Report to: Development Services Committee Date of Meeting: March 18, 2008
SUBJECT: PRELIMINARY REPORT
Ruland Properties Inc.
Verdale
Project – Downtown
Zoning By-law Amendment Application
Plan 19TM01012
ZA 08 107542
PREPARED BY:
Extension 6588
RECOMMENDATION:
That the Preliminary Report titled “Ruland Properties Inc., Verdale Project – Downtown Markham – Phase 1, Zoning By-law Amendment Application”, be received;
That staff be authorized to schedule a public meeting on the requested zoning amendments;
That the enhanced notice procedure for Markham Centre applications not be applied to this application, and that the notice for public meeting be based upon the statutory requirement of 120 metres from the property line, as well as a direct mailing to members of the Markham Centre Advisory and all those on record of requesting notice; and,
That Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable
FINANCIAL CONSIDERATIONS:
Not applicable
1. Purpose 2.
Background 3. Discussion 4.
Financial
5. Others (Environmental,
Accessibility, Engage 21st, Affected Units) 6. Attachment(s)
The purpose of this report is to discuss, and call a public meeting on, proposed amendments to the Markham Centre Zoning By-law to permit an additional 4 storeys (approximately 12.43 metres) of height within Building ‘I’ of the Remington Group’s (Ruland Properties Inc.) Verdale project within Downtown Markham. Currently, the permitted height is 10 storeys.
The vacant, 0.817 hectares (2.02 acre)
property is located within the Remington Group’s ‘Downtown Markham’ project, at
the southwest corner of the future intersection of
In June, 2007, Council considered a report recommending endorsement of
an application for site plan control approval for three apartment
buildings (Verdale) 6 and 10 storeys in height containing a total of 421 units within
the first residential phase of the ‘Downtown Markham’ project (which also
includes the four Rouge Bijou buildings currently under construction). At that time, concerns were identified with
respect to certain design elements and the proposed colour palette and Council
referred the application to the
Unionville Sub-Committee.
The Sub-Committee, following its meeting in July, endorsed the recommendations contained in the staff report, subject to final approval of brick colour and balcony details. Since then the Remington Group, working with staff and the local Councillor have finalized the design, and staff are in the process of issuing endorsement of the site plan application.
Height Policies are set out in the Secondary Plan
The Markham Centre Secondary Plan
contains a series of provisions relating to height, with the final
determination to be addressed through the Precinct Plan process. Higher buildings may be permitted at key
strategic “landmark” locations, subject to Council being satisfied as to the
quality of the design, and provided there is a proper gradation of overall height. Policies are also in place which allow for
residential buildings to have an equivalent height to the 13 storey office
building module, which has resulted in the 16 storey residential buildings
which have been approved in the Highway 7 and
Key strategic or “landmark” locations for taller buildings within Markham Centre are set out in Schedule DD – Community Structure Plan in OPA 21. The Secondary Plan also provides Council with the flexibility to allow for a building or buildings to exceed the general maximums as set out in the Plan, without amendment, provided the purpose and intent of the Secondary Plan are otherwise met. A key consideration in achieving this height programme is Council being satisfied with the quality of the building design.
Zoning
Amendments are Proposed
The vacant lands are designated
“Community Amenity Area” by the
The Zoning By-law also establishes minimum and maximum height provisions for these lands of 12 metres (3 to 4 storeys) and 31 metres (10 storeys) respectively. The applicants are seeking to increase the maximum permitted height for the northerly-most building – ‘I’ (Figure 4) by 12.43 metres to 43.43 metres, or to 14 storeys from 10 storeys.
While not part of the zoning amendment application, the additional height would accommodate approximately 29 more units within the combined project for a total of 450. These units would be permitted under the current zoning, and allocation is available from the earlier assignment to the Remington Group for their first phase residential component.
Height and Density Review is Underway
In September, 2007, Council considered a staff report on height and density issues in Markham Centre. The report validated the original vision for Markham Centre, as set out in the Markham Centre Secondary Plan (OPA 21), which is based on human-scale, pedestrian-oriented buildings, generally 6 to 8 storeys in height. The report also discussed various technical amendments to the Secondary Plan, and the need to respond to issues associated with taller buildings in Markham Centre, including developing design criteria and examining “landmark” location policies. This review is underway and staff will be evaluating this application in the context of the on-going study, the approved Precinct Plan and the Secondary Plan.
The streetscape relationship to height is important and Markham Centre approvals to-date have included a very strong, urban, built-form next to the street edge, generally with a well-defined building base. In certain instances buildings have been stepped back from the main wall at upper levels (i.e. at 8 storeys and above) to ensure that a comfortable pedestrian environment is maintained at street level. The on-going review of the height policies will look to formalize specific design criteria above the 8 storey benchmark to ensure appropriate massing, streetscape relationship and architectural design, while addressing potential impacts relating to sun/shadow and wind.
Applicant has Responded to Massing Issues
During preliminary discussions with the applicant on the proposal to increase the height of Building ‘I’, staff identified a number of matters which should be addressed in the design of the upper floors (10 – 14) of the building. The applicant’s architect has responded to these matters and has modified the elevations to provide additional stepping at the upper levels for a more distinct building profile and larger green roof terraces for the top 5 floors. New architectural elements have been introduced for the upper floors of this building which are distinct from the other two buildings in the project, including a precast concrete sill at the 10th floor datum line (Figures 6 and 7).
As noted in Figure 6 the design study undertaken by the applicant’s architect indicates that the additional height proposed comprises approximately 7% of the combined site area for the three buildings. The applicant has also reduced the size of the floor plate for the upper floors of the project. Staff are generally comfortable with the treatment of the building as it relates to the additional storeys and the interface with the approved building elevations.
Enhanced notification procedures for
In February, 2003, Council adopted procedures to better promote Markham Centre meetings, including an expanded notice for statutory public meetings that would apply to this application. These enhanced procedures include:
Given the nature of this proposal (revisions to approved plans) and the lack of an established residential community within the area of the Remington Draft Plan, staff recommend that the expanded notice procedure not be applied to this application and that the notice be based upon the statutory requirement of 120 metres, as well as a direct mailing to members of the Markham Centre Advisory and all those on record of requesting notice.
Markham Centre Advisory will be Consulted
This application will be presented to the Markham Centre Advisory for discussion. It is noted, when the original concept for the three 6 to 10 storey buildings within the Verdale project was first before the Advisory (February, 2007), the Advisory rated the proposal Gold for its Built Form, Open Space and Green Infrastructure components, while Transportation was rated Silver. The Advisory complimented the project’s architecture and rated the project “on-target”. As with other projects within their Downtown Markham project, the applicant is committed to L.E.E.D. principles and is targeting a “Silver” ranking.
FINANCIAL TEMPLATE:
Not applicable
ENVIRONMENTAL CONSIDERATIONS:
This previous site plan proposal was evaluated against the Markham Centre Performance Measures and the applicants advise they are targeting a ’Silver’ L.E.E.D. ranking.
ACCESSIBILITY CONSIDERATIONS:
There are no accessibility implications for the
Town in this report.
ENGAGE 21ST CONSIDERATIONS:
The
proposal aligns with the following key Town of
BUSINESS UNITS CONSULTED AND AFFECTED:
The application has been
circulated to applicable departments and agencies for comment, and their
requirements will be addressed in the recommendation report.
RECOMMENDED BY:
|
|
|
Valerie Shuttleworth, M.C.I.P., R.P.P. Director of |
|
Jim
Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
Figure
1: Site Location
Figure
2: Area Context and Zoning
Figure
3: Aerial Photo
Figure
4: Site Plan
Figure 5: Elevations
Figure
6: Architectural Response
Figure
7: Architectural Response - Rendering
Q:\Development\Planning\Teams\Markham
Centre\Coordinator\Remington\Verdale Zoning\Verdale Preliminary Height
Report.doc