Report to: Development Services Committee Report Date:
SUBJECT: PRELIMINARY REPORT
Markham
Centre Development Corporation
Enterprise
Boulevard, west of Kennedy Road
Applications
for Official Plan Amendment and rezoning to permit a mixed-use development
including residential buildings up to 39 storeys,
retail uses and an office building
Files: OP 08 106659 and ZA 08 106664
PREPARED BY: Scott Heaslip, Senior Project Coordinator
Central District, ext. 3140
RECOMMENDATION:
That the report dated April 8,
2008 titled “Preliminary Report, Markham Centre Development Corporation,
Enterprise Boulevard, west of Kennedy Road, Applications for Official Plan
Amendment and rezoning to permit a mixed-use development including residential
buildings up to 39 storeys, retail uses and an office
building,” be received;
And that staff continue discussions with the applicant to address the issues outlined in the staff report;
And that upon resolution of the
issues outlined in the report, staff be directed to report back to Development
Services Committee regarding scheduling a Public Meeting to consider the
applications;
And that Staff be authorized and directed to do all things
necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable.
FINANCIAL CONSIDERATIONS:
1. Purpose 2. Background 3. Discussion 4. Financial 5. Environmental
6. Accessibility 7.
Engage 21st 8. Affected Units 9.
Attachment(s)
The concept plans submitted by the applicant (Figures 4 and 5) show the following:
The applicant
presented the concept plan to Development Services Committee on
The subject lands are designated “Commercial” in the Official Plan.
The overall policy direction for the lands in these designations is as follows:
“Community Amenity Area - General”
“Community Amenity Area - Major Urban Place”
“Open Space – Environmentally Significant”
The lands are currently zoned “Single Family Rural Residential” (RR4) by By-law No. 122-72.
The Owner has applied for Official Plan Amendment and rezoning.
· a maximum building height of 39 storeys on the south block, and 25 storeys on the north block.
· a maximum of 1250 residential units.
· a maximum overall FSI of 3.0.
The requested zoning by-law amendment proposes to rezone the subject lands to permit development in accordance with the applicant’s concept plan. In the event of approval, the lands would be incorporated into the Markham Centre Zoning By-law.
Potential Benefits of Approval of Proposal
The
proposed development would provide the following benefits:
Identified
Concerns/Issues with Proposal
The draft Precinct Plan provides as follows for the subject property:
On September
18, 2007, Development Services Committee passed a resolution affirming the
original vision for Markham Centre as a human-scale, pedestrian-oriented,
transit-supportive, major activity centre for the Town, in particular the
height policies contained within the Markham Centre Secondary Plan (OPA 21),
which call for a mid-rise community with taller building elements concentrated
around strategic “landmark” locations. As noted above the draft Precinct Plan
identifies the portions of the subject property at south-west and north-west
corners of the Enterprise/Rivis intersection as landmark
locations.
Staff
is currently reviewing the height and density policies of the Markham Centre
Secondary Plan, including specific design criteria relating to taller buildings
at “landmark” locations. The subject applications will be considered in
the context of this review. Built
form:
The proposed development needs to address the urban relationship to Density: The Region’s Centres
and Corridors policies include a minimum density target of 2.5 for lands
adjoining the major transit corridors and in Regional Centres,
including Markham Centre. The proposed
development has an overall Floor Space Index of 3.0. Staff are not
fundamentally opposed to the proposed density, provided it can be delivered
within a built form program consistent with the Town’s vision for Markham
Centre as outlined above, and provided that the Town’s Transportation Section
can confirm that the development would not have an unacceptable impact on the
local road network. The applicant needs
to examine with staff how the proposed uses and densities can be achieved in a
built form more consistent with the Markham Centre Secondary Plan vision and
height framework. Retail
component: Appendix 1
(Central Area Statistics) to the Secondary Plan establishes a retail target of
6000 m2 (64,585 ft2) for the entire East District. The proposed development includes a retail
component having a gross leasible area of 11,200 m2
(120,559 ft2). This is
comparable in scale to the existing plaza at the north-east corner of Woodlot: An
environmental impact study is required to confirm the boundaries of the
existing woodlot, assess the impact of the proposed
development and recommend appropriate mitigation measures. As a condition of approval of development of
the subject lands this woodlot will be required to be conveyed to the Town to
be incorporated into the adjoining neighbourhood
park. Technical
reports: Town
departments and public agencies are currently reviewing servicing and
transportation studies submitted by the applicant. The applicant will also be
required to submit wind/shadow studies, an archeological assessment and a noise
study for review. The applicant will also need to
complete the Markham Centre Performance Measures Checklist for review by the
Markham Centre Advisory Committee. Staff will coordinate a presentation of the
proposed development to the Advisory Committee once the applicant has completed
the checklist. Sustainable
Development Standards: The project
architect verbally advised Development Services Committee in February that they
intend to achieve “at least” LEED Silver certification and are considering
connecting the project to District Energy.
Conclusions The applicant needs to reconsider the
built form, height and retail programs to be more consistent with the Town’s
vision for Markham Centre, as expressed in the secondary plan and recently
reconfirmed by Council. Staff will work
with applicant in the context of the review of the Markham Centre Secondary
Plan’s height and density policies to address the issues outlined in this
report. Staff will report back to
Committee regarding the scheduling of a Public Meeting once the issues outlined
in this report have been sufficiently addressed. FINANCIAL
TEMPLATE: Not applicable. ENVIRONMENTAL
CONSIDERATIONS: The applicant will be required to
submit reports to address tree conservation and other environmental impacts of
the proposed development. A minor tributary (manmade ditch)
crosses a small portion of the subject lands south of the YDSS easement. As part of the Canadian Sports Institute
proposal, the Town retained a consultant to review the relocation of this
watercourse to an alignment adjoining Highway 407 and ACCESSIBILITY CONSIDERATIONS: None at this time.
ENGAGE
21ST CONSIDERATIONS: The proposed development promotes a
number of key goals set out in “Engage 21st Century Markham”
including Managed Growth, Quality
Community and Infrastructure Management. BUSINESS
UNITS CONSULTED AND AFFECTED: The proposal has been circulated to other Town
departments and public agencies for review and comment. RECOMMENDED
BY: ________________________
________________________ Valerie Shuttleworth,
M.C.I.P, R.P.P Jim Baird, M.C.I.P, R.P.P Director,
Planning & Urban Design Commissioner, Development Services ATTACHMENTS: Figure 1 – Location Map Figure 2 – Area Context/Zoning Figure 3 – Air Photo Figure 4 – Concept Site Plan Figure 5 – Sections through South
Block Figure 6 - Secondary Plan Figure 7 - Draft East Precinct Plan APPLICANT/AGENT: Peter Smith Bousfields
Inc. 3 Church Street, Unit 200 Toronto, M5E 1M2 Tel: (416) 947-9744 Fax: (416) 947-0781 Email: psmith@bousfields.ca