APPENDIX B:  Markham Energy Conservation Office Budget
20-May-05
Approved Programs Year 1 Year 2 Year 3 Total Annual Energy Savings (kWh)  Annual Energy Savings ($0.11/kWh)
Markham ECO BBP $105,000 $95,000 $95,000 $295,000 3,000,000 $330,000
Advancing High Performance Building $105,000 $90,000 $90,000 $285,000 1,250,000 $137,500
Cool Shops $95,000 $40,000 $40,000 $175,000 1,200,000 $132,000
Combined Metering Pilot $95,000 $5,000 $5,000 $105,000 160,000 $17,600
Intelligent System Monitoring $50,000 $10,000 $10,000 $70,000 200,000 $22,000
Employee Awareness Programming  $50,000 $10,000 $10,000 $70,000 800,000 $88,000
Totals $500,000 $250,000 $250,000 $1,000,000 6,610,000 $727,100
Individual Program Budgets 
Markham ECO BBP CUI I0&R $13,500 $0 $0 $13,500
BBP Energy Analyst $59,000 $70,000 $70,000 $199,000
Program Design/Upgrades $12,500 $5,000 $5,000 $22,500
Admin $5,000 $5,000 $5,000 $15,000
Communication $5,000 $5,000 $5,000 $15,000
Operations $10,000 $10,000 $10,000 $30,000
Totals $105,000 $95,000 $95,000 $295,000
Advancing High Performance Building CUI I0&R $13,500 $0 $0 $13,500
AHPB Guideline Design  $26,500 $5,000 $5,000 $36,500
AHPB Program Advisor  $45,000 $65,000 $65,000 $175,000
Admin $5,000 $5,000 $5,000 $15,000
Communication $5,000 $5,000 $5,000 $15,000
Operations $10,000 $10,000 $10,000 $30,000
Totals $105,000 $90,000 $90,000 $285,000
Cool Shops  CUI I0&R $12,500 $0 $0 $12,500
CS Mgmt&Admin $14,500 $9,500 $9,500 $33,500
Street Teams $13,500 $6,500 $6,500 $26,500
MECO Coordinator $13,500 $6,500 $6,500 $26,500
Marketing  $12,500 $2,500 $2,500 $17,500
Products $6,000 $3,750 $3,750 $13,500
Incentives $2,500 $1,250 $1,250 $5,000
Admin $5,000 $2,500 $2,500 $10,000
Communication $5,000 $2,500 $2,500 $10,000
Operations $10,000 $5,000 $5,000 $20,000
Totals $95,000 $40,000 $40,000 $175,000
Combined Metering Pilot CUI I0&R $12,500 $0 $0 $12,500
Pilot Design/ Assessment  $12,500 $5,000 $5,000 $22,500
Capital Investment $60,000 $0 $0 $60,000
Admin  $5,000 $0 $5,000
Operations $5,000 $0 $0 $5,000
Totals $95,000 $5,000 $5,000 $105,000
Intelligent System Monitoring CUI I0&R $6,500 0 0 $6,500
ISM Staff $13,500 $0 $0 $13,500
System Purchase $20,000 $0 $0 $20,000
Upgrades/Hosting $7,500 $7,500 $7,500 $22,500
Admin $2,500 $2,500 $2,500 $7,500
Totals $50,000 $10,000 $10,000 $70,000
Employee Awareness Programming  CUI I0&R $6,500 $0 $0 $6,500
Program  Design  $7,500 $0 $0 $7,500
EAP Staff $23,500 $5,000 $5,000 $33,500
Admin $2,500 $1,250 $1,250 $5,000
Communication $5,000 $1,250 $1,250 $7,500
Operations $5,000 $2,500 $2,500 $10,000
Totals $50,000 $10,000 $10,000 $70,000
Combined MECO Budget Items
CUI I0&R $65,000 $0 $0 $65,000
Admin $25,000 $16,250 $16,250 $57,500
Communication $20,000 $13,750 $13,750 $47,500
Operations $40,000 $27,500 $27,500 $95,000
Totals $150,000 $57,500 $57,500 $265,000