Pond and, in turn, the functioning of the lake. 

 

Other concerns identified by TRCA include impacts to water quality and quantity within the adjacent Rouge River, water temperature, impacts to fisheries, and the lack of a design solution which would ensure the continued functioning of the tributary through to the Rouge River.  Given that the applicant has not been able to satisfy these concerns, nor fully addressed the requirements of the other affected agencies (i.e. Hydro One and the Federal Department of Fisheries and Oceans), TRCA staff advise that they accept the applicant’s conclusion that the proposed lake is not viable.  Under the “one window approach” of environmental agency commenting, Town staff have relied on the TRCA to integrate their own comments with those of the Ministry of Natural Resources and the Department of Fisheries and Oceans.

 

Process to be Established to Determine Alternate Amenity Feature

Staff met with the applicant to discuss a process for developing an alternate amenity feature within the Downtown Markham plan.  A key component to any programme to create an alternate feature is the need to ensure public involvement through not only the Advisory Committee but also the broader Markham population.  Other issues which need to be addressed include budget, design elements, programmable components, consultant and capital construction resources required and developer commitment to finance these items, and timing. 

 

It is recommended that a design charrette integrated with a limited design competition, is the most appropriate approach to address the Town’s interests in achieving a central open space feature with professional design input and public consultation, in a timely fashion.  The primary advantage of the design charrette/limited competition is that it is a very inclusive process with greater opportunities for public input.  The charrette can provide an effective process to gain public input into alternative design ideas and a consensus on the types of activities and programmes to be incorporated into the new feature. 

 

Alternative concepts resulting from the charrette will then be evaluated by a selection committee with recommendations brought back to Development Services Committee for approval.  A charrette can be organized relatively quickly to address timing concerns and the need to confirm the design for this central open space feature of Markham Centre.

 

In this regard, staff anticipate that a design competition/charrette could be held in March, provided that technical and financial issues can be resolved, and that a final recommended design could be available for approval by Council as early as April or May. 

 

Memorandum of Understanding Required

The applicant will work with Town and TRCA staff to define the future amenity boundaries, establish an appropriate alignment and buffer zone for the tributary adjacent to the amenity, and resolve any technical issues relating to potential municipal infrastructure requirements beneath the amenity feature.  In this regard, staff recommend that a Memorandum of Understanding be entered into with the applicant which outlines their responsibilities to provide the additional technical material required to move forward with an alternate amenity feature.  The Memorandum would also outline the anticipated financial obligations associated with running a design charrette, and ultimately funding the final design and construction of the new amenity feature. Staff will report back to Committee on the draft terms of the MOU.

 

Terms of Reference for Design Process to be Developed

Once there is a clear understanding of the parameters for developing an amenity feature, staff will prepare detailed terms of reference for a process to identify a design for the amenity feature.  The terms of reference will include the budget, constraints, fixed parameters, key design themes/features, such as fountain/skating rink, public art, cultural components, and requirements for programmable elements/spaces.  The organization, composition and structure of the design charrette, communications programme to support the process, and the retention of design consultants to develop alternatives and support the process, will also be included in the terms of reference.  A report outlining the Terms of Reference and recommended approach will be brought back to Committee at the first available opportunity.

 

Staff also anticipate reporting to Development Service Committee at a later date on any other issues which may arise or necessitate revisions to the previously approved draft plan and/or Conditions of Draft Plan Approval.

 

CONCLUSIONS:

Determining an appropriate alternate central amenity feature for Markham Centre represents a unique challenge and opportunity to engage the community and create a space tailored to the Town’s vision of a truly vibrant, human scale, mixed–use town centre.  In order to position the Town to take full advantage of this opportunity, and recognizing the time urgency to confirm a program for this feature, a number of items need to be resolved, including the execution of the Memorandum of Understanding, the approval of the Terms of Reference for the Design Charrette process, and the resolution of a number of technical and financial issues.  Staff will report back on the draft terms of a Memorandum of Understanding with the applicant, the Terms of Reference for the design process, and on any appropriate revisions to the draft plan and/or Conditions of Draft Plan Approval resulting from changes to the lake and the introduction of a new amenity feature.

 

FINANCIAL CONSIDERATIONS:

Financial obligations on the part of the applicant will be discussed in the Terms of Reference and associated responsibilities identified in the Memorandum of Understanding.

 

ENVIRONMENTAL CONSIDERATIONS:

Issues relating to the interface with the Rouge River Valley and other technical requirements will be resolved through discussions with the TRCA.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Town Solicitor will be consulted in the preparation of the Memorandum of Understanding.  We anticipate that Community Services Staff will actively participate with Development Services Staff in the design process for this important open space feature.

 

 

 

 

 

 

 

 

 

Valerie Shuttleworth, M.C.I.P., R.P.P.

Director of Planning & Urban Design

 

Jim Baird, M.C.I.P., R.P.P.

Commissioner of Development Services

 

 

ATTACHMENTS:

1.         Letter dated December 3, 2003, from Ruland Properties Inc.

2.         Letter dated January 14, 2004, from the TRCA.

 

 

 

Q:\dev\planning\teams\markham centre\coordinators\remington\report-alter amenity