| Budget | Revised Budget | Comments | |
| Project 6113 Clegg Rd Extension to Warden Ave - Detailed Design | 72,800 | 180,904 | Original design did not incorporate reconstruction of Cedarland Dr and construction of Courtyard Lane |
| Project 6740 Construction of the extension of Clegg Road and the reconstruction of Cedarland Drive from Town Centre Blvd. to Warden Avenue. | 2,101,900 | 2,552,527 | Original construction did not incorporate construction of Courtyard Lane |
| MDE Heating/ Cooling Component Cost | 480,000 | ||
| 10% Construction Contingency | 255,253 | ||
| Geotechnical and Material Testing | 40,000 | ||
| Warden Connections by the Region | 400,000 | ||
| Intersection Improvement at Warden by the Region | 56,460 | ||
| Contract Administration | 107,800 | ||
| Internal Capital Admin | 55,468 | 178,328 | |
| 2,230,168 | 4,251,272 | ||
| Funding By | DCA | DCA - Developer financed | |