Budget |
Revised Budget |
Comments |
Project
6113 Clegg Rd Extension to Warden Ave - Detailed Design |
72,800 |
180,904 |
Original design did not
incorporate reconstruction of Cedarland Dr and construction of Courtyard Lane |
Project
6740 Construction of the extension of Clegg Road and the reconstruction of
Cedarland Drive from Town Centre Blvd. to Warden Avenue. |
2,101,900 |
2,552,527 |
Original construction did not
incorporate construction of Courtyard Lane |
MDE
Heating/ Cooling Component Cost |
|
480,000 |
|
10%
Construction Contingency |
|
255,253 |
|
Geotechnical
and Material Testing |
|
40,000 |
|
Warden
Connections by the Region |
|
400,000 |
|
Intersection
Improvement at Warden by the Region |
|
56,460 |
|
Contract
Administration |
|
107,800 |
|
Internal
Capital Admin |
55,468 |
178,328 |
|
|
|
|
|
2,230,168 |
4,251,272 |
|
|
|
Funding By |
DCA |
DCA - Developer financed |
|
|
|
|
|