Report to: General Committee Report
Date:
SUBJECT: Award of Tender 060-T-07
Construction of
PREPARED BY: Linda A. Irvine, Manager, Parks and Open Space
Alex Moore, Senior Construction Buyer
RECOMMENDATION:
THAT the report entitled “Award
of Tender 060-T-07, Construction of Orchard View Neighbourhood Park” be
received;
AND THAT
the contract for Tender 060-T-07 for the construction of Orchard View Neighbourhood Park be awarded to the lowest priced bidder, Zuron Construction
Inc in the amount of $405,312.72 exclusive of a $40,531.00 contingency and GST;
AND THAT a
consultant and construction contingency amount of $40,531.00 exclusive of GST,
be established to cover additional consultant/construction costs and that the
Director of
AND
THAT Staff be authorized to
issue a
AND
THAT Staff be authorized to
retain Cosburn Giberson for contract administration services in the amount of
$15,500 on a non-competitive procurement basis pursuant to Purchasing By-law 2004-341,
Part II, Section 7 (1c);
AND
THAT the above be funded from
AND
THAT upon payment of all
invoices associated with this project, any remaining funds will be returned to
the original funding sources.
AND THAT FURTHER staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not Required
1. Purpose 2. Background 3. Discussion 4. Financial
5. Others (Environmental, Accessibility, Engage 21st, Affected Units) 6.
Attachment(s)
The purpose of this report is to award
the contract for the construction of
In
Staff recommends extending the services of
Cosburn Giberson for the next phase of work involving contract administration
services in the amount of $15,500 and that the tendering process be waived in
accordance with Purchasing By-Law 2004-341, Part II, Section 7 Non Competitive
Procurement, item 1 (b) which states “when the extension of an existing
contract would prove more cost-effective or beneficial;”
A Public Information Meeting was held to receive community input, parks concepts were presented to the Building and Parks Construction Committee and the Operations Department has reviewed the plans and provided input on operational matters.
A construction contingency of $40,531.00 has been established to cover any additional and unanticipated design and/or construction costs including authorized contingencies and approved change orders associated with this project.
Upon payment of all invoices associated with
this project, any remaining funds will be returned to the original funding
sources.
The construction tender 060-T-07 was
issued in accordance with the
Total
Estimated Project Costs:
Construction
Cost |
$ 405,312.72 |
Contingency
– Consulting Fees and Construction |
$ 40,531.00 |
Internal
Capital Admin. Fee (2%) |
$ 37,440.00 |
Design
Cost (Cosburn Giberson) |
$ 28,788.76 |
Contract
Admin (Cosburn Giberson) |
$ 15,500.00 |
Total
Project Costs |
$ 527,572.48 |
Total
Budget |
$ 494,400.00 |
Project
Shortfall |
($ 33,172.48) |
Advertised |
ETN |
Bids closed on |
|
Number picking up bid documents |
14 |
Number responding to bid |
9 |
DETAILED
PRICING INFORMATION:
Company |
Prices |
Zuron
Construction Inc |
$405,312.72 |
Gateman-Milloy Inc |
$412,295.57 |
Mopal Construction Ltd |
$425,664.00 |
Pine Valley Enterprises Inc |
$431,107.00 |
|
$460,119.72 |
Hank Deenen |
$474,629.00 |
Royal Crest |
$492,799.80 |
Lomco |
$518,435.00 |
Rand General |
$559,274.05 |
Note: Prices are exclusive of GST
The tender was evaluated
on the selection of the lowest qualified bid. The bids have been verified for
accuracy and compliance with the tender terms and conditions.
PROJECT SCHEDULE:
Subject to Council’s award of this tender, construction of this
project is scheduled to commence
None
None
None
The Finance Department has reviewed this report and their comments have been incorporated.
RECOMMENDED
BY: ________________________
Valerie Shuttleworth, MCIP, RPP
Director,
________________________
Jim Baird, MCIP, RRP
Commissioner, Development Services
None
Q:\Development\Design\linda\Parks\Greensborough (Orchard View) Construction Report May 141.doc