| Appendix A | |||||||
| Clegg Rd Extension and Courtyard Ln Construction Budget Change | |||||||
| Original Budget | |||||||
| Funding Source | |||||||
| Components | Projects | Description | Tax | DCA | DCA - Developer Financed | MDE | Total |
| Design | 83 5350 6113 005 | Clegg Road Extension to Warden Avenue - Detail Design | 72,800 | 72,800 | |||
| Construction | 83 5350 6740 005 | Clegg Extension & Cedarland Dr. | 49,360 | 1,942,380 | 110,160 | 2,101,900 | |
| 83 6150 7265 00 | Clegg Road Extension and Cedarland Drive Reconstruction | 898,100 | 898,100 | ||||
| Total | 49,360 | 2,015,180 | 1,008,260 | - | 3,072,800 | ||
| Revised Budget | |||||||
| Funding Source | |||||||
| Components | Account | Description | Tax | DCA | DCA - Developer Financed | MDE | Total |
| Design | 83 5350 6113 005 | Clegg Road Extension to Warden Avenue - Detail Design | 180,904 [1] | 180,904 | |||
| Construction | 83 5350 6740 005 | Clegg Extension & Courtyard Lane Construction | - | - | 3,563,976 [2] | 480,000 | 4,043,976 |
| 83 6150 7265 00 | Clegg Road Extension and Cedarland Drive Reconstruction | Close | |||||
| Total | - | - | 3,744,880 | 480,000 | 4,224,880 | ||
| Change vs. Original Budget | |||||||
| Funding Source | |||||||
| Components | Projects | Description | Tax | DCA | DCA - Developer Financed | MDE | Total |
| Design | 83 5350 6113 005 | Clegg Road Extension to Warden Avenue - Detail Design | - | (72,800) | 180,904 | - | 108,104 |
| Construction | 83 5350 6740 005 | Name Changed to Clegg Extension & Courtyard Lane Construction | (49,360) | (1,942,380) | 3,453,816 | 480,000 | 1,942,076 |
| 83 6150 7265 00 | Clegg Road Extension and Cedarland Drive Reconstruction | - | - | (898,100) | - | (898,100) | |
| Total | (49,360) | (2,015,180) | 2,736,620 | 480,000 | 1,152,080 | ||