Budget Revised Budget Comments
Project 6113 Clegg Rd Extension to Warden Ave - Detailed Design           72,800                            180,904 Original design did not incorporate reconstruction of Cedarland Dr and construction of Courtyard Lane
Project 6740 Construction of the extension of Clegg Road and the reconstruction of Cedarland Drive from Town Centre Blvd. to Warden Avenue.        2,101,900                         2,552,527 Original construction did not incorporate construction of Courtyard Lane
MDE Heating/ Cooling Component Cost                            480,000
10% Construction Contingency                            255,253
Geotechnical and Material Testing                              40,000
Warden Connections by the Region                            400,000
Intersection Improvement at Warden by the Region                              56,460
Contract Administration                            107,800
Internal Capital Admin           55,468                            178,328
      2,230,168                         4,251,272
Funding By DCA DCA - Developer financed