PREPARED BY:

West District

Stephen Kitagawa, Senior Planner

 

 

 

 

DATE OF MEETING:

September 21, 2004     

 

 

 

 

SUBJECT:

Al Hussain Foundation

10992 Kennedy Road

Applications to amend the Official Plan, Zoning By-law, Minister’s Zoning Order (Airport) and For Site Plan Approval, to permit a place of worship in addition to the existing permitted cemetery

File Nos. OPA.96-005, ZO.96-029, ZA.01-118321 & SC.04-018281

 

 

 


 

RECOMMENDATION:

That the Record of the Public Meeting held on October 2, 2001 regarding applications submitted by the Al Hussain Foundation at 10992 Kennedy Road to Amend the Official Plan, Zoning By-law, Minister’s Zoning Order (Airport), to permit the conversion of the existing funeral chapel to a place of worship and the construction a 183.5 m2 addition, be received;

 

That Council endorse the proposed draft Official Plan and Zoning By-law Amendments, to permit the conversion of the existing funeral chapel to a place of worship and construction of a 183.5 m2 addition, attached as Appendix ‘A’ and ‘B’

 

And That the applicant’s exemption request from Bill 27 be endorsed by Council and referred to the Ministry of Municipal Affairs and Housing;

 

And That the draft Official Plan and the Zoning By-law Amendments be presented to Council for adoption, once the Ministry of Municipal Affairs has granted an exemption from Bill 27, permitting the conversion of the funeral chapel to a place of worship and the construction of the 183.5 m2 addition;

 

And Further That staff prepare a further report to Development Services regarding the proposed site plan application to permit the 183.5 m2 addition.

 

PURPOSE:

The purpose of this report is to provide an evaluation of the applicant’s proposal for an amendment to the Official Plan, Zoning By-law, Ministers Zoning Order (Airport) and site plan approval to permit a place of worship, in addition to the existing funeral prayer chapel and cemetery on the subject lands.  The report recommends adoption of the Official Plan Amendment and approval of the Zoning By-law Amendment.

 

BACKGROUND:

Property located on the west side of Kennedy Rd., north of Elgin Mills

The 1.9 hectare (4.74 ac.) property is located on the west side of Kennedy Road, North of Elgin Mills Road, with 66 metres (216 ft) of frontage on Kennedy Road.  The site currently contains a cemetery and an accessory 600 m2 (6,458 ft2) funeral prayer chapel.  There is an additional 12 ha (30 ac) of land to the north and west of the site within the same ownership, which is intended to remain in agricultural use.

 

In 1997 Council approved a cemetery and accessory funeral prayer chapel on the subject lands.  The application for a 2500 m2 place of worship was deferred at that time

In 1996, the Al Hussain Foundation submitted applications to amend the Official Plan (Revised 1987) and Zoning By-law 304-87, as amended, to permit a 2500 sq. m. place of worship and a cemetery on 4 hectares of land at 10992 Kennedy Road.  Council partially approved those applications (excluding the 2,500 m2 place of worship) as follows:

 

a.       Official Plan Amendment No. 53, approved May 26, 1999, re-designated 1.9 ha of land at the southeast corner of the property municipally known as 10992 Kennedy Road from “Agriculture- A1” to “Institutional – Cemetery” to permit a cemetery;

b.      Zoning By-law 238-98 was passed by Council to permit a cemetery and an accessory funeral prayer chapel and storage building not exceeding 600 sq. m. on the subject property. The building was restricted to a maximum of one storey not exceeding 300 sq. m. ground floor area, with the remainder of the floor area below grade; 

c.       That portion of the Al Hussain Foundation applications for Official Plan amendment and rezoning seeking approval to permit a place of worship on the subject property was deferred by Council in 1997 pending a review of the Town’s place of worship policies; and,

d.   A site plan control agreement for a cemetery and funeral prayer chapel was registered in June 2000.

 

Other necessary approvals for the cemetery and accessory funeral prayer chapel were obtained

A Regional Official Plan Amendment, required to permit the cemetery, was approved in April 1999.  It added a site-specific exception to permit a cemetery and accessory building on 1.9 ha (4.6 ac) of land in the “Agriculture Policy Area” designation in the Regional Official Plan.

 

A Minister’s Zoning Order (Airport) Amendment was approved in March 1999, permitting a cemetery together with an accessory prayer chapel and storage shed, subject to a maximum height of one storey, a maximum gross floor area of 600 m2 (6,458 ft2), a maximum ground floor area of 300 m2 (3,229 ft2) and minimum front and side yard requirements.

 

February 2001, the owner submitted a revised application to permit a place of worship on the site

The applicant’s revised proposal was to construct a 1058 sq. m. addition to the north, west and south sides of the existing 600 sq. m. funeral prayer chapel, and reconfigure the building to a 1658 m2 (17,847 ft2) place of worship, half of which would be below grade.  The proposed uses within the expanded building included a lobby, prayer hall, office, and funeral chapel on the ground floor, and a second prayer hall, kitchen, washrooms, library, and storage area on the basement floor.  The proposed building would have a height of 20m for the dome, and 25.5m for two minarets.  In support of the revised applications, the applicant submitted:

  1. A conceptual site plan illustrating a 1658 m2 (17,847 ft2) place of worship and 98 parking spaces;
  2. A draft Official Plan Amendment proposing a redesignation of the site from “Institutional – Cemetery” to “Institutional – Place of Worship”;
  3. A Justification Report for the proposal which included:

a.       Planning analysis (February 2001);

b.      Agricultural Assessment (March 1997);

c.       Traffic Analysis (June 1997);

d.      Functional Servicing Analysis (June1997); and,

e.       Hydrogeologic Review (March 1997).

 

In October 2001, the applicant submitted an application to the Ministry of Municipal Affairs and Housing to amend the Minister’s Zoning Order (Airport) to permit this development.  The Province is awaiting the Town’s comments.  To date, no decision has been made by the Minister on that application.

 

A statutory public meeting was held in October 2001.

On October 2, 2001 a statutory public meeting was held to consider the applications for Official Plan Amendment and rezoning to permit an expansion and conversion of the existing 600 m2 (6,458 ft2) building to a 1658 m2 (17,847 ft2) place of worship.   Development Services Committee referred the applications back to staff and the consultant for the Places of Worship Study for a report and recommendation following the Places of Worship Study open house.  The Open House was held on September 5, 2002.

 

Revised plans for a 2011 m2 (21,646 ft2) place of worship submitted in 2002.

In February 2002, the applicant submitted revised drawings illustrating a 2011 m2 (21,646 ft2) place of worship, with a capacity of 511 persons in the ground floor prayer hall, and 116 parking spaces.  On September 19, 2002 these plans were presented at a public information meeting arranged by the Ward Councillor.

 

Resident’s concerns relate primarily to the impact of the proposal on the surrounding area

Concerns expressed through the public process included traffic congestion, the capacity of the building, adequacy of on-site parking, preservation of the rural atmosphere, noise, impact on agricultural operations, precedent for further urban development in the rural area, the impact of the proposed development and associated septic system on surrounding wells and tile drainage, the relationship between the proposal and the Places of Worship Study, and the visual impact, including lighting, massing and colour of the building.

 

Council authorized the Places of Worship Study to include an evaluation of the Al Hussain Foundation Applications.

In July 2001, Council authorized the retention of Macauley Shiomi Howson Ltd., and associated sub-consultants, to undertake the Places of Worship Study.  The approved Terms of Reference for the Places of Worship study included identification of issues and trends relating to places of worship, a comprehensive review of the Town’s policies relating to places of worship including parking standards, as well as a review of the Al Hussain Foundation applications for Official Plan Amendment and rezoning to permit a place of worship at 10992 Kennedy Road.

 

The review of the applicant’s justification report by Macaulay Shiomi Howson concluded that:

  • The Place of Worship needs of the Islamic community are for regional places of worship, however, this trend is also true for other religious groups;
  • The Town’s policies appear to be successful in providing locations for regional places of worship;
  • There is no general trend to combining new cemeteries and places of worship; and,
  • The financial issue raised, related to the additional costs of combining cemeteries and places of worship, is unique to the Al Hussain site and arises because they have an existing cemetery and funeral prayer chapel facility, which can be easily expanded to accommodate a place of worship.

 

The Places of Worship Study concluded that the Town’s current planning policies for new places of worship in the rural area are appropriate.

The Places of Worship Study concluded that there appears to be no need or justification for a change to the current policy of prohibiting the development of new places of worship in the rural area, except in unique circumstances.  The rationale for these conclusions included:

·        The range of site needs, including places of worship which serve a regional function, can be met in the urban area;

·        No significant growth is expected in the rural area, so new places of worship are not required to serve the rural community;

·        The policy direction at the Provincial, Regional and Town levels directs that the rural area be “the focus of resource activity, resource-based recreational activity and other rural land uses”, and not uses which have the option of locating in the Urban Area; and,

·        The financial situation of worship groups is not sufficient justification for permitting places of worship in the rural area.

 

The consultant’s study concluded that the Al Hussain proposal for a place of worship presents a unique circumstance in which a place of worship could be permitted within the existing building with minimal impacts on the surrounding area, provided that certain technical issues can be addressed.  The unique circumstances noted by the consultants included:

 

·        the lands have already been taken out of agriculture use (as a result of the redesignation to permit a cemetery and prayer chapel);

·        the lands have been designated for institutional use, including an approved building intended for funeral prayers and preparation;

 

The consultant concluded that the key impacts from the proposed expansion and conversion of the building to a place of worship are the additional visual impact and the impact of the expanded activity at the site on the rural area.  Restricting the place of worship use to the existing building could minimize each of these impacts, provided that technical issues relating to traffic, parking and servicing can be addressed. 

 

The applicant’s current application proposes to convert existing funeral prayer chapel to place of worship and to construct a 183.5 m2 addition

The applicant has submitted an Official Plan Amendment, Zoning By-law Amendment and an Amendment to the Minister’s Zoning Order (Airport) in support of the proposal to permit the conversion of the existing funeral prayer chapel to a place of worship in addition to the permitted cemetery.  The applicant has also submitted a site plan application to permit the construction of a 183.5 m2 (1,975 ft2) addition to the existing 600m2 (6,485ft2) prayer chapel.

 

Council has approved, in principle the conversion of the funeral prayer chapel to a place of worship

In June 2003, Council approved, in principle, the conversion of the existing funeral prayer chapel to a place of worship, in addition to the permitted cemetery, subject to:

 

  • The place of worship use being confined to the existing building (600 m2) plus any necessary minor additions which serve to improve the functionality of the existing structure for use as a place of worship, but do not increase the person capacity of the worship area;
  • Clarification from an architect, as to the person capacity of the worship area, as defined by the Places of Worship Study;
  • Provision of sufficient parking on the site to meet or exceed the new parking standard for places of worship recommended by the Places of Worship Study;
  • Submission of a traffic impact study, acceptable to the Town and the Region;
  • Confirmation that the proposed private sewage and water services are adequate for the proposed place of worship use and will not have any significant negative impact on surrounding land uses;
  • Submission of a site plan application for a place of worship within the existing building, including landscaping and elevation drawings; and,
  • Submission of an application to the Region of York for amendment to the Regional Official Plan to permit the conversion of the existing building to a place of worship, in addition to the permitted cemetery use.

 

Following the submission of the required plans, supporting studies and applications, staff was directed by Council, to report back to Development Services Committee regarding the revised applications.

 

 

OPTIONS/DISCUSSION:

 

Official Plan Amendment required to allow development to proceed

The proposed Official Plan Amendment (Appendix ‘A’) includes a new site-specific policy providing for the place of worship on these lands.

 

Amendment to the Zoning By-law required to support development

In order to permit the place of worship on the subject property, a zoning by-law amendment is required adding the new use.  A draft by-law is attached as Appendix ‘B’.

 

The lands are subject to Bill 27

Bill 27 is a Provincial Act to establish a greenbelt study area that is intended to, among other things, protect agricultural land by establishing clear limits on development.  The Act received first reading in December 2003, and is retroactive to that date.  It received Royal Assent on June 24, 2004.  The Act restricts municipalities from making decisions on some planning matters within the defined greenbelt study area.

 

Under Bill 27, municipalities are not permitted to adopt or approve any of the following, if it would permit urban uses outside of urban settlement areas:

 

  • Enact by-laws under Section 34 (Zoning), 36 (Holding Provision), 37 (Bonusing), 38 (Interim Control), or 39 (Garden Suites) of the Planning Act.
  • Adopt Official Plans or amendments under Section 17, 21, or 22 of the Planning Act.
  • Approve a draft plan of subdivision under Section 51 of the Planning Act.

 

Bill 27 defines “Urban Settlement Area” as land designated in an upper tier Official Plan as an urban area, urban policy area, town, village, hamlet, rural cluster, rural settlement area, urban or rural system or rural service centre or future urban use area as of December 16, 2003.  The York Region Official Plan does not designate the property at 10922 Kennedy Road as any of the above.  As such, the passing of a zoning by-law or adoption and approval of a local Official Plan Amendment in connection with proposed additional development at 10992 Kennedy Road does not appear to comply with Bill 27.

 

Bill 27 states that any Amendment to the Official Plan and Zoning By-law purported to be enacted or given by a municipality that contravenes this Bill is of no effect. 

 

In March 2004, the applicant forwarded a letter to the Ministry of Municipal Affairs and Housing, requesting an exemption from the provisions of Bill 27 citing, among other things, the recommendations of the Places of Worship Study, comments from the Region of York supporting an exemption to Bill 27 and Council’s approval, in principle, permitting the conversion of the existing funeral prayer chapel to a place of worship.  The Ministry indicated that a Greenbelt Task Force has been formed to determine how to most effectively establish greenbelt protection.  Although they recognize that there may be legitimate reasons why some applications should be allowed to proceed, the Task Force will explore how it might establish a clear and transparent process for dealing with requests from property owners who are affected by Bill 27.  This process is still being formulated.

 

The Region of York is the approval authority for this local Official Plan Amendment.  The Region will not issue a Notice of Decision on this amendment unless it complies with the final provisions of Bill 27.

 

The adoption of the Official Plan Amendment or passing of the Zoning By-law for additional urban uses at 10922 Kennedy Road should await approval of an exemption to Bill 27 by the Ministry of Municipal Affairs.

 

The Official Plan Amendment and Zoning By-law will be presented to Council for adoption, once the Ministry of Municipal Affairs grants an exemption from Bill 27.

 

The Region of York and Town staff support an exemption from Bill 27 to permit the current place of worship proposal.

 

 

Current Proposal is for Place of worship use confined to existing building, plus any necessary minor additions

The current proposal is in keeping with the June 2003 Council direction to support the conversion of the existing funeral prayer chapel to a place of worship, plus an addition to improve the functionality of the structure.

 

The applicant proposes to construct a 183.5 m2 addition to the existing prayer chapel, 120.8 m2 (1,300 ft2) of this floor area will be above grade, the basement will be 62.7 m2 (674.9 ft2).  The uses of the proposed addition to the ground floor plan are limited to men’s and women’s coat/shoe rooms, lobby, stairs and elevator shaft.  The basement addition consists of a lobby, stairs and elevator shaft (Figure 7).  The addition does not increase the person capacity of the worship area.  The worship area is contained within the existing building.

 

Clarification of the person capacity from architect

The Places of Worship Study recommends the person capacity of the worship area should be determined as the greater of:

 

  • One fixed seat person or,
  • 0.5 m bench space per person or,
  • 0.75 m2 net floor area per person in non-fixed seating areas.

 

The applicant has indicated that the worship area does not contain any fixed seats or benches.  Therefore, the capacity is 464 persons, based on the net floor area of the worship area.  The applicant has indicated that the person capacity as defined by the Places of Worship Study is higher than the 150 persons they anticipate will attend.

 

 

 

Sufficient on site parking is to be provided, in accordance with the new parking standards

Based on the higher of 1 space per 4 person capacity of the worship area or 1 space per 9 m2 net floor area of the building, 116 parking spaces are required.  The applicant’s original site plan submission indicated only 109 parking spaces.  The applicant revised the plan to provide the additional 6 spaces, including 5 handicapped spaces to comply with the parking standards recommended in the Places of Worship Study.

 

Submission of traffic study required

The applicant submitted a traffic study to the Town and the Region of York in December 2003.  The Region of York have advised that they concur with the conclusions of the Traffic Impact Study submitted by the proponent and that a southbound right turn lane and a northbound centre left turn lane are required.  The new turn lanes are required as a condition of site plan approval.  The study indicates that the total future traffic volumes revealed good levels of service at the Kennedy Road entrance and the expansion is not expected to generate additional site traffic, as the capacity of the mosque (i.e. prayer hall area) is not being increased.

 

Confirmation that the proposed private sewage and water services are adequate and will not have a negative impact on the surrounding uses.

The applicant’s environmental engineer indicates that the existing sewage system has a one week storage of effluent.  The proposed mosque is typically utilized once per week and although the daily discharge is for 250 people per day, the weekly sewage loading rate is 1,750 people/week.  Any peak load that may occur in one day would be held in the balancing tank and discharged to the system over the next six days.  The proposed mosque’s person capacity is set at 464 persons.  Should this many people attend on a given day, the effluent would be discharged over the next two days and there would be no generated flow other than for cleaning staff.  The applicant’s engineer recommends that a permanent sign indicating that the occupant load should be posted for a maximum weekly occupancy of 1,750 people, thus meeting the requirements of the Ontario Building Code.

 

Site plan approval required

The applicant submitted a site plan application and revised plans on June 17, 2004, to permit a 183.5 m2 (1,975 ft2) expansion to the existing building.  The site plan application is currently under review by Town Departments and outside agencies.  Site plan approval is delegated to the Director of Planning and Urban Design, however, on August 30, 2004, Development Services Committee directed staff to report to Development Services with respect to site plan approval.  Once the Official Plan Amendment and Zoning By-law have been adopted by Council, the site plan will be forwarded to Development Services at a later date.

 

Submission of an application to amend the Regional Official Plan

The site is designated “Agricultural Policy Area” by the Regional Official Plan, which permits farm and accessory uses.  On April 20, 1999, Amendment No. 8 to the Regional Official Plan came into full force and effect providing a site specific exception to the policies of the “Agricultural Policy Area.”  That amendment permits a cemetery and accessory building on 1.9 hectares (4.7 ac.) of the applicant’s landholding.

 

The Planning Justification Study submitted by the applicant indicates that the proposed addition to the existing building will improve the functionality of the building, acknowledge a unique situation on the property and will not remove any additional land from the agricultural production.  Based on this, the proposed addition is considered a minor addition to the existing funeral prayer chapel building permitted by Regional Official Plan Amendment No. 8.  The Region indicates that a further amendment to the Regional Official Plan to permit the conversion of the funeral prayer chapel to a place of worship and to construct the addition is not required.

 

FINANCIAL CONSIDERATIONS:

There are no financial matters to be considered

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The application has been circulated to Town Departments for review and comments.  All conditions and requirements received have been addressed and will be incorporated in the site plan agreement.        

 

CONCLUSION:

Region of York and Town staff support the applicant’s exemption request from Bill 27.  The Official Plan and Zoning By-law Amendments attached as Appendix ‘A’ and ‘B’ will be forwarded to Council, without further report, once an exemption from Bill 27 is received from the Ministry of Municipal Affairs.  A further report to Development Services Committee related to the site plan application will be forwarded once all site plan issues have been dealt with and an exemption to Bill 27 has been granted.

 

 

 

 

 

 

 

Valerie Shuttleworth, M.C.I.P., R.P.P.

Director of Planning & Urban Design

 

Jim Baird, M.C.I.P., R.P.P.

Commissioner of Development Services

 

 

 


 

ATTACHMENTS:                Figure 1 – Applicant/Agent and Location Map

                                                Figure 2 – Area Context and Zoning

                                                Figure 3 – Air Photo

                                                Figure 4 – Site Plan

                                                Figure 5 – Elevations

                                                Figure 6 – Elevations

 

                                                Appendix ‘A’ – Draft Official Plan Amendment

                                                Appendix ‘B’ – Draft Zoning By-law

 

APPLICANT/AGENT:          Khalil U. Syed

                                                100 Mclevin Avenue

                                                Suite 211

                                                Scarborough, ON

                                                M1B 2V5

                                                Tel:  (416) 298-4001

                                                Fax:  (416) 298-4341

 

 

 

 

 

 

 

 

 

Q:\Development\Planning\APPL\SITEPLAN\04 018281 Al Hussain Foundation\final report.doc