TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Jim Baird, Commissioner of
Development Services Valerie Shuttleworth, Director of
Planning & Urban Design |
|
|
|
|
PREPARED BY: |
West District Stephen Kitagawa, Senior Planner |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
PRELIMINARY REPORT Branstone Estates Inc. (Greenpark
Homes) Re: Applications For Zoning By-law Amendment
And Site Plan Approval For Condominium Townhouses (Blocks 72, 73 and 75, Plan
65M-3719) (ZA.04-006288 & SC.04-006347) |
|
|
|
RECOMMENDATION:
That a Public Meeting be
held to consider the applications submitted by Branstone Estates Inc.
(Greenpark Homes) for Zoning By-law Amendment and Site Plan Approval for three
blocks of condominium townhouses, Blocks 72, 73 and 75, of Registered Plan
65M-3719, west side of McCowan Road, north of Bur Oak Avenue in the Berczy
Village Community, once the concerns noted in this report have been resolved to
the satisfaction of the Commissioner of Development Services.
PURPOSE:
The purpose of this report is to
provide preliminary information regarding the zoning and site plan applications
by Branstone Estates Inc. consisting of 167 condominium residential dwelling
units on, Blocks 72, 73 and 75, Registered Plan 65M-3719. It is recommended that a statutory public
meeting be held to consider these applications once concerns noted in this
report have been resolved to the satisfaction of the Commissioner of
Development Services.
BACKGROUND:
Property and Area Context
The proposal consists of three separate parcels located within the
Berczy Village Community (Figure 1).
The first parcel (Block 72) is located on the northwest corner of
The third parcel (Block 75) is located on the east side of
Proposal for 167 condominium townhouses
The applicant is proposing a total of 167 condominium townhouse units
ranging in size from 1,500 square feet to 2,217 square feet. The applicant is also proposing to preserve
the existing historic Peterson-Jarvis house located on Block 73. The house is designated under Part IV of the
Ontario Heritage Act and a heritage easement agreement was registered on
TABLE A |
||
Block |
Number Of Units |
Density |
72 |
62 |
44.6 uph (18 upa) |
73 |
54 |
38.6 uph (15.65 upa) |
75 |
51 |
42.5 uph (17.5 upa) |
Total |
167 |
|
Proposal complies with the
The subject lands are designated Urban Residential – Medium Density and
Community Amenity – Arterial in the Berczy Village Secondary Plan. These designations provide for medium density
housing. Detached, semi-detached,
linked, duplex, triplex, fourplex, townhouses, street townhouses, stacked
townhouses, apartments and other forms of multiple unit
housing are contemplated.
The Secondary Plan provides for a net site density (Medium Density
housing) of 37.1 to 79.9 units per hectare (15 to 32 units per acre). The proposed condominium townhouses have a
density ranging from 38.6 uph (15.65 upa) to 44.6 uph (18 upa). The proposed development complies with the
Berczy Village Secondary Plan.
Existing zoning permits townhouses,
amendment required to permit attached front yard garages
Blocks 72 and 73 are currently zoned Residential Three (R3) and Block 75
is zoned Community Amenity One (CA1) by By-law 177-96, as amended by By-law 2002-78. The
amending By-law was implemented in conjunction with Markham Trail’s plan of
subdivision which was registered in January 2003. The existing Residential Three (R3) and
Community Amenity One (CA1) zoning permits a range of low and medium density
residential uses, including townhouses.
However, the Residential Three (R3) zone only permits townhouses that
are accessed by a lane, with detached garages.
A zoning by-law amendment is required to permit the proposed attached
garages in the front yard. Site plan
approval is also required for the three blocks.
POTENTIAL BENEFITS OF APPROVAL OF THE
PROPOSAL:
Some of the anticipated benefits of the proposal include:
·
Provision of valley land;
·
Proposal is in keeping with the Berczy Village Secondary Plan:
·
Increased range of housing types and tenure in the Berczy Community.
The following is a brief summary of concerns/issues raised to date. These matters, and any others identified through the circulation and detailed review of the proposal, will be addressed in a final staff report to be presented to Committee at a later date. The list below includes initial concerns raised by staff; other issues may be raised during a more detailed review of the proposal.
Design
concerns
Initial concerns expressed by the Town’s Planning and Design staff include:
- Staff is reviewing the interface of the residential units to the valley for Blocks 72 and 75, which may entail the relocation of internal driveways to minimize back-lotting onto valleylands.
-
Further clarification and
possibly modification to the design of the townhouse units fronting onto
-
The townhouse elevations are under
review at this time (sample elevations Figures 7 – 9). The units adjacent to
- The tot lot on Block 72 is located in the middle of a traffic island and on Block 75 it is obscured by residential lots. Alternate locations will be recommended by staff to better integrate the tot lots into the development which will improve public safety and allow them to act as focal points within the community.
- The elevations of the townhouses adjacent to the heritage dwelling are to be of a sympathetic design.
Noise
study required
Blocks 72 and 73, particularly the units
adjacent to
Sufficient
water allocation
On
As endorsed by Council in December 1998, water allocation of 1427 units
was granted to the Berczy Secondary Plan Area to be distributed by the Trustee
of the Developers Group. The subdivision
within which these blocks are located in (Markham Trails) was allocated 607
units by the Developers Group. On
The previous phases (phases 1 and 2) of Markham Trails’ subdivision had
approval for 565 units. Their final phase (Phase 3, within which the subject
blocks are located in) includes 159 units of low density residential, plus the
167 medium density townhouses proposed by Branstone Estates Inc. (Greenpark
Homes). As a result, a total of 891
units are to be developed, while water allocation is available for 907
units. Any remaining unassigned water
allocation should be returned to the Developers Group.
FINANCIAL CONSIDERATIONS:
There are no financial matters to
be considered at this time.
ENVIRONMENTAL CONSIDERATIONS:
The TRCA has no objections to the approval of the zoning by-law
amendment and site plan applications.
They note that they were involved in the review and approval of the
draft plan of subdivision within which these blocks are located. The limits of development were approved as
part of the plan of subdivision approval process, and a minimum 10 metre
environmental buffer conveyed to the Town along with the valley lands.
BUSINESS UNITS CONSULTED AND AFFECTED:
The application has been circulated
to the Town Departments for review and comments. All conditions and requirements received will
be addressed and incorporated in the recommendation report.
|
|
|
Valerie Shuttleworth, M.C.I.P., R.P.P. Director of Planning & Urban Design |
|
Jim
Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
DOCUMENT #: Q:\Development\Planning\APPL\ZONING\04 006288 Markham
Trails (Green Park)\dscmarch23preliminary.doc
ATTACHMENTS: Figure 1 –
Applicant/Agent and Location Map
Figure
2 – Area Context and Zoning
Figure
3 – Air Photo
Figure
4 – Site Plan (Block 72)
Figure
5 – Site Plan (Block 73)
Figure
6 – Site Plan (Block 75)
Figure
7 to 9 – Sample Elevations
APPLICANT/AGENT: Greenpark
Homes (Branstone Estates)
Attn: Frank Principe
L4K
4S6
Tel: (416) 736-4096
Fax: (905) 660-0746